Asociación de Productores de Energía Renovable – Aclaración R&O 20231106 Subject: Asociación de Productores de Energía Renovable  (APER)- Aclaración R&O 20231106 15/enero/2025 2025/01/15 File
Motion to Submit an Amendment for Review of YFN Yabucoa Solar, LLC’s PPOA by Energy Bureau Subject: PREPA – Motion to Submit an Amendment for Review of YFN Yabucoa Solar, LLC’s PPOA by Energy Bureau 04/enero/2025 2025/01/04 File
Resolution and Order Subject: Renewable Energy Generation and Energy Storage Resource Procurement Plan – fourth Tranche Project Approval 30/diciembre/2024 2024/12/30 File
Motion to Submit the Report of the Selection Committee’s Evaluation of the Tranche 4 Renewable Energy and Energy Storage Solicitation Subject: IN RE: Implementation of the Puerto Rico Electric Power Authority Integrated Resource Plan and Modified Action Plan 26/diciembre/2024 2024/12/26 File
Resolution Subject: Request of Amendments of Covergent Coamo Energy Storage 1, LLC; Covergent Ponce Energy Storage 1, LLC; Covergent Peñuelas Energy Storage 1, LLC; Covergent Caguas Energy Storage […] 20/diciembre/2024 2024/12/20 File
Resolution Subject: Approval of two additional energy storage service agreements (ESSAs) 20/diciembre/2024 2024/12/20 File
Motion in Compliance with the December 13th Resolution and Order Subject: IN RE: Implementation of the Puerto Rico Electric Power Authority Integrated Resource Plan and Modified Action Plan 20/diciembre/2024 2024/12/20 File
Resolution and Order Subject: Request of Amendments of Convergent Coamo Energy Storage 1, LLC; Convergent Ponce Energy Storage 1, LLC; Convergent Peñuelas Energy Storage 1, LLC; Convergent Caguas Energy Storage […] 13/diciembre/2024 2024/12/13 File
Resolution and Order Subject: Request of Amendments of Clean Flexible Energy, LLC ESSAs and PPOAs. 05/diciembre/2024 2024/12/05 File
Resolution and Order Subject: Approval of two additional energy storage service agreements (ESSAs) 05/diciembre/2024 2024/12/05 File
Motion to Submit Amendments for the Review and Approval of Certain PPOA and ESSAS By the Energy Bureau Subject: Motion to Submit Amendments for the Review and Approval of Certain PPOA and ESSAS By the Energy Bureau 21/noviembre/2024 2024/11/21 File
Resolution and Order Subject: Request of Amendments of Clean Flexible Energy, LLC ESSAs and PPOAs. 06/noviembre/2024 2024/11/06 File
Motion in Compliance with the Resolution and Order Dated October 3rd, 2024 Subject: IN RE: The Implementation of the Puerto Rico Electric Power Authority Integrated Resource Plan and Modified Action Plan 30/octubre/2024 2024/10/30 File
Resolution and Order Subject: Renewable Energy Generation and Energy Storage Resource Procurement Plan Cancellation of Tranche 3 Solicitation. 23/octubre/2024 2024/10/23 File
Resolution and Order Subject: Request of Amendments of Clean Flexible Energy, LLC ESSAs and PPOAs. 03/octubre/2024 2024/10/03 File
Motion to Submit Revised Amendments and PPOAs of Clean Flexible Energy LLC for Review and Approval by the Energy Bureau Subject: Motion to Submit Revised Amendments and PPOAs of Clean Flexible Energy LLC for Review and Approval by the Energy Bureau 26/septiembre/2024 2024/09/26 File
Resolution and Order Subject: Request for Ammendments of Clean Flexible Energy, LLC ESSAs and PPOAs to meet the financing requirements of the Department of Energy’s Loan Program Office (“LPO”). 04/septiembre/2024 2024/09/04 File
Resolution and Order Subject: Renewable Energy Generation and Energy Storage Resource Procurement Plan – Second Tranche Projects Approval 26/agosto/2024 2024/08/26 File
Motion in Compliance with the July 3rd Resolution and Order Subject: IN RE: Implementation of the Puerto Rico Electric Power Authority Integrated Resource Plan and Modified Action Plan. 02/agosto/2024 2024/08/02 File
Motion in Compliance with the June 14th Order Subject: IN RE: Implementation of the Puerto Rico Electric Power Authority Integrated Resource Plan and Modified Action Plan. 31/julio/2024 2024/07/31 File
Motion in Compliance with June 27th Order Subject: Motion in Compliance with June 27th Order 29/julio/2024 2024/07/29 File
Motion for Extension of Time to Comply with the July 3rd Resolution and Order Subject: Motion for Extension of Time to Comply with the July 3rd Resolution and Order 23/julio/2024 2024/07/23 File
Renewal of Request for Extension of Time to Comply Subject: IN RE: Implementation of the Puerto Rico Electric Power Authority Integrated Resource Plan and Modified Action Plan. 22/julio/2024 2024/07/22 File
Partial Compliance with the June 14th Order and Request for Extension of Time to Comply Subject: Exhibit 4A 10/julio/2024 2024/07/10 File
Partial Compliance with the June 14th Order and Request for Extension of Time to Comply Subject: Exhibit A3 10/julio/2024 2024/07/10 File
Partial Compliance with the June 14th Order and Request for Extension of Time to Comply Subject: Exhibit A2 10/julio/2024 2024/07/10 File
Partial Compliance with the June 14th Order and Request for Extension of Time to Comply Subject: Exhibit A1 10/julio/2024 2024/07/10 File
Partial Compliance with the June 14th Order and Request for Extension of Time to Comply Subject: Partial Compliance with the June 14th Order and Request for Extension of Time to Comply 10/julio/2024 2024/07/10 File
Motion in Partial Compliance with the June 27th Order and Request for Extension of Time to Comply Subject: IN RE: Implementation of the Puerto Rico Electric Power Authority Integrated Resource Plan and Modified Action Plan. 08/julio/2024 2024/07/08 File
Resolution and Order Subject: First Request for Information in relation to request of approval of two additional energy storage service agreements (ESSAs) 03/julio/2024 2024/07/03 File
Resolution and Order Subject: Request for Information in relation to request of amendments of Clean Flexible Energy, LLC ESSAs and PPOAs. 27/junio/2024 2024/06/27 File
Motion to Reiterate the Request for the Review and Approval of Certain PPOAS and ESSAS Amendments by the Energy Bureau Subject: Motion to Reiterate the Request for the Review and Approval of Certain PPOAS and ESSAS Amendments by the Energy Bureau 24/junio/2024 2024/06/24 File
Motion for Extension of Time to Comply with the June 14th Resolution Subject: Motion for Extension of Time to Comply with the June 14th Resolution 20/junio/2024 2024/06/20 File
Motion to Submit the Report of the Selection Committee’s Evaluation of the Tranche 2 Renewable Energy and Energy Storage Solicitation Subject: Motion to Submit the Report of the Selection Committee’s Evaluation of the Tranche 2 Renewable Energy and Energy Storage Solicitation 18/junio/2024 2024/06/18 File
Resolution and Order Subject: Request for Information (“ROI”) 14/junio/2024 2024/06/14 File
Motion to Submit Amendments for the Review and Approval of Clean Flexible Energy, LLC’s PPOAS and ESSAS by the Energy Bureau Subject: IN RE: The Implementation of the Puerto Rico Electric Power Authority Integrated Resource Plan and Modified Action Plan. 31/mayo/2024 2024/05/31 File
Motion to Submit Additional Energy Storage Service Agreements (ESSAS) for the Energy Bureau’s Approval Subject: Motion to Submit Additional Energy Storage Service Agreements (ESSAS) for the Energy Bureau’s Approval 07/mayo/2024 2024/05/07 File
Motion to Submit Amendments for Two Executed ESSA’s Subject: Motion to Submit Amendments for Two Executed ESSA’s 16/abril/2024 2024/04/16 File
Memorandum of Law in Support of Confidential Treatment of Exhibit 1 Filed by LUMA on February 12, 2024 Subject: Memorandum of Law in Support of Confidential Treatment of Exhibit 1 Filed by LUMA on February 12, 2024 23/febrero/2024 2024/02/23 File
NEPR-MI-2020-0012 Motion for Extension of Time to File Memorandum of Law in Support of Confidential Treatment of Exhibit 1 Filed by LUMA on February 12, 2024 Subject: NEPR-MI-2020-0012 Motion for Extension of Time to File Memorandum of Law in Support of Confidential Treatment of Exhibit 1 Filed by LUMA on February 12, 2024 […] 23/febrero/2024 2024/02/23 File
Resolución Subject: Resolución sobre Moción Solicitando Participar en Primer Tranche de Proyectos y sobre Moción Solicitando Acción del NEPR. 14/febrero/2024 2024/02/14 File
Motion to Submit Information in Compliance with Resolution and Order of February 5, 2023 and Request for Confidential Treatment Subject: Motion to Submit Information in Compliance with Resolution and Order of February 5, 2023 and Request for Confidential Treatment 12/febrero/2024 2024/02/12 File
Motion in Compliance With the February 5, 2024 Resolution and Order Subject: Tranche 1 Interconnection costs 12/febrero/2024 2024/02/12 File
Resolution and Order Subject: Tranche 1 Interconnection Costs 05/febrero/2024 2024/02/05 File
Notice of Withdrawal as Attorney of Record  Subject: Notice of Withdrawal as Attorney of Record 08/enero/2024 2024/01/08 File
Notice of Withdrawal as Attorney of Record  Subject: Notice of Withdrawal as Attorney of Record 08/enero/2024 2024/01/08 File
Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 Subject: YFNY Amendment 1_Redacted 21/diciembre/2023 2023/12/21 File
Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 Subject: YFNY Interconnection Agreement_Redacted 21/diciembre/2023 2023/12/21 File
Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 Subject: Tetris Amendment 1_Redacted 21/diciembre/2023 2023/12/21 File
Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 Subject: Interconnection Agreement (Brownfield) (Tetris) Full Execution Version 11.29.23_Redacted 21/diciembre/2023 2023/12/21 File
Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 Subject: First Amendment to Interconnection Agreement Salinas Solar _Redacted 21/diciembre/2023 2023/12/21 File
Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 Subject: Interconnection Agreement (Greenfield) (Salinas Solar PPOA)_Redacted 21/diciembre/2023 2023/12/21 File
Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 Subject: Pattern Barceloneta Interconnection Agreement_Redacted 21/diciembre/2023 2023/12/21 File
Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 Subject: Pattern Barceloneta Interconnection Agreement Amendment 1_Redacted 21/diciembre/2023 2023/12/21 File
Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 Subject: First Amendment to Interconnection Agreement Execution Version (JobosPV) _Redacted 21/diciembre/2023 2023/12/21 File
Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 Subject: Interconnection Agreement (CFE) (Brownfield) (Jobos PV) _Redacted 21/diciembre/2023 2023/12/21 File
Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 Subject: Guayama Solar Interconnection Agreement_Redacted 21/diciembre/2023 2023/12/21 File
Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 Subject: Guayama Solar Interconnection Agreement Amendment 1 pdf_Redacted 21/diciembre/2023 2023/12/21 File
Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 Subject: Go Green Interconnection Agreement_Redacted 21/diciembre/2023 2023/12/21 File
Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 Subject: Ciro One – Interconnection Agreement_Redacted 21/diciembre/2023 2023/12/21 File
Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 Subject: Solaner Interconnection Agreement_Redacted 21/diciembre/2023 2023/12/21 File
Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 Subject: Solaner Amendment 1_Redacted 21/diciembre/2023 2023/12/21 File
Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 Subject: Interconnection Agreement (Greenfield) (Salinas BESS) _Redacted 21/diciembre/2023 2023/12/21 File
Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 Subject: First Amendment to Interconnection Agreement Salinas BESS _Redacted 21/diciembre/2023 2023/12/21 File
Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 Subject: CS_UR Juncos Amendment_Redacted 21/diciembre/2023 2023/12/21 File
Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 Subject: CS_UR Juncos (AQ-1-P)_Redacted 21/diciembre/2023 2023/12/21 File
Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 Subject: Convergent Coamo Interconnection Agreement_Redacted 21/diciembre/2023 2023/12/21 File
Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 Subject: Convergent Coamo Interconnection Agreement Amendment 1_Redacted 21/diciembre/2023 2023/12/21 File
Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 Subject: Ciro Two Interconnection Agreement_Redacted 21/diciembre/2023 2023/12/21 File
Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 Subject: Ciro Two Interconnection Agreement Amendment 1_Redacted 21/diciembre/2023 2023/12/21 File
Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 Subject: Interconnection Agreement (CFE) (Job ESSA) (Brownfield) _Redacted 21/diciembre/2023 2023/12/21 File
Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 Subject: First Amendment to Interconnection Agreement Execution Version _Redacted 21/diciembre/2023 2023/12/21 File
Motion to Submit Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 and Memorandum of Law in Support of Confidential Treatment of Exhibit 1 Subject: Motion to Submit Corrected Exhibit 1 to «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» Filed by LUMA on December 7, 2023 and […] 21/diciembre/2023 2023/12/21 File
Motion in Compliance with the November 29th, 2023 Resolution and Order Subject: Motion in Compliance with the November 29th, 2023 Resolution and Order 20/diciembre/2023 2023/12/20 File
Motion for Extension of Time to file Memorandum of Law in Suppport of Confidential Treatment of Exhibit 1 to the «Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment» filed by LUMA on December 7, 2023 Subject: Motion for Extension of Time to file Memorandum of Law in Suppport of Confidential Treatment of Exhibit 1 to the «Motion to Submit Executed Interconnection Agreements […] 18/diciembre/2023 2023/12/18 File
Motion to Request an Extension of Time to Comply with November 29th Order Subject: Motion to Request an Extension of Time to Comply with November 29th Order 13/diciembre/2023 2023/12/13 File
Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment Subject: Motion to Submit Executed Interconnection Agreements and Request for Confidential Treatment 07/diciembre/2023 2023/12/07 File
Resolution and Order Subject: Resolution and Order regarding Motion for Partial Reconsideration of the Resolution and Order Dated November 29, 2023, filed by the Puerto Rico Electric Power Authority 07/diciembre/2023 2023/12/07 File
Motion in Compliance with the November 29th, Resolution and Order Subject: Motion in Compliance with the November 29th, Resolution and Order 06/diciembre/2023 2023/12/06 File
Informative Motion on Execution of Tranche 1 Interconnection Agreements, Request for Determination Regarding Interconnection Costs and Request for Confidential Treatment Subject: Informative Motion on Execution of Tranche 1 Interconnection Agreements, Request for Determination Regarding Interconnection Costs and Request for Confidential Treatment 06/diciembre/2023 2023/12/06 File
Motion in Compliance with Energy Bureau November 29, 2023 Resolution and Order Subject: Motion in Compliance with Energy Bureau November 29, 2023 Resolution and Order 04/diciembre/2023 2023/12/04 File
Motion for Partial Reconsideration of the Resolution and order Dated November 29, 2023 Subject: Motion for Partial Reconsideration of the Resolution and order Dated November 29, 2023 30/noviembre/2023 2023/11/30 File
Resolution and Order Subject: Resolution and Order regarding Urgent Motion to Submit Amended PPOA and ESSA, filed by the Puerto Rico Electric Power Authority 29/noviembre/2023 2023/11/29 File
Urgent Motion to Submit Amended PPOA and ESSA Subject: Urgent Motion to Submit Amended PPOA and ESSA 28/noviembre/2023 2023/11/28 File
Asociación de Productores de Energía Renovable – Request for Clarification Subject: Asociación de Productores de Energía Renovable – Request for Clarification 14/noviembre/2023 2023/11/14 File
Resolution and Order Subject: Motion in Compliance with Order regarding «Restricted Parties» provision 06/noviembre/2023 2023/11/06 File
Resolution and Order Subject: PREPA representative for the Selection Committee and a point of contact with PREB -IC 19/octubre/2023 2023/10/19 File
Notice of Withdrawal as Attorney of Record Subject: Notice of Withdrawal as Attorney of Record 10/octubre/2023 2023/10/10 File
Resolution and Orden Subject: Resolution and Order regarding Motion to Submit N- 1 -P Proponent Best and  Final Offer Information, filed by the Puerto Rico Electric Power Authority 27/septiembre/2023 2023/09/27 File
Resolution and Order Subject: Resolution and Order regarding Motion to Comply with Resolution and Order of September 15, 2023, as Modified by Resolution and Order of September 20, 2023, filed […] 26/septiembre/2023 2023/09/26 File
Motion to Supplement PREPA’s September 6 Motion and Request for Approval of Amendment to the N-1-P Project PPOA Subject: Motion to Supplement PREPA’s September 6 Motion and Request for Approval of Amendment to the N-1-P Project PPOA 25/septiembre/2023 2023/09/25 File
Motion in Compliance with the September 15 Resolution and Order Subject: Motion in Compliance with the September 15 Resolution and Order 22/septiembre/2023 2023/09/22 File
Motion to Comply with Resolution and Order of September 15, 2023, as Modified by Resolution and Order of September 20, 2023 Subject: Motion to Comply with Resolution and Order of September 15, 2023, as Modified by Resolution and Order of September 20, 2023 22/septiembre/2023 2023/09/22 File
Motion to Submit Proposed Amendment to AI-1P PPOA Subject: Motion to Submit Proposed Amendment to AI-1P PPOA 20/septiembre/2023 2023/09/20 File
Resolution and Order Subject: LUMA’s Motion Requesting Extension to Comply with September 15th Order 20/septiembre/2023 2023/09/20 File
Motion Requesting Extension of Time to Comply with September 15th Order Subject: Motion Requesting Extension of Time to Comply with September 15th Order 19/septiembre/2023 2023/09/19 File
Resolution and Order Subject: Tranche 1 Interconnection Costs. 15/septiembre/2023 2023/09/15 File
Motion in Compliance with Order Regarding Quanta Services Inc. Request for Revision to the Provision Regarding «Restricted Parties» in the RFP’s for Tranches 1-6 Subject: Motion in Compliance with Order Regarding Quanta Services Inc. Request for Revision to the Provision Regarding «Restricted Parties» in the RFP’s for Tranches 1-6 11/septiembre/2023 2023/09/11 File
Motion in Compliance with the August 24 Order Subject: Motion in Compliance with the August 24 Order 06/septiembre/2023 2023/09/06 File
Resolution and Order Subject: Quanta Services Inc. request for revision to the provision regarding «Restricted Parties» in the RFPs for Tranches 1 – 6 01/septiembre/2023 2023/09/01 File
Resolution and Order Subject: Resolution and Order regarding Motion to Submit N-1-P Proponent Best and Final Offer Information, filed by the Puerto Rico Electric Power Authority 30/agosto/2023 2023/08/30 File
Informative Motion and Request for Extension to Comply with the August 24 Order Subject: Informative Motion and Request for Extension to Comply with the August 24 Order 28/agosto/2023 2023/08/28 File
Resolution and Order Subject: Resolution and Order regarding Motion to Submit N-1-P Proponent Best and Final Offer Information, filed by the Puerto Rico Electric Power Authority. 24/agosto/2023 2023/08/24 File
Motion to Submit N-1-P Proponent Best and Final Offer Information Subject: Motion to Submit N-1-P Proponent Best and Final Offer Information 22/agosto/2023 2023/08/22 File
Resolution and Order Subject: Resolution and Order regarding Motion to Submit Amendment to PPOA Between Esmeralda Solar Farm and PREPA, filed by the Puerto Rico Electric Power Authority. 16/agosto/2023 2023/08/16 File
Moción Solicitando Acción de NEPR Subject: (Windmar) Determinations for Subset of Tranche 1 Solar PV Projects 15/agosto/2023 2023/08/15 File
Motion to Submit Amendment to PPOA Between Esmeralda Solar Farm and PREPA Subject: Motion to Submit Amendment to PPOA Between Esmeralda Solar Farm and PREPA 31/julio/2023 2023/07/31 File
Motion to Submit Negotiated Contract with Selected IRP Technical Consultant and Related Information and Request for Confidentiality Subject: Submittal of Negotiated Contract with Selected IRP Technical Consultant and Related Information and Request for Confidentiality 27/julio/2023 2023/07/27 File
Informative Motion Regarding Request for Proposals for PREPA Interconnection Facilities Works for Tranche 1 Projects  Subject: Informative Motion Regarding Request for Proposals for PREPA Interconnection Facilities Works for Tranche 1 Projects 13/julio/2023 2023/07/13 File
Resolution Nunc Pro Tunc Subject: Resolution Nunc Pro Tunc; Correction Attachment A of Resolution and Order June 30, 2023. 03/julio/2023 2023/07/03 File
Informative Motion Regarding Request for Proposals for PREPA Interconnection Facilities Works for Tranche 1 Projects Subject: Informative Motion Regarding Request for Proposals for PREPA Interconnection Facilities Works for Tranche 1 Projects 03/julio/2023 2023/07/03 File
Resolution and Order Subject: Determinations for Subset of Tranche 1 Solar PV and Battery Energy Storage Projects. 30/junio/2023 2023/06/30 File
Moción Solicitando Participar en Primer Tranche de Proyectos Subject: Determinations for Subset of Tranche I Solar PV Projects 16/junio/2023 2023/06/16 File
Motion to Submit Additional Amended PPOAS and ESSA’s Subject: Motion to Submit Additional Amended PPOAS and ESSA’s 15/junio/2023 2023/06/15 File
Resolution Subject: Request for Confidential Designation and Treatment 06/junio/2023 2023/06/06 File
Motion to Submit Second Amendments for Two Executed PPOAs Subject: Motion to Submit Second Amendments for Two Executed PPOAs 25/mayo/2023 2023/05/25 File
Resolution and Order Subject: Determinations for Subset if Tranche 1 Solar PV Projects. 25/mayo/2023 2023/05/25 File
Resolution Subject: Determination on PREPA’s May 12 and May 16, 2023 Request for Confidential Designation and Treatment. 23/mayo/2023 2023/05/23 File
Motion to Submit LCOS in Support of Energy Storage Service Agreement (ESSAs) Presented by PREPA in its May 12 Motion Subject: Motion to Submit LCOS in Support of Energy Storage Service Agreement (ESSAs) Presented by PREPA in its May 12 Motion 22/mayo/2023 2023/05/22 File
Motion to Submit Additional Amended June 30 PPOAS Subject: Motion to Submit Additional Amended June 30 PPOAS 16/mayo/2023 2023/05/16 File
Resolution Subject: Request for Confidential Designation and Treatment 12/mayo/2023 2023/05/12 File
Motion to Submit Additional Energy Storage Service Agreements (ESSAs) for the Energy Bureau’s Evaluation and Approval Subject: Motion to Submit Additional Energy Storage Service Agreements (ESSAs) for the Energy Bureau’s Evaluation and Approval 12/mayo/2023 2023/05/12 File
Motion to Supplement PREPA’s April 28 Motion in Compliance with the April 24, 2023, Resolution and Order Subject: Motion to Supplement PREPA’s April 28 Motion in Compliance with the April 24, 2023, Resolution and Order 02/mayo/2023 2023/05/02 File
Motion in Compliance with the April 24 Resolution and Order Subject: Motion in Compliance with the April 24 Resolution and Order 28/abril/2023 2023/04/28 File
Resolución Subject: Resolución respecto a Moción en Cumplimiento de Orden del 12 de abril de 2023, presentada por la Autoridad de Energía Eléctrica de Puerto Rico. 26/abril/2023 2023/04/26 File
Motion to Submit Amended June 30 PPOAs Subject: Motion to Submit Amended June 30 PPOAs 26/abril/2023 2023/04/26 File
Resolution Subject: Extension of time for Tranche 1 Executed Projects signed June 30, 2022 to achieve Closing Date. 24/abril/2023 2023/04/24 File
Moción en Cumplimiento de Orden del 12 de abril de 2023  Subject: Moción en Cumplimiento de Orden del 12 de abril de 2023 19/abril/2023 2023/04/19 File
Motion in Compliance with Order Regarding Submittal of Proponent’s Best and Final Offers Information Subject: Motion in Compliance with Order Regarding Submittal of Proponent’s Best and Final Offers Information 19/abril/2023 2023/04/19 File
Resolution Subject: Extension of time for Tranche 1 Executed Projects signed June 30, 2022 to achieve Closing Date 17/abril/2023 2023/04/17 File
Motion Requesting Technical Meeting Subject: Motion Requesting Technical Meeting 14/abril/2023 2023/04/14 File
Motion Requesting Order on PREPA Request to Amend the Modified Budget for FY2023 for the Purpose of Complying with April 4 Resolutions and Orders on Tranche 1 Closing Date Subject: Motion Requesting Order on PREPA Request to Amend the Modified Budget for FY2023 for the Purpose of Complying with April 4 Resolutions and Orders on Tranche […] 11/abril/2023 2023/04/11 File
Resolution and Order Subject: Motion Requesting Approval of Amendments and Informing on Status of Project Development Timeline for Tranche 1 Utility- Scale Project Agreements. 04/abril/2023 2023/04/04 File
Resolution and Order Subject: Resolution and Order addressing LUMA RFP for POI Interconnection Works for Tranche 1. 04/abril/2023 2023/04/04 File
Subject: Motion Submitting Update on IRP Technical Consultant Contracting Process, Request for Modification of Procedural Timeline and Request for Confidential Treatment 31/marzo/2023 2023/03/31 File
Motion Requesting Approval of Amendments and Informing on Status of Project Development Timeline for Tranche 1 Utility-Scale Project Agreements  Subject: Motion Requesting Approval of Amendments and Informing on Status of Project Development Timeline for Tranche 1 Utility-Scale Project Agreements 31/marzo/2023 2023/03/31 File
Motion in Compliance with Order and to Inform and Clarify March 10, 2023 Resolution and Order as Applicable to Sectionalizer Projects Subject: Motion in Compliance with Order and to Inform and Clarify March 10, 2023 Resolution and Order as Applicable to Sectionalizer Projects 17/marzo/2023 2023/03/17 File
Resolution and Order Subject: Resolution and Order regarding various motions. 10/marzo/2023 2023/03/10 File
Informative Motion Regarding Update on LUMA Interconnection Studies Policy Change, Amendment to Closing Date, T1 Project Permitting Process and Request for Order Directing LUMA To Take Specified Actions to Minimize Further Delays Subject: Informative Motion Regarding Update on LUMA Interconnection Studies Policy Change, Amendment to Closing Date, T1 Project Permitting Process and Request for Order Addressing Same 28/febrero/2023 2023/02/28 File
Motion in Compliance with December 19th Order with Respect to Status of Interconnection Studies for Six Approved BESS Projects and Modeling Description for Such Studies Subject: Motion in Compliance with December 19th Order with Respect to Status of Interconnection Studies for Six Approved BESS Projects and Modeling Description for Such Studies 09/enero/2023 2023/01/09 File
Informative Motion in Compliance with the December 19, 2022 Order which Requested a Status Updates on Contract Negotiations with BESS Projects Subject: Informative Motion in Compliance with the December 19, 2022 Order which Requested a Status Updates on Contract Negotiations with BESS Projects 03/enero/2023 2023/01/03 File
Informative Motion Regarding Interconnection Studies for Tranche 1 Approved BESS Projects and Request for Confidential Treatment Subject: Informative Motion Regarding Interconnection Studies for Tranche 1 Approved BESS Projects and Request for Confidential Treatment 22/diciembre/2022 2022/12/22 File
Resolution and Order Subject: Approval for GSA for the 17 MW VPP; and request for updated interconnection studies inclusive of the BESS First Tranche Projects 19/diciembre/2022 2022/12/19 File
SESA Request for a 2nd Extension of the Second Renewable Generation and Energy Storage Resource Procurement Tranche No subject available. 01/diciembre/2022 2022/12/01 File
Motion to Submit Draft Copy of GSA in Compliance with the June 13, 2022 Order Subject: Motion to Submit Draft Copy of GSA in Compliance with the June 13, 2022 Order 02/noviembre/2022 2022/11/02 File
Resolution and Order Subject: Submittal of Status Update on Technical Consultant Contracting Process and Early Stages of IRP Preparation in Compliance with Energy Bureau Resolution and Order of April 22, […] 14/octubre/2022 2022/10/14 File
Motion to Submittal of Status Update on Technical Consultant Contracting Process and Early Stages of IRP Preparation in Compliance with Energy Bureau Resolution and Order of April 22, 2022 Subject: Motion to Submittal of Status Update on Technical Consultant Contracting Process and Early Stages of IRP Preparation in Compliance with Energy Bureau Resolution and Order of […] 03/octubre/2022 2022/10/03 File
Motion to Set Aside Order Given Previous Compliance by PREPA Submitting Responses, on June 16, 2022, to LCOS Request for Information in Compliance with the June 13 Order Subject: Motion to Set Aside Order Given Previous Compliance by PREPA Submitting Responses, on June 16, 2022, to LCOS Request for Information in Compliance with the June […] 09/septiembre/2022 2022/09/09 File
Resolution and Order Subject: Renewable Energy Generation and Energy Storage Resource Procurement Plan – First Tranche Projects for Phase III Contract Negotiation and Final Interconnection Plan Approvals 08/septiembre/2022 2022/09/08 File
Resolution and Order Subject: Renewable Energy Generation and Energy Storage Resource Procurement Plan – First Tranche Projects for Phase III Contract Negotiation and Final Interconnection Plan Approvals 01/septiembre/2022 2022/09/01 File
Motion to Submit List of Qualified Proponents for IRP Consultant Procurement and Related Information and Request for Confidentiality Subject: Submittal of Qualified Proponents for IRP Consultant Procurement and Related Information and Request for Confidentiality 31/agosto/2022 2022/08/31 File
Motion to Submit Remaining Executed PPOAs and Bess Contracts in Compliance with the August 15, 2022, Resolution and Order Subject: BESS PPOA Agreement Between PREPA and Clean Flexible Energy LLC – Jobos (PPOA)_Redacted 26/agosto/2022 2022/08/26 File
Motion to Submit Remaining Executed PPOAs and Bess Contracts in Compliance with the August 15, 2022, Resolution and Order Subject: Naguabo A PPOA BETWEEN PREPA AND CLEAN FLEXIBLE ENERGY LLC – NAGUABO-A (PPOA)_Redacted 26/agosto/2022 2022/08/26 File
Motion to Submit Remaining Executed PPOAs and Bess Contracts in Compliance with the August 15, 2022, Resolution and Order Subject: BESS PPOA Between PREPA and Clean Flexible Energy LLC – Salinas (PPOA)_Redacted 26/agosto/2022 2022/08/26 File
Motion to Submit Remaining Executed PPOAs and Bess Contracts in Compliance with the August 15, 2022, Resolution and Order Subject: Salinas PPOA PREPA and Clean Flexible Energy LLC – Salinas (PPOA)_Redacted (1) 26/agosto/2022 2022/08/26 File
Motion to Submit Remaining Executed PPOAs and Bess Contracts in Compliance with the August 15, 2022, Resolution and Order Subject: Naguabo Power Purchase and Operating Agreement Between PREPA and Clean Flexible Energy LLC (PPOA)_Redacted 26/agosto/2022 2022/08/26 File
Motion to Submit Remaining Executed PPOAs and Bess Contracts in Compliance with the August 15, 2022, Resolution and Order Subject: PPOA Jobos Puerto Rico Electric Power Authority and Clean Flexible Energy LLC – Jobos (PPOA)_Redacted 26/agosto/2022 2022/08/26 File
Motion to Submit Remaining Executed PPOAs and Bess Contracts in Compliance with the August 15, 2022, Resolution and Order Subject: Motion to Submit Remaining  PPOAs  in Compliance with the August 15, 2022, Resolution and Order 26/agosto/2022 2022/08/26 File
Resolution Subject: Resolution regarding Response to Resolution and Order of July 20, 2022, and Request for Technical Conference, filed by LUMA Energy, LLC and LUMA Energy ServCo, LLC. 18/agosto/2022 2022/08/18 File
Resolution and Order Subject: Renewable Energy Generation and Energy Storage Resource Procurement Plan – First Tranche Projects for Phase III Contract Negotiation and Final Interconnection Plan Approvals 15/agosto/2022 2022/08/15 File
Response to Resolution and Order of July 20, 2022, and Request for Technical Conference Subject: Response to Resolution and Order of July 20, 2022, and Request for Technical Conference 15/agosto/2022 2022/08/15 File
Motion to Submit Additional Executed PPOA in Compliance with July 8 Resolution and Order Subject: Redacted Exhibit A – Esmeralda Solar Farm LLC PPOA (Contrato) (002) redacted 13/agosto/2022 2022/08/13 File
Motion to Submit Additional Executed PPOA in Compliance with July 8 Resolution and Order Subject: Motion to Submit Additional Executed PPOA in Compliance with July 8 Resolution and Order 13/agosto/2022 2022/08/13 File
Motion to Submit Additional PPOAS in Compliance with July 8 Resolution and Order Subject: Exhibit A-Go Green USA América Corp. PPOA (Contrato) Redacted 05/agosto/2022 2022/08/05 File
Motion to Submit Additional PPOAS in Compliance with July 8 Resolution and Order Subject: Exhibit A-SolarBlue Bemoga, LLC PPOA (Contrato) Redacted 05/agosto/2022 2022/08/05 File
Motion to Submit Additional PPOAS in Compliance with July 8 Resolution and Order Subject: Exhibit A-Enerxia Solar, LLC PPOA (Contrato) Redacted 05/agosto/2022 2022/08/05 File
Motion to Submit Additional PPOAS in Compliance with July 8 Resolution and Order Subject: Exhibit A-Diversys Solar, LLC PPOA (Contrato) Redacted 05/agosto/2022 2022/08/05 File
Motion to Submit Additional PPOAS in Compliance with July 8 Resolution and Order Subject: Motion to Submit Additional PPOAS in Compliance with July 8 Resolution and Order 04/agosto/2022 2022/08/04 File
Motion To Submit Federal Funding Roadmap in Compliance with Energy Bureau Resolution and Order of June 13, 2022 Subject: Motion To Submit Federal Funding Roadmap in Compliance with Energy Bureau Resolution and Order of June 13, 2022 28/julio/2022 2022/07/28 File
Informative Motion and Request for Extension to Submit Supplemental Interconnection Studies for two Pending Solar PV Projects Subject: Informative Motion and Request for Extension to Submit Supplemental Interconnection Studies for two Pending Solar PV Projects 21/julio/2022 2022/07/21 File
Resolution and Order  Subject: Resolution and Order regarding LUMA’s Urgent Motion Requesting Reconsideration of Energy Bureau’s Resolution and Order of June 13, 2022 and Stay of all Directives Therein 20/julio/2022 2022/07/20 File
Motion Requesting Extension of Time to Submit Execution Copies of Additional PPOAs in Compliance with July 8 Resolution and Order Subject: Motion for Extension of Time to Submit Execution Copies of Additional PPOAs in Compliance with July 8 Resolution and Order 18/julio/2022 2022/07/18 File
Resolution Subject: Resolution regarding Motion Requesting Modification of Energy Bureau’s Resolution and Order of June 9, 2022, with Respect to the Composition of the Selection Committee Established Therein […] 14/julio/2022 2022/07/14 File
Informative Motion Relating to Energy Bureau’s Approval of Nine Tranche 1 Bess Projects Subject: Informative Motion Relating to Energy Bureau’s Approval of Nine Tranche 1 Bess Projects 13/julio/2022 2022/07/13 File
Amended Motion to Submit Confidential and Redacted Execution Copies of PPOAS Subject: Exhibit-APattern Barceloneta Solar LLC PPOA_Redacted (1) 12/julio/2022 2022/07/12 File
Amended Motion to Submit Confidential and Redacted Execution Copies of PPOAS Subject: Exhibit-A YFN Yabucoa Solar LLC PPOA_Redacted 12/julio/2022 2022/07/12 File
Amended Motion to Submit Confidential and Redacted Execution Copies of PPOAS Subject: Exhibit-A Guayama Solar Energy LLC PPOA_Redacted 12/julio/2022 2022/07/12 File
Amended Motion to Submit Confidential and Redacted Execution Copies of PPOAS Subject: Exhibit-A Ciro Two Salinas LLC PPOA_Redacted 12/julio/2022 2022/07/12 File
Amended Motion to Submit Confidential and Redacted Execution Copies of PPOAS Subject: Exhibit A-Solaner Puerto Rico One LLC PPOA_Redacted 12/julio/2022 2022/07/12 File
Amended Motion to Submit Confidential and Redacted Execution Copies of PPOAS Subject: Exhibit A-Pattern Vega Baja Solar LLC PPOA_Redacted 12/julio/2022 2022/07/12 File
Amended Motion to Submit Confidential and Redacted Execution Copies of PPOAS Subject: Exhibit A-CS-UR Juncos PV LLC PPOA_Redacted 12/julio/2022 2022/07/12 File
Amended Motion to Submit Confidential and Redacted Execution Copies of PPOAS Subject: Exhibit A-Convergent Coamo Energy Storage 1 LLC PPOA_Redacted 12/julio/2022 2022/07/12 File
Amended Motion to Submit Confidential and Redacted Execution Copies of PPOAS Subject: Exhibit A- Tetris Power LLC PPOA_Redacted (1) 12/julio/2022 2022/07/12 File
Amended Motion to Submit Confidential and Redacted Execution Copies of PPOAS Subject: Amended Motion to Submit Confidential and Redacted Execution Copies of PPOA 12/julio/2022 2022/07/12 File
Resolution and Order Subject: Renewable Energy Generation and Energy Storage Resource Procurement Plan – First Tranche Projects for Phase III Contract Negotiation and Final Interconnection Plan Approvals 08/julio/2022 2022/07/08 File
Response to PREPA’s Second Motion on Gas Conversions for Aguirre, San Juan, Palo Seco Power Plants Subject: Response to PREPA’s Second Motion on Gas Conversions for Aguirre, San Juan, Palo Seco Power Plants 05/julio/2022 2022/07/05 File
Resolution and Order Subject: Request for Confidential Designation and Treatment 05/julio/2022 2022/07/05 File
Motion to Submit Status Update On Technical Consultant Contracting Process And Early Stages of 2024 IRP Preparation In Compliance With Energy Bureau Resolution And Order Of April 22, 2022 Subject: Submittal of Status Update On Technical Consultant Contracting Process And Early Stages of 2024 IRP Preparation In Compliance With Energy Bureau Resolution And Order Of April […] 01/julio/2022 2022/07/01 File
Motion to Submit Execution Copies of PPOAS in Compliance with April 27 and June 13 2022 Orders,  Request for Additional Time to Submit Certain PPOAS and Memorandum of Law Requesting Confidential Treatment of PPOAS and Exhibits  Subject: Motion to Submit Execution Copies of PPOAS in Compliance with April 27 and June 13 2022 Orders,  Request for Additional Time to Submit Certain PPOAS and […] 30/junio/2022 2022/06/30 File
Motion in Compliance with Resolution and Order of June 9, 2022 Subject: Motion in Compliance with Resolution and Order of June 9, 2022 30/junio/2022 2022/06/30 File
Motion to Submit the Appointment of PREPA Representatives in Compliance with the June 9 Resolution and Order Subject: Motion to Submit the Appointment of PREPA Representatives in Compliance with the June 9 Resolution and Order 29/junio/2022 2022/06/29 File
Motion Requesting Modification of Energy Bureau Resolution and Order of June 9, 2022 with Respect to the Composition of the Selection Committee Established Therein Subject: Request for Modification of Energy Bureau Resolution and Order of June 9, 2022 with Respect to the Composition of the Selection Committee Established Therein 29/junio/2022 2022/06/29 File
Urgent Motion Requesting Reconsideration of Energy Bureau’s Resolution and Order on June 13, 2022, and Stay of All Directives Therein Subject: Urgent Motion Requesting Reconsideration of Energy Bureau’s Resolution and Order on June 13, 2022, and Stay of All Directives Therein 22/junio/2022 2022/06/22 File
Resolution and Order Subject: Renewable Energy Generation and Energy Storage Resource Procurement Plan – First Tranche Projects for Phase III Contract Negotiation and Final Interconnection Plan Approvals 13/junio/2022 2022/06/13 File
Memorandum of Law in Support of Confidential Treatment of Interconnection Studies Submitted by LUMA on May 31, 2022 Subject: Memorandum of Law in Support of Confidential Treatment of Interconnection Studies Submitted by LUMA on May 31, 2022 13/junio/2022 2022/06/13 File
Resolution and Order Subject: Funds for Transmission System Network Upgrades that contribute to raising system performance to industry standards 13/junio/2022 2022/06/13 File
Resolution and Order Subject: Roles of PREPA and LUMA in the Procurement Process for Upcoming Tranches 09/junio/2022 2022/06/09 File
Motion to Submit Letter Sent by the Oversight Board to Reiterate the Petition to Initiate Works to Comply with Environmental Regulations, and Request for Technical Conference Subject: Motion to Submit Letter Sent by the Oversight Board, to Reiterate the Petition to Initiate Works to Comply with Environmental Regulations, and Request for Technical Conference 03/junio/2022 2022/06/03 File
Motion Submitting Final Technical Interconnection Studies for Eighteen Tranche 1 Projects Required Under Energy Bureau’s Resolution and Order of April 27, 2022, and Request for Confidential Treatment Subject: Submittal of Final Technical Interconnection Studies for Eighteen Tranche 1 Projects Required Under Energy Bureau’s Resolution and Order of April 27, 2022, and Request for Confidential […] 31/mayo/2022 2022/05/31 File
Motion to Inform Approval of Mayaguez Project Subject: Motion to Inform Approval of Mayaguez Hydro-Gas Power Plant Permanent Repairs 19/mayo/2022 2022/05/19 File
Memorandum of Law in Support of Confidential Treatment of Responses Submitted in Compliance with Resolution and Order Dated April 11, 2022 Subject: Memorandum of Law in Support of Confidential Treatment of Responses Submitted in Compliance with Resolution and Order Dated April 11, 2022 09/mayo/2022 2022/05/09 File
Motion in Compliance with the Progress Report and Update Task Schedule Requirements of the Energy Bureau’s Resolution and Order of April 27, 2022 Subject: Motion in Compliance with the Progress Report and Update Task Schedule Requirements of the Energy Bureau’s Resolution and Order of April 27, 2022 29/abril/2022 2022/04/29 File
Sixth Motion to Reiterate Request for Entry of Resolution and Order Detailing PREPA’s Role in the Tranche 2 RFP Process and to Request Meeting Subject: Sixth Motion to Reiterate Request for Entry of Resolution and Order Detailing PREPA’s Role in the Tranche 2 RFP Process and to Request Meeting 28/abril/2022 2022/04/28 File
Motion Submitting Complete Responses to Questions 6 and 7 in Energy Bureau’s Resolution and Order of April 11, 2022 and Requesting Confidential Treatment Subject: Motion Submitting Complete Responses to Questions 6 and 7 in Energy Bureau’s Resolution and Order of April 11, 2022 and Requesting Confidential Treatment 28/abril/2022 2022/04/28 File
Memorandum of Law in Support of Request for Confidential Treatment of Attachment A Subject: Memorandum of Law in Support of Request for Confidential Treatment of Attachment A 28/abril/2022 2022/04/28 File
Resolution and Order Subject: Execution of Approved Power Purchase and Operation  Agreements 27/abril/2022 2022/04/27 File
Resolution and Order Subject: Submittal of Report on Resource Planning Process for Next IRP cycle and Draft RFQ/RFP for IRP Consultant and Request for Confidential Treatment 22/abril/2022 2022/04/22 File
Resolution and Order Subject: PREPA’s and LUMA’s request for Extension of Time to Comply with Responses Required by Resolution and Order of April 11, 2022 22/abril/2022 2022/04/22 File
Motion Submitting Partial Response and Requesting Brief Extension to Submit LUMA’s Full Answers to Questions 6 and 7 in Energy Bureau’s Resolution and Order of April 11, 2022 Subject: Motion Submitting Partial Response and Requesting Brief Extension to Submit LUMA’s Full Answers to Questions 6 and 7 in Energy Bureau’s Resolution and Order of April […] 19/abril/2022 2022/04/19 File
Motion for Extension of Time Until April 25, 2022, to Comply with Responses Required by the April 11, 2022, Resolution and Order Subject: Motion for extension of time to comply with April 11 Order 19/abril/2022 2022/04/19 File
Resolution and Order Subject: Renewable Energy Generation and Energy Storage Resource Procurement Plan-First Tranche Projects for Phase III Contract Negotiation and Final Interconnection Plan  Approvals 11/abril/2022 2022/04/11 File
SESA Request regarding Tranche 1 and Tranche 2 Renewable Generation and Energy Storage Resource and VPP Procurement Subject: SESA Request regarding Tranche 1 and Tranche 2 Renewable Generation and Energy Storage Resource and VPP Procurement 29/marzo/2022 2022/03/29 File
Firth Motion to Reiterate Request for Entry of Resolution and Order Detailing PREPA’s Role in the Tranche 2 RFP Process and to Request Meeting Subject: Firth Motion to Reiterate Request for Entry of Resolution and Order Detailing PREPA’s Role in the Tranche 2 RFP Process and to Request Meeting 28/marzo/2022 2022/03/28 File
Informative Motion and Request for Approval of RFQ/RFP for IRP Consultant Contracting Process Subject: Informative Motion and Request for Approval of RFQ/RFP for IRP Consultant Contracting Process 21/marzo/2022 2022/03/21 File
Moción Solicitando Acción Referente a Moción Titulada «Request for Access to Information Concerning Tranche I Renewable Contracts» Radicada el 8 de febrero de 2022 Subject: Renewable Energy Generation and Energy Storage Resource Procurement Plan-First Tranche Projects or Phase III Contract Negotiation and Final Interconnection Plan Approvals 17/marzo/2022 2022/03/17 File
Memorandum of Law in Support of Request for Confidential Treatment of Attachment A Subject: Memorandum of Law in Support of Request for Confidential Treatment of Attachment A 17/marzo/2022 2022/03/17 File
Moción del Instituto de Competitividad y Sostenibilidad Económica de Puerto Rico para la Inclusión de Factores de Política Pública en la Contratación Subject: ICSE-Aprobación de Solar PV PPOAs 24/febrero/2022 2022/02/24 File
Fourth Motion to Reiterate for Entry of Resolution and Order Detailing PREPA’s Role in the Tranche 2 RFP Process and Informing PREPA’s Point of Contact Subject: Fourth Motion to Reiterate Request for Entry of Resolution and Order Detailing PREPA’s Role in the Tranche  2 RFP Process   21/febrero/2022 2022/02/21 File
Motion Regarding the Preliminary Studies for New Combined Cycle Power Plant in Palo Seco Subject: Motion Regarding the Preliminary Studies for New Combined Cycle Power Plant in Palo Seco 17/febrero/2022 2022/02/17 File
Motion in Compliance with Energy Bureau Resolution and Order of January 27, 2022 Subject: Motion in Compliance with Energy Bureau Resolution and Order of January 27, 2022 15/febrero/2022 2022/02/15 File
Request for Access to Information Concerning Tranche I Renewable Contracts Subject: Renewable Energy Generation and Energy Storage Resource Procurement Plan-First Tranche Projects for phase III Contract negotiation and Final Interconnection Plan Approvals 08/febrero/2022 2022/02/08 File
Resolution and Order Subject: Renewable Energy Generation and Energy Storage Resource Procurement Plan-First Tranche Project for Phase III Contract Negotiation and Final Interconnection Plan Approvals 02/febrero/2022 2022/02/02 File
Motion in Compliance with the January 28 Order Submitting Energy Storage Resources Information, the Next Two Projects Totaling 50 MW of Solar PV Resources and Memorandum of Law Requesting Confidential Treatment Subject: Motion in Compliance with the January 28 Order Submitting Energy Storage Resources Information, the Next Two Projects Totaling 50 MW of Solar PV Resources and Memorandum […] 02/febrero/2022 2022/02/02 File
Motion Compliance With the January 28 Order Submitting Responses to Attachment A Of the December 28 Order and Memorandum of Law Requesting Confidential Treatment Subject: Motion Compliance With the January 28 Order Submitting Responses to Attachment A Of the December 28 Order and Memorandum of Law Requesting Confidential Treatment 31/enero/2022 2022/01/31 File
Motion Reiterating Request for Meeting to Discuss Subject: Motion Reiterating Request for Meeting to Discuss 31/enero/2022 2022/01/31 File
Motion to Inform Submittal of Public Version of Several Motion in Compliance with the January 28 Order Subject: Motion to Inform Submittal of Public Version of Several Motion in Compliance with the January 28 Order 31/enero/2022 2022/01/31 File
Request For Clarification, Partial Reconsideration of December 28 Order, Confidential Meeting and Extension of Time Subject: Request For Clarification, Partial Reconsideration of December 28 Order, Confidential Meeting and Extension of Time 31/enero/2022 2022/01/31 File
Motion in Compliance with the January 28 Order Submitting Responses to Attachment A and Requesting Confidential Treatment Subject: Motion in Compliance with the January 28 Order Submitting Responses to Attachment A and Requesting Confidential Treatment 31/enero/2022 2022/01/31 File
Motion in Compliance with the December 28 Order Submitting 167 MW of VPP Resources and Reiterating Request for Confidential Meeting and Extension of Time Subject: Motion in Compliance with the December 28 Order Submitting 167 MW of VPP Resources and Reiterating Request for Confidential Meeting and Extension of Time 31/enero/2022 2022/01/31 File
Resolution and Order Subject: Renewable Energy Generation and Energy Storage Resource Procurement Plan-First Tranche Projects for Phase III Contract Negotiation and Final Interconnection Plan 28/enero/2022 2022/01/28 File
Resolution and Order Subject: Appointment of Tranche 2 Independent Coordinator; scheduling of webinar 27/enero/2022 2022/01/27 File
Third Motion to Reiterate Request for Entry of Resolution and Order Detailing PREPA’s Role in the Tranche 2 RFP Process Subject: Third Motion to Reiterate Request for Entry of Resolution and Order Detailing PREPA’s Role in the Tranche 2 RFP Process 25/enero/2022 2022/01/25 File
Motion to Submit LUMA’s Presentation for Technical Conference Scheduled for January 25, 2022 Subject: Submittal of Presentation for Technical Conference 20/enero/2022 2022/01/20 File
Motion to Reiterate Request for Entry of Resolution and Order Detailing PREPA’s Role in the Tranche 2 RFP Process Subject: Motion to Reiterate Request for Entry of Resolution and Order Detailing PREPA’s Role in the Tranche 2 RFP Process 14/enero/2022 2022/01/14 File
CAMBIO Public Comments on the Energy Bureau and PREPA’s Ongoing Procurement of Renewable Energy and Storage Subject: CAMBIO public comments 11/enero/2022 2022/01/11 File
Motion to Restate Request to Lift Imposition of Sanction and Request for Reimbursement of Fine Paid Subject: Motion to Restate Request to Lift Imposition of Sanction and Request for Reimbursement of Fine Paid 31/diciembre/2021 2021/12/31 File
Resolution and Order Subject: Renewable Energy Generation and Energy Storage Resource Procurement Plan-First Tranche Projects for Phase III Contract Negotiation and Final Interconnection Plan 28/diciembre/2021 2021/12/28 File
Memorandum of Law in Support of Request for Confidential Treatment of Draft RFQ/RFP for IRP Consultant and Draft Contract Subject: Memorandum of Law in Support of Request for Confidential Treatment of Draft RFQ/RFP for IRP Consultant and Draft Contract Submitted on December 17, 2021 27/diciembre/2021 2021/12/27 File
Informative Motion Providing Update on Status and Timing of Selection of Virtual Power Plant Resources in Relation to the Tranche 1RFP Subject: Informative Motion Providing Update on Status and Timing of Selection of Virtual Power Plant Resources in Relation to the Tranche 1RFP 23/diciembre/2021 2021/12/23 File
Supplemental Motion Submitting PV Renewable Energy Draft Power Purchase and Operating Agreements (ESSA’s) As Well As Energy Storage Service Agreements (ESSA’s) As Part of PREPA’s Tranche 1 Renewable Generation and Energy Storage Resources RFP for Energy Bureau Evaluation and Approval Subject: Supplemental Motion Submitting PV Renewable Energy Draft Power Purchase and Operating Agreements (ESSA’s) As Well As Energy Storage Service Agreements (ESSA’s) As Part of PREPA’s Tranche […] 23/diciembre/2021 2021/12/23 File
Motion to Submit Report on Resource Planning Process for Next IRP Cycle and Draft RFQ-RFP Consultant and Request for Confidential Treatment Subject: Submittal of Report on Resource Planning Process for Next IRP Cycle and Draft RFQ- REP for IRP Consultant and Request for Confidential Treatment 17/diciembre/2021 2021/12/17 File
Motion Submitting 733 MW of PV Renewable Energy Draft Power Purchase and Operating Agreements Offered in Tranche 1 of PREPA’s Renewable Generation and Energy Storage Resources RFP for Energy Bureau Evaluation and Approval Subject: Motion Submitting 733 MW of PV Renewable Energy Draft Power Purchase and Operating Agreements Offered in Tranche 1 of PREPA’s Renewable Generation and Energy Storage Resources […] 16/diciembre/2021 2021/12/16 File
Resolution and Order Subject: Request for Additional Time to Submit the Resource Planning for the Next IRP Cycle and the Draft RFQ and RFP Consultant and Request to Schedule Technical […] 15/diciembre/2021 2021/12/15 File
Motion Requesting Expedited Appointment of the PREB Independent Coordinator and Resolution and Order Detailing PREPA Role in Anticipation for the Tranche 2 RFP Subject: Motion Requesting Expedited Appointment of the PREB Independent Coordinator and Resolution and Order Detailing PREPA Role in Anticipation for the Tranche 2 RFP 13/diciembre/2021 2021/12/13 File
Motion Submitting Updated Pricing Information Per Technology Group in Compliance with December 3, 2021, Resolution and Order Subject: Motion Submitting Pricing Information Per Technology Group in Compliance with December 3, 2021, Resolution and Order 08/diciembre/2021 2021/12/08 File
Resolution and Order Subject: Renewable Energy Generation and Energy Storage Resource Procurement Plan-First Tranche Projects for Phase III Contract Negotiation and Final Interconnection Plan Approvals 03/diciembre/2021 2021/12/03 File
SESA Comments and Request Regarding Tranche 1 and Tranche 2 Renewable Generation and Energy Storage Resource Procurement; NEPR-MI-2020-0012 Subject: SESA Comments 03/diciembre/2021 2021/12/03 File
Informative Motion on Timeline to Submit the Report on Resource Planning for the Next IRP Cycle and the Draft RFQ and RFP for IRP Consultant and Request for Additional Time Subject: Informative Motion on Timeline to Submit the Report on Resource Planning for the Next IRP Cycle and the Draft RFQ and RFP for IRP Consultant and […] 30/noviembre/2021 2021/11/30 File
Motion Requesting Limited Extension of Time of Seven (7) Days to Finalize Phase III of the Tranche I Renewables RFP Subject: Motion Requesting Limited Extension of Time of Seven (7) Days to Finalize Phase III of the Tranche I Renewables RFP 18/noviembre/2021 2021/11/18 File
Motion Submitting Copies of Communications to Proponents Selected to Proceed to Phase III Related to the Tranche 1 RFP Subject: Motion submitting Information Relates to Phase III of the Tranche I RFP in compliance with November 8 Resolution and Order 12/noviembre/2021 2021/11/12 File
Motion Submitting Pricing Information Per Technology Group Regarding the Tranche 1 RFP and Request to Lift Imposition of Sanctions Subject: Motion Submitting Pricing Information Per Technology Group Regarding the Tranche 1 RFP and Request to Lift Imposition of Sanctions 09/noviembre/2021 2021/11/09 File
Resolution and Order Subject: Noncompliance with Request for Submittal of the Results of Selection of Proposals for Phase III Evaluation and Imposition of Administrative Fine 08/noviembre/2021 2021/11/08 File
Informative Motion on Status of Activities Related to Next IRP Cycle, Request for Extension to File Documents, and Request to Schedule Technical Conference Subject: Informative Motion on Status of Activities Related to Next IRP Cycle, Request for Extension to File Documents, and Request to Schedule Technical Conference 05/noviembre/2021 2021/11/05 File
Resolution and Order Subject: Energy Bureau-Appointed Independent Coordination for Tranche 2 RFP 29/octubre/2021 2021/10/29 File
Motion to Supplement Attachment a of «Response to, and Motion for Clarification of, October 12, 2021 Resolution and Order Addressing the Target Date for Issuance of the Tranche 2 RFP and Other Matters» Subject: Response to, and Motion for Clarification of, October 12, 2021 Resolution and Order Addressing the Target Date for Issuance of the Tranche 2 RFP and Other […] 19/octubre/2021 2021/10/19 File
Response to, and Motion for Clarification of, October 12, 2021 Resolution and Order Addressing the Target Date for Issuance of the Tranche 2 RFP and Other Matters Subject: Response to, and Motion for Clarification of Energy Bureau  Resolution and Order for October 12, 2021 Addressing Target Date for Issuance of Tranche 2 RFP and […] 15/octubre/2021 2021/10/15 File
Motion Submitting Tranche 2 Request for Proposals for Renewable Energy Generation and Energy Storage Resources Subject: Appendix G_ESSA_01_Standalone_RE RFP 2 (Draft Publication Version) 15/octubre/2021 2021/10/15 File
Motion Submitting Tranche 2 Request for Proposals for Renewable Energy Generation and Energy Storage Resources Subject: Appendix R_ESSA_01_ITC Compliant_RE RFP 2 (Draft Publication Version) 15/octubre/2021 2021/10/15 File
Motion Submitting Tranche 2 Request for Proposals for Renewable Energy Generation and Energy Storage Resources Subject: Tranche 2_RE RFP (Draft Publication Version) 15/octubre/2021 2021/10/15 File
Motion Submitting Tranche 2 Request for Proposals for Renewable Energy Generation and Energy Storage Resources Subject: Appendix Q_GSA_01_RE RFP 2 (DRAFT Publication Version) 15/octubre/2021 2021/10/15 File
Motion Submitting Tranche 2 Request for Proposals for Renewable Energy Generation and Energy Storage Resources Subject: Appendix F_PPOA_01_RE RFP 2 (Draft Publication Version) 15/octubre/2021 2021/10/15 File
Motion Submitting Tranche 2 Request for Proposals for Renewable Energy Generation and Energy Storage Resources Subject: Appendix D_Proposal Data Forms 15/octubre/2021 2021/10/15 File
Motion Submitting Tranche 2 Request for Proposals for Renewable Energy Generation and Energy Storage Resources Subject: Tranche 2 RFP 15/octubre/2021 2021/10/15 File
Documento no encontrado. Subject: Appendix F_PPOA_01_RE RFP 2 (Draft Publication Version) 13/octubre/2021 2021/10/13
Resolution and Order Subject: Target Date for Issuance of Tranche 2 RFP 12/octubre/2021 2021/10/12 File
Motion to Submit Timeline of Anticipated Installations of Battery Storage and Renewable Energy Resources Subject: Motion to Submit Timeline of Anticipated Installations of Battery Storage and Renewable Energy Resources 24/septiembre/2021 2021/09/24 File
Motion to Submit Proposals Under Seal and Request for Confidential Designation Subject: Motion to Submit Proposals Under Seal and Request for Confidential Designation 20/septiembre/2021 2021/09/20 File
Motion to Clarify Request for Extension of Dates for Notification of Proponents Being Selected for Phase III Negotiations and for Submission of Pricing Information Per Technology Group Subject: Motion to Clarify Request for Extension of Dates for Notification of Proponents Being Selected for Phase III Negotiations and for Submission of Pricing Information Per Technology […] 19/septiembre/2021 2021/09/19 File
Motion for Extension of Dates for Notification of Proponents Being Selected for Phase III Negotiations, for Submission of Pricing Information per Technology Group and for Additional Time to Issue the Tranche 2 RFP Subject: Request to Extend Dates for Notification of Proponents Selected  to Proceed to Phase III  and Modification of Target Date for Issuance of Tranche 2 RFP 17/septiembre/2021 2021/09/17 File
Resolution and Order Subject: Target Date for Issuance of Tranche 2 RFP 17/septiembre/2021 2021/09/17 File
Resolution and Order Subject: Joint motion Requesting Clarification of July 23, 2021 Resolution and Order 15/septiembre/2021 2021/09/15 File
Joint Motion Requesting Clarification of a Portion of the Energy Bureau’s Resolution and Order of July 23, 2021 Subject: Request for Clarification of a Portion of Energy Bureau’s Resolution and Order of July 23, 2021 10/septiembre/2021 2021/09/10 File
Comments Alten Energy Subject: Comments Alten Energy 09/septiembre/2021 2021/09/09 File
Motion for Extension of Time to Submit Information Requested on Resolution and Order Dated August 26, 2021, Including Information Related to Pricing Subject: Request For Information and Target Date for Issuance of Tranche 2 RFP 08/septiembre/2021 2021/09/08 File
SESA Concerns Regarding Tranche 1 and Tranche 2 Renewable Generation and Energy Storage Resource Procurement Subject: SESA Concerns Regarding Tranche 1 and Tranche 2 Renewable Generation and Energy Storage Resource Procurement 26/agosto/2021 2021/08/26 File
Resolution and Order Subject: Request for information and Target Date for Insurance of Tranche 2 RFP 26/agosto/2021 2021/08/26 File
Motion to Submit Responses in Compliance with Resolution and Order Entered on August 6, 2021 Subject: Motion to Submit Responses in Compliance with Resolution and Order Entered on August 6, 2021 13/agosto/2021 2021/08/13 File
Motion to Submit Responses to in Compliance with Resolution and Order Entered on August 6, 2021 Subject: Motion to Submit Responses to in Compliance with Resolution and Order Entered on August 6, 2021 13/agosto/2021 2021/08/13 File
Resolution and Order Subject: Request for Information 06/agosto/2021 2021/08/06 File
Joint Motion to Revised Update Procurement Plan Subject: Joint Motion to Submit Revised Update Procurement Plan 23/julio/2021 2021/07/23 File
Resolution and Order Subject: Wind  Study 23/julio/2021 2021/07/23 File
Motion to Inform and Request for Extension of Time Subject: Motion to Inform and Request for Extension of Time 20/julio/2021 2021/07/20 File
Motion to Submit Presentation to be Projected by PREPA During the July 6, 2021 Technical Conference Subject: Motion to Submit Presentation to be Projected by PREPA During the July 6, 2021 Technical Conference 06/julio/2021 2021/07/06 File
Notice of Appearance and Request for Notice Subject: Notice of Appearance and Request for Notice 02/julio/2021 2021/07/02 File
SESA Comments and Request on PREPA Motions Regarding Tranche 1 and Tranche 2 Renewable Generation and Energy Storage Resource Procurement Subject: SESA Comments 01/julio/2021 2021/07/01 File
Urgent Motion for Reconsideration of the June 30, 2021 Order Subject: Urgent Motion for Reconsideration of the June 30, 2021 Order 01/julio/2021 2021/07/01 File
Resolution and Orden Subject: Request for Extension of Time for filing of Presentation and Rescheduling of Technical Conference 01/julio/2021 2021/07/01 File
Resolution and Prder Subject: Request for Extension of Time for filing of Presentation and Rescheduling of Technical Conference 30/junio/2021 2021/06/30 File
Request of The Puerto Rico Electric Power Authority for Extension of Time to File Presentation on Changes Incorporated in Updated Procurement Plan and for a Continuance of the Technical Conference Currently Scheduled for July 6, 2021 Subject: Request for Extension of Time to File Presentation on Update Procurement Plan and for Continuance of Technical  Conference Required by June 24,2021 Resolution and Order   […] 29/junio/2021 2021/06/29 File
Motion in Compliance with Order Entered on June 14, 2021 Submitting Redline Version of the Updated Procurement Plan Subject: Update Procurement Plan 28/junio/2021 2021/06/28 File
Resolution And Order Subject: Update Procurement Plan 24/junio/2021 2021/06/24 File
SESA’s Comments on PREPA’s Motion on Updated Procurement Plan Addressing the Second Renewable Generation and Energy Storage Resource Procurement Tranche Subject: SESA’s Comments on PREPA’s Motion on Updated Procurement Plan Addressing the Second Renewable Generation and Energy Storage Resource Procurement Tranche 24/junio/2021 2021/06/24 File
Motion to Submit Updated Procurement Plan Addressing Plans for the Second Renewable Generation and Energy Storage Resource Procurement Tranche Subject: Updated Procurement Plan 15/junio/2021 2021/06/15 File
Resolution and Order Subject: Request for Extension of time 03/junio/2021 2021/06/03 File
Request of The Puerto Rico Electric Power Authority for Additional Time to Issue Second Renewable Generation and Energy Storage Resource Procurement Tranche and to Submit Timeline for Anticipated Installation of Battery Storage and Renewable Energy Resources Subject: Request  for Extensions of Time to Issue Tranche 2  Request for Proposals and to Submit Timeline for Anticipated Installation of Battery Storage and Renewable Energy Resources […] 29/mayo/2021 2021/05/29 File
Resolution and Order Subject: PREPA’s Response to May 21, 2021 Resolution and Order Addressing SESA Comments Request and Extension of Time for Submission of Proposals to Renewable Generation and Energy […] 27/mayo/2021 2021/05/27 File
Response of the Puerto Rico Electric Power Authority to May 21, 2021 Resolution and Order Addressing Comments Presented by the Solar and Energy Storage Association of Puerto Rico and Statement of Support for Extension of Time for Submission of Proposals in Renewable Generation and Energy Storage Resource RFP Tranche 1 Subject: PREPA’s Response to May 21, 2021 Resolution and Order Addressing SESA Request 24/mayo/2021 2021/05/24 File
Resolution and Order Subject: Request for Consideration of Content and Schedule Changes 21/mayo/2021 2021/05/21 File
SESA’s Further Comments on Implementation of PREPA’s Procurement Plan Subject: SESA’s Comments 19/mayo/2021 2021/05/19 File
Motion Submitting Detailed Plan to Address and Solve Any Potential Long-Term Renewable Energy Penetration Issues Subject: Plan to Address and Solve Potential Long-Term Renewable  Energy Penetration Issues 17/mayo/2021 2021/05/17 File
Resolution and Order Subject: Request for Extension of Time to File Update Procurement Plan Required by December 8, 2020 Resolution and Order 11/mayo/2021 2021/05/11 File
Request of the PREPA for Extension of Time to File an Updated Procurement Plan Addressing Plans for the Second Renewable Generation and Energy Storage Resource Procurement Tranche Subject: Request for Extension of Time to File an Updated Procurement Plan Required by December 8, 2020 Resolution and Order 30/abril/2021 2021/04/30 File
SESA’s Comments on Implementation of PREPA’s Procurement Plan Subject: SESA’s Comments 21/abril/2021 2021/04/21 File
Comentarios Solaner Puerto Rico One LLC- Informe sobre Criterios para Evaluar Proyectos Renovables Subject: Comentarios Solaner Puerto Rico One, LLC 06/abril/2021 2021/04/06 File
Motion Requesting Extension of Time to Submit Detailed Plan to Address and Solve Any Potential Long-Term Renewable Energy Penetration Issues Subject: Extension of Time to Submit Plan to Address and Solve Any Potential Long-Term Renewable Energy Penetration Issues 31/marzo/2021 2021/03/31 File
Moción sobre Intervención o Participación, Solicitud de Cumplimiento de Ley y Otros Remedios Subject: Solicitud de Cumplimiento de Ley 15/marzo/2021 2021/03/15 File
Motion in Compliance with Order Submitting Information on Weighted Criteria Used to Evaluate and Choose the Projects to Acquire 150 MW of Renewable Energy Subject: Motion in Compliance with February 3, 2021 Orden, and Request for Confidential Treatment 15/marzo/2021 2021/03/15 File
Motion Compliance with Order Submitting Redacted List of Projects PREPA will Potentially Choose to Acquire 150 MW of Renewable Energy Subject: Motion to Compliance with February 3, 2021 Order, and Request for Confidential Treatment 08/marzo/2021 2021/03/08 File
Resolution and Order Subject: Motion in Compliance with February  3, 2021 Order, and Request for Confidential  Treatment of Information 03/marzo/2021 2021/03/03 File
Motion to Clarify PREPA’s Webpage Public Link Access to Renewables RFP Tranche 1 Subject: Issuance of Renewables RFP Tranche 1 24/febrero/2021 2021/02/24 File
Motion Informing Issuance of Renewables RFP Tranche 1 Subject: Issuance of Renewables RFP Tranche 1 22/febrero/2021 2021/02/22 File
Motion in Compliance with Order Submitting Responses to Stakeholder’s Questions Subject: Issuance of RFP and timeline for filing responses to questions received from stakeholders 16/febrero/2021 2021/02/16 File
Comentarios – PBJL Energy Corporation Subject: Comentarios – PBJL Energy Corporation – NEPR-MI-2020-0012 16/febrero/2021 2021/02/16 File
Motion Compliance with Order Submitting List of Projects PREPA will Potentially Choose to Acquire 150 MW Renewable Subject: Draft Procurement Plan 09/febrero/2021 2021/02/09 File
Motion Compliance with Order Submitting Renewables RFP Package with Modifications Requested by the Financial Oversight and Management Board for Puerto Rico and Draft Communications Subject: Draft Procurement Plan 05/febrero/2021 2021/02/05 File
Resolution and Order Subject: Modifications to RFP required by the Financial Oversight & Management Board for Puerto Rico 03/febrero/2021 2021/02/03 File
Motion Submitting Letter from the Financial Oversight and Management Board for Puerto Rico Regarding Procurement Plan and Renewables RFS Recommendation Subject: Letter for the Financial Oversight Management Board for Puerto Rico 29/enero/2021 2021/01/29 File
Resolution and Order Subject: Issuance of RFP and timeline for filing of responses to questions received for stakeholders 26/enero/2021 2021/01/26 File
SESA – Written Questions Regarding Pending PREPA RFP for 1000MW Renewable Energy & 500 MW Storage Subject: SESA – Written Questions Regarding Pending PREPA RFP for 1000MW Renewable Energy & 500 MW Storage – NEPR-MI-2020-0012 19/enero/2021 2021/01/19 File
Local Environmental Organizations’Additional Questions for PREPA Subject: Additional Question for PREPA 19/enero/2021 2021/01/19 File
Comentarios Alten Energy Subject: Comentarios Alten Energy 19/enero/2021 2021/01/19 File
Windmar-Stakeholders Meeting additional questions of Request for Proposals Subject: Additional questions of Request for Proposals 19/enero/2021 2021/01/19 File
Motion in Compliance with Order Submitting Preferred Interconnection Regions Map Subject: Draft  Procurement Plan 13/enero/2021 2021/01/13 File
Resolution Subject: Request for Confidential Designation and Treatment 12/enero/2021 2021/01/12 File
Motion for Reconsideration and Modification of January 7, 2021 Resolution on Request for Confidential Designation and Treatment of Identifying Preferred Locations for Interconnection Subject: Draft Procurement Plan – Request for Temporary Confidential Designation and Treatment of Preferred Interconnection Location Information 11/enero/2021 2021/01/11 File
Motion in Compliance with Order Submitting Redacted/ Public Versions of Request for Proposal (RFP) and Appendices Subject: 04 SL Renewable Integration Study of Puerto Rico 22Dec2020_Redacted_02 11/enero/2021 2021/01/11 File
Motion in Compliance with Order Submitting Redacted/ Public Versions of Request for Proposal (RFP) and Appendices Subject: 03 RE RFP_Appendix I_Interconnection_Wind 11/enero/2021 2021/01/11 File
Motion in Compliance with Order Submitting Redacted/ Public Versions of Request for Proposal (RFP) and Appendices Subject: 03 Solar PPOA_RE RFP_02 – Appendix E_Form of Solar PPOA 11/enero/2021 2021/01/11 File
Motion in Compliance with Order Submitting Redacted/ Public Versions of Request for Proposal (RFP) and Appendices Subject: 03 RE RFP_Appendix I_Interconnection_Solar 11/enero/2021 2021/01/11 File
Motion in Compliance with Order Submitting Redacted/ Public Versions of Request for Proposal (RFP) and Appendices Subject: 03 RE RFP_Appendix I_Interconnection_BESS 11/enero/2021 2021/01/11 File
Motion in Compliance with Order Submitting Redacted/ Public Versions of Request for Proposal (RFP) and Appendices Subject: 03 RE RFP_Appendix C_Proposal Data Forms 11/enero/2021 2021/01/11 File
Motion in Compliance with Order Submitting Redacted/ Public Versions of Request for Proposal (RFP) and Appendices Subject: 03 RE RFP_Appednix H_MTRs 11/enero/2021 2021/01/11 File
Motion in Compliance with Order Submitting Redacted/ Public Versions of Request for Proposal (RFP) and Appendices Subject: 03 RE RFP_02B (PREB Submittal Version II) 11/enero/2021 2021/01/11 File
Motion in Compliance with Order Submitting Redacted/ Public Versions of Request for Proposal (RFP) and Appendices Subject: 03 Appendix F_Form of Energy Storage Services Agreement – Appendix F_Form of Energy Storage Services Agreement Redacted 11/enero/2021 2021/01/11 File
Motion in Compliance with Order Submitting Redacted/ Public Versions of Request for Proposal (RFP) and Appendices Subject: 02 Procurement Plan Appendix B_22Dec2020 11/enero/2021 2021/01/11 File
Motion in Compliance with Order Submitting Redacted/ Public Versions of Request for Proposal (RFP) and Appendices Subject: Draft Procurement Plan 11/enero/2021 2021/01/11 File
Resolution Subject: Request for Confidential Designation and Treatment 07/enero/2021 2021/01/07 File
Resolution and Order Subject: Ruling on Motion titled Motion for Reconsideration of the Resolution and Order on the Evaluation of Puerto Rico Electric Power Authority’s Draft Procurement Plan. 07/enero/2021 2021/01/07 File
Motion to Submit Notarized Affidavit Subject: Draft Procurement Plan 23/diciembre/2020 2020/12/23 File
Request for Confidencial Designation and Supporting Memorandum of Law Subject: Draft Procurement Plan 23/diciembre/2020 2020/12/23 File
Motion in Compliance with Order Submitting Final Procurement Plan and Associated Request for Proposal Subject: Draft Procurement Plan 22/diciembre/2020 2020/12/22 File
Motion for Reconsideration of Resolution and Order on Draft Procurement Plan Subject: Draft Procurement Plan 22/diciembre/2020 2020/12/22 File
Request for Term to Submit Affidavit and Apostille Subject: Draft Procurement Plan 22/diciembre/2020 2020/12/22 File
Resolution and Order Subject: Evaluation of Draft Procurement Plan 08/diciembre/2020 2020/12/08 File
PREPA-Third Motion Reiterating Request for Technical Conference Subject: Procurement Plan 02/diciembre/2020 2020/12/02 File
Motion to Reiterate Request for Technical Conference Subject: Procurement Plan 23/noviembre/2020 2020/11/23 File
Motion to Submit Presentation for Technical Conference No subject available. 17/noviembre/2020 2020/11/17 File
Resolution and Order Subject: Notice of Appearance 06/noviembre/2020 2020/11/06 File
Request for Technical Conference Subject: Procurement Plan 05/noviembre/2020 2020/11/05 File
Motion Submitting Draft Procurement Plan Subject: Draft Procurement Plan 23/octubre/2020 2020/10/23 File
Local Environmental Organization’ Public Comment on PREPA Status Report Subject: Public Comment on PREPA Status Report 20/octubre/2020 2020/10/20 File
Motion Clarify Subject: Procurement Plan 09/octubre/2020 2020/10/09 File
Resolution and Order Subject: Resolution and Order opening the instant docket to implement the Puerto Rico Electric Power Authority’s Integrated Resource Plan and Modified Action Plan 06/octubre/2020 2020/10/06 File
Notice of Appearance and Request for Notice Subject: Notice od Appearance. 06/octubre/2020 2020/10/06 File
Second Request for Technical Conference Subject: Procurement Plan 02/octubre/2020 2020/10/02 File
Presentation of Status Report on the Development of PREPA’s Draft Procurement Plan Subject: Procurement Plan 23/septiembre/2020 2020/09/23 File

Antonio Torres-Miranda is presently an Associate Commissioner for the Energy Bureau of the Puerto Rico Public Service Regulatory Board (Energy Bureau). Previously, Mr. Torres had been the Director of the Legal Advisory Division of the Energy Bureau.

Mr. Torres has a bachelor’s degree in mechanical engineering from the University of Puerto Rico. He also has a master’s degree in engineering management from the Polytechnical University of Puerto Rico. In the 1990’s he passed the exam to be a Certified Energy Manager. He is presently a member of the Puerto Rico Professional College of Engineer and Land Surveyors.

Mr. Torres graduated with honors from the Interamerican University of Puerto Rico where he obtained his Juris Doctor degree. He is presently member of the bar of the Commonwealth of Puerto Rico and is a member of the U.S. District of Puerto Rico Federal bar.

He commenced his engineering work experience with the Department of Defense in a Naval base in Virginia were he designed industrial ventilation systems. He then went to New York to work with Kennetech Energy Management were he first commenced being immersed in the energy sector. He then transferred to Puerto Rico with Kennetech in which he conducted wind studies throughout the island together with U.S. Wind Power. He continued implementation of energy management systems in several industrial companies throughout Puerto Rico until Kennetech joined forces with Enron to develop the first privately owned power plant in Puerto Rico known as EcoElectrica. This 450 MW natural gas power plant included the development of the first LNG terminal in Puerto Rico.

He also worked as a contractor with the Puerto Rico Electric Power Authority in the development of a 42 miles natural gas pipeline.

Before joining the Energy Bureau Mr. Torres developed several natural gas projects in Puerto Rico.

Ferdinand Ramos-Soegaard attained a bachelor’s degree in electrical engineering (BSEE) graduating from the Georgia Institute of Technology in Atlanta, GA in 2000. His degree specialized in power distribution and telecommunications systems.

Mr. Ramos-Soegaard is a licensed professional engineer in the Commonwealth of Puerto Rico and the state of Florida. Throughout his professional carrier Mr. Ramos has been involved in all aspects of the design, construction and maintenance of electrical distribution systems, including high voltage transmission lines and renewable energy interconnections to the Puerto Rico Electric Power Authority subtransmission grid.

Sylvia B. Ugarte Araujo holds a bachelor’s degree in industrial and Systems Engineering from the University of Florida (1998). She studied at the Inter-American University of Puerto Rico School of Law (2004) and then obtained a Master of Laws from the Inter-American University of Puerto Rico (2019). Ms. Ugarte is admitted to the practice of law and notary by the Supreme Court of Puerto Rico (2004), the Federal Court for the District of Puerto Rico, for the First Circuit of Boston (2005), the Court of Appeals of the First Circuit (2005) and the Supreme Court of Texas (2018). She was Director of the Office of Legal Counsel of the Energy Bureau of the Public Service Regulatory Board and the Designated Director of the Office of Legal Counsel of the Public Service Regulatory Board. She has served as Legal Director of the Puerto Rico Infrastructure Financing Authority and has worked with renowned law firms. She has over fifteen (15) years of vast professional experience as a trial attorney with an emphasis on commercial and construction litigation and extensive experience in administrative law. Also, as an industrial engineer she has been a consultant for government agencies in charge of large projects and in private entities.

Lillian Mateo-Santos obtained her Bachelor’s Degree in Business Administration from the University of Puerto Rico, Río Piedras Campus, in 1993 and a Juris Doctor degree from the University of Puerto Rico School of Law in 1996. In 1999, she obtained a degree of Masters of Laws (LLM) in Environmental and Energy of the Tulane University Law School. Before joining the Puerto Rico Energy Bureau, Ms. Mateo-Santos was a member of various law firms. Her private practice was focused on energy, environmental, land use and permitting matters, including administrative law litigation.

On June 5, 2019, Ms. Mateo-Santos was elected 2nd Vice President of the Southeastern Association of Regulatory Utility Commissioners (SEARUC). She is a member of the American Bar Association and is admitted to practice law and notary law in Puerto Rico, and the United States Court of Appeals for the First Circuit.

Edison Avilés-Deliz obtained his Bachelor of Science in Electrical Engineering with specialties in Power and Control Systems (BSEE) Cum Laude from the University of Puerto Rico, Mayagüez Campus in 1991 and a Juris Doctor (JD) also Cum Laude from the University of Puerto Rico School of Law in 1997. In addition, he holds Master degrees with Distinctions in Diplomacy/International Relations/Business (MA) from Norwich University in Vermont and in Energy Law from Vermont Law School (LLM).

Avilés-Deliz is a licensed engineer and member of the College of Engineers and Surveyors of Puerto Rico (CIAPR). He was president of the Disciplinary and Professional Ethics Tribunal of the CIAPR, of the Institute of Electrical Engineers of CIAPR and of the Society of Electrical Engineers of Puerto Rico. He is admitted to practice as a public notary in Puerto Rico and as a lawyer, both in the District Court of Puerto Rico and the Court of Appeals for the First Federal Circuit.

He is a member of Phi Eta Mu Fraternity, the Engineering Honor Society Tau Beta Pi, and the International Studies Honor Society Sigma Iota Rho. He is also a Senior member of the IEEE.

Antonio Torres-Miranda es actualmente Comisionado Asociado del Negociado de Energía de la Junta Reglamentadora de Servicios Públicos de Puerto Rico (Negociado de Energía). Anteriormente, el Sr. Torres había sido Director de la División de Asesoría Legal del Negociado de Energía.

El Sr. Torres tiene un bachillerato en ingeniería mecánica de la Universidad de Puerto Rico. También tiene una maestría en administración de ingeniería de la Universidad Politécnica de Puerto Rico. En la década de 1990 aprobó el examen para ser Gerente de Energía Certificado. Actualmente es miembro del Colegio de Ingenieros y Agrimensores de Puerto Rico.

El Sr. Torres se graduó con honores de la Universidad Interamericana de Puerto Rico donde obtuvo su título de Juris Doctor (JD). Actualmente es miembro del Colegio de Abogados del Estado de Puerto Rico y es miembro del Colegio de Abogados Federal del Distrito de Puerto Rico de los Estados Unidos.

Comenzó su experiencia laboral en ingeniería con el Departamento de Defensa en una base naval en Virginia donde diseñó sistemas de ventilación industrial. Luego se fue a Nueva York para trabajar con Kennetech Energy Management, donde comenzó a sumergirse en el sector energético. Luego se transfirió a Puerto Rico con Kennetech, donde realizó estudios eólicos en toda la isla U.S. Wind Power. Continuó con la implementación de sistemas de administración de energía en varias empresas industriales en todo Puerto Rico hasta que Kennetech unió fuerzas con Enron para desarrollar la primera planta de energía de propiedad privada en Puerto Rico conocida como EcoEléctrica. Esta planta de energía de gas natural de 450 MW incluyó el desarrollo de la primera terminal de GNL en Puerto Rico.

También trabajó como contratista con la Autoridad de Energía Eléctrica de Puerto Rico en el desarrollo de una tubería de gas natural de 42 millas.

Antes de unirse al Negociado de Energía, el Sr. Torres desarrolló varios proyectos de gas natural en Puerto Rico.

La Lcda. Sylvia B. Ugarte Araujo posee un Bachillerato en Ingeniería Industrial y de Sistemas de la Universidad de la Florida (1998). Estudió en la Escuela de Derecho de la Universidad Interamericana de Puerto Rico (2004) y luego obtuvo una Maestría en Derecho de la Universidad Interamericana de Puerto Rico (2019). La Lcda. Ugarte está admitida a la práctica de la abogacía y la notaría por el Tribunal Supremo de Puerto Rico (2004), al Tribunal Federal, Distrito de Puerto Rico, al Primer Circuito Federal de Boston (2005), al Tribunal de Apelaciones del Primer Circuito (2005) y al Tribunal Supremo de la jurisdicción del estado de Texas (2018). Fue Directora de la Oficina de Asesoramiento Legal del Negociado de Energía de la Junta Reglamentadora de Servicio Público y la Directora Designada de la Oficina de Asesoramiento Legal de la Junta Reglamentadora de Servicio Público. Ha ejercido como Directora Legal de la Autoridad para el Financiamiento de la Infraestructura de Puerto Rico y ha trabajado con bufetes de abogado de renombre. Tiene sobre quince (15) años de vasta experiencia profesional como abogada litigante con énfasis en litigio comercial y construcción y una amplia experiencia en derecho administrativo. Así también, como ingeniera industrial ha sido consultora para agencias gubernamentales encargadas de proyectos de envergadura y en entidades privadas.

Ferdinand A. Ramos-Soegaard obtuvo su Bachillerato en Ciencias en Ingeniería Eléctrica (BSEE, por sus siglas en inglés) del Georgia Institute of Technology en Atlanta, GA en el 2000, con especialidad en sistemas de distribución de potencia y telecomunicaciones.

Ramos-Soegaard es ingeniero licenciado en el Estado Libre Asociado de Puerto Rico y en el Estado de Florida. A través de su carrera profesional, Ramos-Soegaard ha estado envuelto en todos los aspectos del diseño, construcción y mantenimiento de sistemas de distribución eléctrica, incluyendo líneas de transmisión de alto voltaje e interconexiones de sistemas de energía renovable a la red de subtransmisión de la Autoridad de Energía Eléctrica de Puerto Rico.

Lillian Mateo-Santos obtuvo su Bachillerato en Administración de Empresas de la Universidad de Puerto Rico, Recinto de Río Piedras en 1993 y el grado de Juris Doctor de la Facultad de Derecho de la Universidad de Puerto Rico en 1996. En 1999 obtuvo una Maestría en Derecho (LLM) en Ambiental y Energía de la Facultad de Derecho de la Universidad de Tulane. Antes de formar parte del Negociado de Energía de Puerto Rico, la Lic. Mateo-Santos fue miembro de varios bufetes de abogados. Su práctica privada se enfocó en asuntos de energía, ambiental, uso de terrenos y permisos, incluyendo litigación de derecho administrativo.

El 5 de junio de 2019, la Lic. Mateo-Santos fue elegida 2nda Vice Presidenta del Southern Association of Regulatory Utility Commissioners (SEARUC). Es miembro de la American Bar Association y está admitida para ejercer como abogado y notario público en Puerto Rico, y en el Tribunal de Apelaciones para el Primer Circuito Federal.

Edison Avilés-Deliz obtuvo su bachillerato Cum Laude en Ingeniería Eléctrica con especialidades en Sistemas de Controles y Potencia (BSEE) de la Universidad de Puerto Rico, Recinto de Mayagüez en 1991 y un Juris Doctor (JD) también Cum Laude de la Facultad de Derecho de la Universidad de Puerto Rico en 1997. Además, ostenta maestrías con Distinciones en Diplomacia/Relaciones Internacionales/Negocios (MA) de la Universidad de Norwich en Vermont y en Derecho en Energía de la Universidad de Derecho de Vermont (LLM).

Avilés-Deliz es ingeniero licenciado y miembro del Colegio de Ingenieros y Agrimensores de Puerto Rico (CIAPR). Fue presidente del Tribunal Disciplinario y de Ética Profesional del CIAPR, del Instituto de Ingenieros Electricistas del CIAPR y de la Sociedad de Ingenieros Electricistas de Puerto Rico. Está admitido para ejercer como notario público en Puerto Rico y como abogado, tanto en el Tribunal de Distrito de Puerto Rico como el Tribunal de Apelaciones para el Primer Circuito Federal.

Pertenece a la fraternidad Phi Eta Mu, a la Sociedad de Honor de Ingeniería Tau Beta Pi, a la Sociedad de Honor de Estudios Internacionales Sigma Iota Rho. También es miembro senior de la IEEE.