Docket Number: NEPR-MI-2022-0003
LUMA's Response to Hurricane FionaAvailable files: 28
Files | Date | Download |
---|---|---|
Motion Submitting Ninth Update on Stabilization Plan for Temporary Emergency Generation Capacity Subject: Motion Submitting Ninth Update on Stabilization Plan | March/15/2023 | File |
Motion Submitting Eight Update on Stabilization Plan for Temporary Emergency Generation Capacity Subject: Motion Submitting Eight Update on Stabilization Plan | March/01/2023 | File |
Notice of Withdrawal of Attorney of Record Subject: Notice of Withdrawal of Attorney of Record | February/15/2023 | File |
Motion Submitting Seventh Update on Generation Stabilization Plan for Temporary Emergency Generation Capacity Subject: Motion Submitting Seventh Update on Generation Stabilization Plan | February/15/2023 | File |
Motion Submitting Sixth Update on Stabilization Plan for Temporary Emergency Generation Capacity Subject: Motion Submitting Sixth Update on Stabilization Plan for Temporary Emergency Generation Capacity | February/01/2023 | File |
Motion Submitting Sixth Update on Stabilization Plan for Temporary Emergency Generation Capacity Subject: Motion Submitting Sixth Update on Stabilization Plan | February/01/2023 | File |
Fifth Update on Stabilization Plan for Temporary Emergency Generation Capacity Subject: Fifth Update on Stabilization | January/17/2023 | File |
Resolution and Order Subject: LUMA’s Fourth Update on Stabilization Plan and Request to Release LUMA from the Requirement to File an Update on January 2, 2023. | December/21/2022 | File |
Fourth Update on Stabilization Plan for Temporary Emergency Generation Capacity and Request to Release LUMA from the Requirement to File an Update on January 2, 2023 Subject: Fourth Update on Stabilization Plan and Request to Release LUMA from the Requirement to File an Update on January 2, 2023 | December/15/2022 | File |
Fourth Update on Stabilization Plan for Temporary Emergency Generation Capacity and Request to Release LUMA from the Requirement to File and Update on January 2, 2023 Subject: Fourth Update on Stabilization Plan for Temporary Emergency Generation Capacity and Request to Release LUMA from the Requirement to File and Update on January 2, 2023 | December/15/2022 | File |
Third Update on Stabilization Plan for Temporary Emergency Generation Capacity Subject: Third Update on Stabilization Plan | December/01/2022 | File |
LUMA’s Responses to Requirements of Information on LUMA’s Response to Hurricane Fiona Subject: RFI-LUMA-MI-2022-0003-20221118-PREB-C001_Attachment 1 | November/18/2022 | File |
LUMA’s Responses to Requirements of Information on LUMA’s Response to Hurricane Fiona Subject: EXHIBIT 1 LUMA Response to Hurricane Fiona RFIs | November/18/2022 | File |
LUMA’s Responses to Requirements of Information on LUMA’s Response to Hurricane Fiona Subject: Responses to Requirements of Information | November/18/2022 | File |
Supplemental Submission to Second Update on Stabilization Plan to Inform of Announcement by Puerto Rico Government and FEMA on Temporary Emergency Generation Capacity Subject: Supplemental Submission to Second Update on Stabilization Plan | November/15/2022 | File |
Motion Submitting Second Update on Stabilization Plan Subject: Exhibit 1 Second Update to Stabilization Plan – NEPR-MI-2022-0003 | November/15/2022 | File |
Motion Submitting Second Update on Stabilization Plan Subject: Motion Submitting Second Update on Stabilization Plan | November/15/2022 | File |
Motion Submitting Update on Stabilization Plan Subject: Submission of Update Stabilization Plan | October/31/2022 | File |
Motion Submitting Supplemental Information in Attention to Questions Posed in Technical Conference of October 11, 2022 Subject: Submission of Supplemental Information | October/31/2022 | File |
Resolution and Order Subject: Initial Generation Stabilization Plan (“GSP”) Update – Scheduling of Technical Conference | October/27/2022 | File |
Resolution and Order Subject: Requirement of Information (“ROl”) – Review of LUMA’s Response to Hurricane Fiona | October/25/2022 | File |
Notice of Appearance and Request for Notice Subject: Notice of Appearance and Request for Notice | October/14/2022 | File |
Resolution and Order Subject: LUMA to prepare a stabilization plan, in coordination with PREPA and FEMA, regarding the inadequacy of dispatch of Baseload Generation to avoid load shedding events due […] | October/12/2022 | File |
Motion Submitting Presentation Offered in Technical Conference of October 11, 2022 Subject: Presentation Offered in Technical Conference of October 11, 2022 | October/11/2022 | File |
Motion Submitting Presentation Offered in Technical Conference of October 11, 2022 Subject: Presentation Offered in Technical Conference of October 11, 2022 | October/11/2022 | File |
Resolution and Order Subject: Baseload Generation Dispatch Status – Post-Hurricane Fiona | October/07/2022 | File |
Carta al Negociado de Energía Subject: Risk Assessment of the Puerto Rico Electric Grid Following Hurricane Fiona | October/06/2022 | File |
Notice on Preliminary Damage Assessment in Response to Hurricane Fiona Subject: Notice on Preliminary Damage Assessment in Response to Hurricane Fiona | September/23/2022 | File |