Dockets

Docket Number: NEPR-MI-2022-0003
LUMA's Response to Hurricane Fiona
Available files: 87
Files Date Orden Download
Notice of Withdrawal as Attorney of Record Subject: IN RE: LUMA’S Response to Hurricane Fiona October/25/2024 2024/10/25 File
Resolution and Order Subject: Resolution and Order in response to the Motion in Compliance with the March 15th Resolution and Order filed by the Puerto Rico Electric Power Authority. March/15/2024 2024/03/15 File
Motion in compliance with the March 15th Resolution and Order Subject: Motion in compliance with the March 15th Resolution and Order March/15/2024 2024/03/15 File
Motion in compliance with the March 15th Resolution and Order Subject: Exhibits 1-4 March/15/2024 2024/03/15 File
Urgent Motion in Compliance with the March 15th Resolution and Order Subject: Urgent Motion in Compliance with the March 15th Resolution and Order March/15/2024 2024/03/15 File
Resolution and Order Subject: Resolution and Order regarding Urgent Information Motion, filed by the Puerto Rico Electric Power Authority. March/15/2024 2024/03/15 File
Resolution and Order Subject: Resolution and Order pertaining to the Motion Submitting Fourth Report on Demobilization of FEMA Generation and Request to Release LUMA from the Requirement to File Bi-Weekly […] March/14/2024 2024/03/14 File
Urgent Informative Motion Subject: Urgent Informative Motion March/13/2024 2024/03/13 File
Resolution and Order Subject: Resolution and Order regarding Urgent Motion In Compliance with Resolution and Order, filed by the Puerto Rico Electric Power Authority. March/08/2024 2024/03/08 File
Urgent Motion in Compliance with Resolution and Order Subject: Urgent Motion in Compliance with Resolution and Order March/06/2024 2024/03/06 File
Resolution and Order Subject: Resolution and Order pertaining to the Reinitiation of System Status Daily Updates. February/26/2024 2024/02/26 File
Motion to Clarify the February 17th Informative Motion Subject: Motion to Clarify the February 17th Informative Motion February/22/2024 2024/02/22 File
Resolution and Order Subject: Resolution and Order regarding Informative Motion and in Compliance with the February 14th Resolution and Order and Urgent Motion Submitting for Review and Approval of the […] February/21/2024 2024/02/21 File
Informative Motion and in Compliance with The February 14th Resolution and Order Subject: Informative Motion and in Compliance with The February 14th Resolution and Order February/17/2024 2024/02/17 File
Motion Submitting Fourth Report on Demobilization of FEMA Generation and Request to Release LUMA from the Requirement to File Bi-Weekly Demobilization Reports Subject: Fourth Report on Demobilization of FEMA Generation and Request to Release LUMA from the Requirement to File Bi-Weekly Demobilization Reports February/15/2024 2024/02/15 File
Resolution and Order Subject: Resolution and Order regarding Memorandum of Law in Support of Request for Confidentiality of Documents Submitted Under Seal with the January 14th and January 22nd Motions, […] February/14/2024 2024/02/14 File
Memorandum of Law in Support of Request for Confidentiality of Documents Submitted Under Seal with the January 14th and January 22nd Motions Subject: Motion Submitting for Review and Approval the Scope of Work for the Transfer Ownership to PREPA of Temporary Generation Units February/09/2024 2024/02/09 File
Resolution and Order Subject: Resolution and Order regarding Motion for Extension of Time to Comply with January 26th Resolution, filed by the Puerto Rico Electric Power Authority. February/07/2024 2024/02/07 File
Motion for Extension of Time to Comply with January 26 Resolution Subject: Motion for Extension of Time to Comply with January 26 Resolution February/02/2024 2024/02/02 File
Second Motion in Compliance with the January 19, 2024 Resolution and Order Subject: Motion submitting for review and approval the Scope of Work for the Transfer Ownership to PREPA of Temporary Generation Units February/02/2024 2024/02/02 File
Informative Motion on LUMA’s Compliance with Resolution and Order dated January 19, 2024 Subject: Informative Motion on LUMA’s Compliance with Resolution and Order dated January 19, 2024 February/02/2024 2024/02/02 File
Motion Submitting Third Report on Demobilization of FEMA Generation  Subject: Third Report on Demobilization of FEMA Generation February/01/2024 2024/02/01 File
Resolution and Order Subject: Resolution and Order regarding Urgent Motion Submitting for Review and Approval of the Scope of Work for the Transfer/Ownership to PREPA of the Temporary Generation Units […] January/26/2024 2024/01/26 File
Motion Submitting Updated Version of the Second Report on Demobilization of FEMA Generation, in Compliance with Resolution and Order Dated January 19, 2024 Subject: Motion Submitting Updated Version of the Second Report on Demobilization of FEMA Generation, in Compliance with Resolution and Order Dated January 19, 2024 January/26/2024 2024/01/26 File
Informative Motion on Updated Version of the Second Report on Demobilization of FEMA Generation in Compliance with Resolution and Order Dated January 19, 2024. Subject: Informative Motion on Updated Version of the Second Report on Demobilization of FEMA Generation January/26/2024 2024/01/26 File
Motion in Compliance with the January 19th, 2024 Resolution and Order Subject: Motion Submitting for Review and Approval the Scope of Work for the Transfer Onwership to PREPA of Temporary Generation Units. January/22/2024 2024/01/22 File
Resolution and Order Subject: Resolution and Order regarding Urgent Motion Submitting for Review and Approval of the Scope of Work for the Transfer/Ownership to PREPA of the Temporary Generation Units, […] January/19/2024 2024/01/19 File
Motion Submitting Second Report on Demobilization of FEMA Generation in Compliance with Resolution and Order Dated November 14 2023 Subject: Second Report on Dembolization of FEMA generation January/16/2024 2024/01/16 File
Urgent Motion Submitting for Review and Approval the Scope of Work for the Transfer/Ownership to PREPA of the Temporary Generation Units  Subject: Motion Submitting for Review and Approval the Scope of Work for the Transfer/Ownership to PREPA of the Temporary Generation Units January/14/2024 2024/01/14 File
Urgent Motion Submitting for Review and Approval the Scope of Work for the Transfer/Ownership to PREPA of the Temporary Generation Units Subject: Exhibit 9 – CC Ltr to COR3 January/14/2024 2024/01/14 File
Urgent Motion Submitting for Review and Approval the Scope of Work for the Transfer/Ownership to PREPA of the Temporary Generation Units Subject: Exhibit 4 – COR3 Letter to FEMA- Acquisition of Temporary Generators for the Stabilization of Power Grid January/14/2024 2024/01/14 File
Urgent Motion Submitting for Review and Approval the Scope of Work for the Transfer/Ownership to PREPA of the Temporary Generation Units Subject: Exhibit 3 – COR3 Letter to FEMA Re DFA Power Stabilization January/14/2024 2024/01/14 File
Urgent Motion Submitting for Review and Approval the Scope of Work for the Transfer/Ownership to PREPA of the Temporary Generation Units Subject: Exhibit 2 – October 16, 2023 – Letter from FEMA to COR3 – DFA Power Stabilization January/14/2024 2024/01/14 File
Notice of Withdrawal as Attorney of Record  Subject: Notice of Withdrawal as Attorney of Record January/08/2024 2024/01/08 File
Notice of Withdrawal as Attorney of Record  Subject: Notice of Withdrawal as Attorney of Record January/08/2024 2024/01/08 File
Resolution and Order Subject: Report on Puerto Rico’s Path to Stabilization and Request for Extension to File Update to the Report. December/20/2023 2023/12/20 File
Motion Submitting First Decommissioning Report in Compliance with Resolution and Order Dated November 14, 2023 and Request for Extension to File Update to the Report Subject: Report on Puerto Rico’s Path to Stabilization and Request for Extension to File Update to the Report December/18/2023 2023/12/18 File
Motion Submitting Report Titled “Puerto Rico’s Path to Power Stabilization Subject: Report on Puerto Rico’s Path to Power Stabilization December/15/2023 2023/12/15 File
Resolution and Order Subject: Resolution and Order pertaining to Motion Submitting Final Update on Stabilization Plan for Temporary Emergency Generation Capacity, Request for Confidential Treatment of Portions Thereof and Request […] November/14/2023 2023/11/14 File
Genera PR- PSD Temporary Emissions Permit Subject: PSD Temporary Emissions Permit; In Re; LUMA’s Response to Hurricane Fiona No. NEPR-MI-222-0003 November/06/2023 2023/11/06 File
Motion Submitting Final Update on Stabilization Plan for Temporary Emergency Generation Capacity, Request for Confidential Treatment of Portions Thereof and Request for Release from Requirement to File BI-Weekly Reports Subject: Final Update on Stabilization Plan,  Request for Confidential Treatment of Portions Thereof and Request for Release from Requirement to File BI-Weekly Reports November/01/2023 2023/11/01 File
Motion Submitting Twenty-Third Update on Stabilization Plan for Temporary Emergency Generation Capacity, Request for Confidential Treatment of Portions Thereof and Request for Release from Filing Bi-Weekly Reports Subject: Motion Submitting Twenty-Third Update on Stabilization Plan for Temporary Emergency Generation Capacity, Request for Confidential Treatment of Portions Thereof and Request for Release from Filing Bi-Weekly […] October/16/2023 2023/10/16 File
Notice of Withdrawal as Attorney of Record Subject: Notice of Withdrawal as Attorney of Record October/10/2023 2023/10/10 File
Motion Submitting Twenty-Second Update on Stabilization Plan for Temporary Emergency Generation Capacity and Request for Confidential Treatment of Portions Thereof Subject: Twenty-Second Update on Stabilization Plan and Request for Confidential Treatment of Portions Thereof October/02/2023 2023/10/02 File
Motion Submitting Twenty-First Update on Stabilization Plan for Temporary Emergency Generation Capacity and Request for Confidential Treatment of Portions Thereof Subject: Motion Submitting Twenty-First Update on Stabilization Plan for Temporary Emergency Generation Capacity and Request for Confidential Treatment of Portions Thereof September/15/2023 2023/09/15 File
Motion Submitting Twentieth Update on Stabilization Plan for Temporary Emergency Generation Capacity and Request for Confidential Treatment of Portions Thereof Subject: Motion Submitting Twentieth Update on Stabilization Plan for Temporary Emergency Generation Capacity and Request for Confidential Treatment of Portions Thereof September/01/2023 2023/09/01 File
Motion Submitting Nineteenth Update on Stabilization Plan for Temporary Emergency Generation Capacity and Request for Confidential Treatment of Portions Thereof Subject: Nineteenth Update on Stabilization Plan for Temporary Emergency Generation Capacity and Request for Confidential Treatment of Portions Thereof August/15/2023 2023/08/15 File
Motion Submitting Eighteenth Update on Stabilization Plan for Temporary Emergency Generation Capacity and Request for Confidential Treatment of Portion Thereof Subject: Eighteenth Update on Stabilization Plan and Request for Confidential Treatment of Portion Thereof August/01/2023 2023/08/01 File
Motion Submitting Seventeenth Update on Stabilization Plan for Temporary Emergency Generation Capacity and Request for Confidential Treatment of Portion Thereof Subject: Seventeenth Update on Stabilization Plan for Temporary Emergency Generation Capacity and Request for Confidential Treatment of Portion Thereof July/17/2023 2023/07/17 File
Resolution and Order Subject: LUMA’s Update on Stabilization Plan and Request for Confidential Treatment of Portions Thereof. July/12/2023 2023/07/12 File
Motion Submitting Sixteenth Update on Stabilization Plan for Temporary Emergency Generation Capacity and Request for Confidential Treatment of Portion Thereof Subject: Sixteenth Update on Stabilization Plan and Request for Confidential Treatment of Portion Thereof July/03/2023 2023/07/03 File
Resolution and Order Subject: LUMA’s Updates on Stabilization Plan and Request for Confidential Treatment. June/30/2023 2023/06/30 File
Motion Submitting Fifteenth Update on Stabilization Plan for Temporary Emergency Generation Capacity and Request for Confidential Treatment of Portions Thereof Subject: Motion Submitting Fifteenth Update on Stabilization Plan for Temporary Emergency Generation Capacity and Request for Confidential Treatment of Portions Thereof June/15/2023 2023/06/15 File
Motion Submitting Fourteenth Update on Stabilization Plan for Temporary Emergency Generation Capacity and Request for Confidential Treatment of Portion Thereof Subject: Motion Submitting Fourteenth Update on Stabilization Plan for Temporary Emergency Generation Capacity and Request for Confidential Treatment of Portion Thereof June/01/2023 2023/06/01 File
Motion Submitting Thirteenth Update on Stabilization Plan for Temporary Emergency Generation Capacity and Request for Confidential Treatment of Portions Thereof Subject: Motion Submitting Thirteenth Update on Stabilization Plan for Temporary Emergency Generation Capacity and Request for Confidential Treatment of Portions Thereof May/15/2023 2023/05/15 File
Motion Submitting Twelfth Update on Stabilization Plan for Temporary Emergency Generation Capacity and Request for Confidential Treatment of Portions Thereof Subject: Motion Submitting Twelfth Update on Stabilization Plan for Temporary Emergency Generation Capacity and Request for Confidential Treatment of Portions Thereof May/01/2023 2023/05/01 File
Motion Submitting Eleventh Update on Stabilization Plan for Temporary Generation Capacity and Request for Confidential Treatment Subject: Motion Submitting Eleventh Update on Stabilization Plan for Temporary Generation Capacity and Request for Confidential Treatment April/17/2023 2023/04/17 File
Memorandum of Law in Support of Confidential Treatment of Certain Portions of Exhibit 1 to Tenth Update on Stabilization Plan Subject: Memorandum of Law in Support of Confidential Treatment of Certain Portions of Exhibit 1 to Tenth Update on Stabilization Plan April/12/2023 2023/04/12 File
Motion Submitting Tenth Update on Stabilization Plan Subject: Motion Submitting Tenth Update on Stabilization Plan for Temporary Emergency Generation Capacity April/03/2023 2023/04/03 File
Motion Submitting Ninth Update on Stabilization Plan for Temporary Emergency Generation Capacity Subject: Motion Submitting Ninth Update on Stabilization Plan March/15/2023 2023/03/15 File
Motion Submitting Eight Update on Stabilization Plan for Temporary Emergency Generation Capacity Subject: Motion Submitting Eight Update on Stabilization Plan March/01/2023 2023/03/01 File
Notice of Withdrawal of Attorney of Record Subject: Notice of Withdrawal of Attorney of Record February/15/2023 2023/02/15 File
Motion Submitting Seventh Update on Generation Stabilization Plan for Temporary Emergency Generation Capacity Subject: Motion Submitting Seventh Update on Generation Stabilization Plan February/15/2023 2023/02/15 File
Motion Submitting Sixth Update on Stabilization Plan for Temporary Emergency Generation Capacity Subject: Motion Submitting Sixth Update on Stabilization Plan for Temporary Emergency Generation Capacity February/01/2023 2023/02/01 File
Motion Submitting Sixth Update on Stabilization Plan for Temporary Emergency Generation Capacity Subject: Motion Submitting Sixth Update on Stabilization Plan February/01/2023 2023/02/01 File
Fifth Update on Stabilization Plan for Temporary Emergency Generation Capacity Subject: Fifth Update on Stabilization January/17/2023 2023/01/17 File
Resolution and Order Subject: LUMA’s Fourth Update on Stabilization Plan and Request to Release LUMA from the Requirement to File an Update on January 2, 2023. December/21/2022 2022/12/21 File
Fourth Update on Stabilization Plan for Temporary Emergency Generation Capacity and Request to Release LUMA from the Requirement to File an Update on January 2, 2023 Subject: Fourth Update on Stabilization Plan and Request to Release LUMA from the Requirement to File an Update on January 2, 2023 December/15/2022 2022/12/15 File
Fourth Update on Stabilization Plan for Temporary Emergency Generation Capacity and Request to Release LUMA from the Requirement to File and Update on January 2, 2023 Subject: Fourth Update on Stabilization Plan for Temporary Emergency Generation Capacity and Request to Release LUMA from the Requirement to File and Update on January 2, 2023 December/15/2022 2022/12/15 File
Third Update on Stabilization Plan for Temporary Emergency Generation Capacity Subject: Third Update on Stabilization Plan December/01/2022 2022/12/01 File
LUMA’s Responses to Requirements of Information on LUMA’s Response to Hurricane Fiona Subject: RFI-LUMA-MI-2022-0003-20221118-PREB-C001_Attachment 1 November/18/2022 2022/11/18 File
LUMA’s Responses to Requirements of Information on LUMA’s Response to Hurricane Fiona Subject: EXHIBIT 1 LUMA Response to Hurricane Fiona RFIs November/18/2022 2022/11/18 File
LUMA’s Responses to Requirements of Information on LUMA’s Response to Hurricane Fiona Subject: Responses to Requirements of Information November/18/2022 2022/11/18 File
Supplemental Submission to Second Update on Stabilization Plan to Inform of Announcement by Puerto Rico Government and FEMA on Temporary Emergency Generation Capacity Subject: Supplemental Submission to Second Update on Stabilization Plan November/15/2022 2022/11/15 File
Motion Submitting Second Update on Stabilization Plan Subject: Exhibit 1 Second Update to Stabilization Plan – NEPR-MI-2022-0003 November/15/2022 2022/11/15 File
Motion Submitting Second Update on Stabilization Plan Subject: Motion Submitting Second Update on Stabilization Plan November/15/2022 2022/11/15 File
Motion Submitting Update on Stabilization Plan Subject: Submission of Update Stabilization Plan October/31/2022 2022/10/31 File
Motion Submitting Supplemental Information in Attention to Questions Posed in Technical Conference of October 11, 2022 Subject: Submission of Supplemental Information October/31/2022 2022/10/31 File
Resolution and Order Subject: Initial Generation Stabilization Plan (“GSP”) Update – Scheduling of Technical Conference October/27/2022 2022/10/27 File
Resolution and Order Subject: Requirement of Information (“ROl”) – Review of LUMA’s Response to Hurricane Fiona October/25/2022 2022/10/25 File
Notice of Appearance and Request for Notice Subject: Notice of Appearance and Request for Notice October/14/2022 2022/10/14 File
Resolution and Order Subject: LUMA to prepare a stabilization plan, in coordination with PREPA and FEMA, regarding the inadequacy of dispatch of Baseload Generation to avoid load shedding events due […] October/12/2022 2022/10/12 File
Motion Submitting Presentation Offered in Technical Conference of October 11, 2022 Subject: Presentation Offered in Technical Conference of October 11, 2022 October/11/2022 2022/10/11 File
Motion Submitting Presentation Offered in Technical Conference of October 11, 2022 Subject: Presentation Offered in Technical Conference of October 11, 2022 October/11/2022 2022/10/11 File
Resolution and Order Subject: Baseload Generation Dispatch Status – Post-Hurricane Fiona October/07/2022 2022/10/07 File
Carta al Negociado de Energía Subject: Risk Assessment of the Puerto Rico Electric Grid Following Hurricane Fiona October/06/2022 2022/10/06 File
Notice on Preliminary Damage Assessment in Response to Hurricane Fiona Subject: Notice on Preliminary Damage Assessment in Response to Hurricane Fiona September/23/2022 2022/09/23 File

Antonio Torres-Miranda is presently an Associate Commissioner for the Energy Bureau of the Puerto Rico Public Service Regulatory Board (Energy Bureau). Previously, Mr. Torres had been the Director of the Legal Advisory Division of the Energy Bureau.

Mr. Torres has a bachelor’s degree in mechanical engineering from the University of Puerto Rico. He also has a master’s degree in engineering management from the Polytechnical University of Puerto Rico. In the 1990’s he passed the exam to be a Certified Energy Manager. He is presently a member of the Puerto Rico Professional College of Engineer and Land Surveyors.

Mr. Torres graduated with honors from the Interamerican University of Puerto Rico where he obtained his Juris Doctor degree. He is presently member of the bar of the Commonwealth of Puerto Rico and is a member of the U.S. District of Puerto Rico Federal bar.

He commenced his engineering work experience with the Department of Defense in a Naval base in Virginia were he designed industrial ventilation systems. He then went to New York to work with Kennetech Energy Management were he first commenced being immersed in the energy sector. He then transferred to Puerto Rico with Kennetech in which he conducted wind studies throughout the island together with U.S. Wind Power. He continued implementation of energy management systems in several industrial companies throughout Puerto Rico until Kennetech joined forces with Enron to develop the first privately owned power plant in Puerto Rico known as EcoElectrica. This 450 MW natural gas power plant included the development of the first LNG terminal in Puerto Rico.

He also worked as a contractor with the Puerto Rico Electric Power Authority in the development of a 42 miles natural gas pipeline.

Before joining the Energy Bureau Mr. Torres developed several natural gas projects in Puerto Rico.

Ferdinand Ramos-Soegaard attained a bachelor’s degree in electrical engineering (BSEE) graduating from the Georgia Institute of Technology in Atlanta, GA in 2000. His degree specialized in power distribution and telecommunications systems.

Mr. Ramos-Soegaard is a licensed professional engineer in the Commonwealth of Puerto Rico and the state of Florida. Throughout his professional carrier Mr. Ramos has been involved in all aspects of the design, construction and maintenance of electrical distribution systems, including high voltage transmission lines and renewable energy interconnections to the Puerto Rico Electric Power Authority subtransmission grid.

Sylvia B. Ugarte Araujo holds a bachelor’s degree in industrial and Systems Engineering from the University of Florida (1998). She studied at the Inter-American University of Puerto Rico School of Law (2004) and then obtained a Master of Laws from the Inter-American University of Puerto Rico (2019). Ms. Ugarte is admitted to the practice of law and notary by the Supreme Court of Puerto Rico (2004), the Federal Court for the District of Puerto Rico, for the First Circuit of Boston (2005), the Court of Appeals of the First Circuit (2005) and the Supreme Court of Texas (2018). She was Director of the Office of Legal Counsel of the Energy Bureau of the Public Service Regulatory Board and the Designated Director of the Office of Legal Counsel of the Public Service Regulatory Board. She has served as Legal Director of the Puerto Rico Infrastructure Financing Authority and has worked with renowned law firms. She has over fifteen (15) years of vast professional experience as a trial attorney with an emphasis on commercial and construction litigation and extensive experience in administrative law. Also, as an industrial engineer she has been a consultant for government agencies in charge of large projects and in private entities.

Lillian Mateo-Santos obtained her Bachelor’s Degree in Business Administration from the University of Puerto Rico, Río Piedras Campus, in 1993 and a Juris Doctor degree from the University of Puerto Rico School of Law in 1996. In 1999, she obtained a degree of Masters of Laws (LLM) in Environmental and Energy of the Tulane University Law School. Before joining the Puerto Rico Energy Bureau, Ms. Mateo-Santos was a member of various law firms. Her private practice was focused on energy, environmental, land use and permitting matters, including administrative law litigation.

On June 5, 2019, Ms. Mateo-Santos was elected 2nd Vice President of the Southeastern Association of Regulatory Utility Commissioners (SEARUC). She is a member of the American Bar Association and is admitted to practice law and notary law in Puerto Rico, and the United States Court of Appeals for the First Circuit.

Edison Avilés-Deliz obtained his Bachelor of Science in Electrical Engineering with specialties in Power and Control Systems (BSEE) Cum Laude from the University of Puerto Rico, Mayagüez Campus in 1991 and a Juris Doctor (JD) also Cum Laude from the University of Puerto Rico School of Law in 1997. In addition, he holds Master degrees with Distinctions in Diplomacy/International Relations/Business (MA) from Norwich University in Vermont and in Energy Law from Vermont Law School (LLM).

Avilés-Deliz is a licensed engineer and member of the College of Engineers and Surveyors of Puerto Rico (CIAPR). He was president of the Disciplinary and Professional Ethics Tribunal of the CIAPR, of the Institute of Electrical Engineers of CIAPR and of the Society of Electrical Engineers of Puerto Rico. He is admitted to practice as a public notary in Puerto Rico and as a lawyer, both in the District Court of Puerto Rico and the Court of Appeals for the First Federal Circuit.

He is a member of Phi Eta Mu Fraternity, the Engineering Honor Society Tau Beta Pi, and the International Studies Honor Society Sigma Iota Rho. He is also a Senior member of the IEEE.

Antonio Torres-Miranda es actualmente Comisionado Asociado del Negociado de Energía de la Junta Reglamentadora de Servicios Públicos de Puerto Rico (Negociado de Energía). Anteriormente, el Sr. Torres había sido Director de la División de Asesoría Legal del Negociado de Energía.

El Sr. Torres tiene un bachillerato en ingeniería mecánica de la Universidad de Puerto Rico. También tiene una maestría en administración de ingeniería de la Universidad Politécnica de Puerto Rico. En la década de 1990 aprobó el examen para ser Gerente de Energía Certificado. Actualmente es miembro del Colegio de Ingenieros y Agrimensores de Puerto Rico.

El Sr. Torres se graduó con honores de la Universidad Interamericana de Puerto Rico donde obtuvo su título de Juris Doctor (JD). Actualmente es miembro del Colegio de Abogados del Estado de Puerto Rico y es miembro del Colegio de Abogados Federal del Distrito de Puerto Rico de los Estados Unidos.

Comenzó su experiencia laboral en ingeniería con el Departamento de Defensa en una base naval en Virginia donde diseñó sistemas de ventilación industrial. Luego se fue a Nueva York para trabajar con Kennetech Energy Management, donde comenzó a sumergirse en el sector energético. Luego se transfirió a Puerto Rico con Kennetech, donde realizó estudios eólicos en toda la isla U.S. Wind Power. Continuó con la implementación de sistemas de administración de energía en varias empresas industriales en todo Puerto Rico hasta que Kennetech unió fuerzas con Enron para desarrollar la primera planta de energía de propiedad privada en Puerto Rico conocida como EcoEléctrica. Esta planta de energía de gas natural de 450 MW incluyó el desarrollo de la primera terminal de GNL en Puerto Rico.

También trabajó como contratista con la Autoridad de Energía Eléctrica de Puerto Rico en el desarrollo de una tubería de gas natural de 42 millas.

Antes de unirse al Negociado de Energía, el Sr. Torres desarrolló varios proyectos de gas natural en Puerto Rico.

La Lcda. Sylvia B. Ugarte Araujo posee un Bachillerato en Ingeniería Industrial y de Sistemas de la Universidad de la Florida (1998). Estudió en la Escuela de Derecho de la Universidad Interamericana de Puerto Rico (2004) y luego obtuvo una Maestría en Derecho de la Universidad Interamericana de Puerto Rico (2019). La Lcda. Ugarte está admitida a la práctica de la abogacía y la notaría por el Tribunal Supremo de Puerto Rico (2004), al Tribunal Federal, Distrito de Puerto Rico, al Primer Circuito Federal de Boston (2005), al Tribunal de Apelaciones del Primer Circuito (2005) y al Tribunal Supremo de la jurisdicción del estado de Texas (2018). Fue Directora de la Oficina de Asesoramiento Legal del Negociado de Energía de la Junta Reglamentadora de Servicio Público y la Directora Designada de la Oficina de Asesoramiento Legal de la Junta Reglamentadora de Servicio Público. Ha ejercido como Directora Legal de la Autoridad para el Financiamiento de la Infraestructura de Puerto Rico y ha trabajado con bufetes de abogado de renombre. Tiene sobre quince (15) años de vasta experiencia profesional como abogada litigante con énfasis en litigio comercial y construcción y una amplia experiencia en derecho administrativo. Así también, como ingeniera industrial ha sido consultora para agencias gubernamentales encargadas de proyectos de envergadura y en entidades privadas.

Ferdinand A. Ramos-Soegaard obtuvo su Bachillerato en Ciencias en Ingeniería Eléctrica (BSEE, por sus siglas en inglés) del Georgia Institute of Technology en Atlanta, GA en el 2000, con especialidad en sistemas de distribución de potencia y telecomunicaciones.

Ramos-Soegaard es ingeniero licenciado en el Estado Libre Asociado de Puerto Rico y en el Estado de Florida. A través de su carrera profesional, Ramos-Soegaard ha estado envuelto en todos los aspectos del diseño, construcción y mantenimiento de sistemas de distribución eléctrica, incluyendo líneas de transmisión de alto voltaje e interconexiones de sistemas de energía renovable a la red de subtransmisión de la Autoridad de Energía Eléctrica de Puerto Rico.

Lillian Mateo-Santos obtuvo su Bachillerato en Administración de Empresas de la Universidad de Puerto Rico, Recinto de Río Piedras en 1993 y el grado de Juris Doctor de la Facultad de Derecho de la Universidad de Puerto Rico en 1996. En 1999 obtuvo una Maestría en Derecho (LLM) en Ambiental y Energía de la Facultad de Derecho de la Universidad de Tulane. Antes de formar parte del Negociado de Energía de Puerto Rico, la Lic. Mateo-Santos fue miembro de varios bufetes de abogados. Su práctica privada se enfocó en asuntos de energía, ambiental, uso de terrenos y permisos, incluyendo litigación de derecho administrativo.

El 5 de junio de 2019, la Lic. Mateo-Santos fue elegida 2nda Vice Presidenta del Southern Association of Regulatory Utility Commissioners (SEARUC). Es miembro de la American Bar Association y está admitida para ejercer como abogado y notario público en Puerto Rico, y en el Tribunal de Apelaciones para el Primer Circuito Federal.

Edison Avilés-Deliz obtuvo su bachillerato Cum Laude en Ingeniería Eléctrica con especialidades en Sistemas de Controles y Potencia (BSEE) de la Universidad de Puerto Rico, Recinto de Mayagüez en 1991 y un Juris Doctor (JD) también Cum Laude de la Facultad de Derecho de la Universidad de Puerto Rico en 1997. Además, ostenta maestrías con Distinciones en Diplomacia/Relaciones Internacionales/Negocios (MA) de la Universidad de Norwich en Vermont y en Derecho en Energía de la Universidad de Derecho de Vermont (LLM).

Avilés-Deliz es ingeniero licenciado y miembro del Colegio de Ingenieros y Agrimensores de Puerto Rico (CIAPR). Fue presidente del Tribunal Disciplinario y de Ética Profesional del CIAPR, del Instituto de Ingenieros Electricistas del CIAPR y de la Sociedad de Ingenieros Electricistas de Puerto Rico. Está admitido para ejercer como notario público en Puerto Rico y como abogado, tanto en el Tribunal de Distrito de Puerto Rico como el Tribunal de Apelaciones para el Primer Circuito Federal.

Pertenece a la fraternidad Phi Eta Mu, a la Sociedad de Honor de Ingeniería Tau Beta Pi, a la Sociedad de Honor de Estudios Internacionales Sigma Iota Rho. También es miembro senior de la IEEE.