Expediente: NEPR-MI-2021-0003
In Re: Preliminary Studies for New Combined Cycle Power Plant in Palo Seco
Documentos Publicados: 6
Documentos Fecha Orden Descargar
Motion to Submit May 2021 Status Report in Compliance with Order Entered on February 1, 2021 Subject: Motion to Submit May 2021 Status Report 17/mayo/2021 2021/05/17 File
Motion to Substitution of April 2021 Status Report Subject: Motion to Substitution of April 2021 Status Report 16/abril/2021 2021/04/16 File
Motion to Submit April 2021 Monthly Status Report in Compliance with the February 1st, 2021 Resolution and Order Subject: Motion to Submit April 2021 Monthly Status Report in Compliance with the Order 15/abril/2021 2021/04/15 File
Motion in Compliance with Order Entered on February 1, 2021 Subject: Compliance with February 1 Order 16/febrero/2021 2021/02/16 File
Notice of Appearance and Request for Notice Subject: Notice of Appearance on behalf of the Puerto Rico Electric Power Authority 09/febrero/2021 2021/02/09 File
Resolution and Order Subject: Report on Preliminary Studies for New Combined Cycle Power Plan at Palo Seco 01/febrero/2021 2021/02/01 File