Dockets

Docket Number: NEPR-MI-2022-0005
In Re: 10 Year Plan Federally Funded Competitive Processes
Available files: 10
Files Date Orden Download
Resolution and Order Subject: Determination for the Project Application Package for the Seven (7) Additional Peakers to be used as Emergency Generation. January/23/2023 2023/01/23 File
Motion to Submit Responses in Compliance with the January 5 Order Subject: PREPA – Motion to Submit Responses in Compliance with the January 5 Order (Emergency Generation Units) January/09/2023 2023/01/09 File
Resolution and Order Subject: Project Application Package for the Seven (7) Additional Peakers to be used as Emergency Generation. January/05/2023 2023/01/05 File
Memorandum of Law Requesting Confidential Designation and Treatment of the New Emergency Generation Units at Jobos, Daguao and Palo Seco Draft RFP Submitted to the Energy Bureau on December 29, 2022 Subject: Memorandum of Law Requesting Confidential Designation and Treatment of the New Emergency Generation Units at Jobos, Daguao and Palo Seco Draft RFP Submitted to the Energy […] January/05/2023 2023/01/05 File
Motion to Inform Publication of RFP for the New Black Start Systems at Costa Sur and Yabucoa Subject: Motion to Inform Publication of RFP for the New Black Start Systems at Costa Sur and Yabucoa December/23/2022 2022/12/23 File
Resolution and Order Subject: Resolution and Order regarding Motion Requesting Order Related to the RFP Process for the New Black Start Systems at Costa Sur and Yabucoa, filed by the […] December/19/2022 2022/12/19 File
Motion Requesting Order Related to the RFP Process for the New Black Start Systems at Costa Sur and Yabucoa Subject: Motion Requesting Order Related to the RFP Process for the New Black Start Systems at Costa Sur and Yabucoa December/10/2022 2022/12/10 File
Resolution and Order Subject: Resolution and Order regarding Motion Requesting Expedited Approval of the RFP Process for the New Black-Start Systems at Costa Sur and Yabucoa, filed by the Puerto […] December/05/2022 2022/12/05 File
Motion Requesting Expedited Approval of the RFP Process for the New Black-Start Systems at Costa Sur and Yabucoa Subject: Motion Requesting Expedited Approval of the RFP Process for the New Black-Start Systems at Costa Sur and Yabucoa November/23/2022 2022/11/23 File
Memorandum of Law Requesting Confidential Designation and Treatment of the Black-Start Systems Draft RFP Submitted to the Energy Bureau in November 10, 2022  Subject: Memorandum of Law Requesting Confidential Designation and Treatment of the Black-Start Systems Draft RFP Submitted to the Energy Bureau in November 10, 2022 November/15/2022 2022/11/15 File