NEPR-MI-2024-0005

Expediente: NEPR-MI-2024-0005
IN RE: PLAN PRIORITARIO PARA LA ESTABILIZACIÓN DE LA RED ELÉCTRICA
Documentos Publicados: 135
Documentos Fecha Orden Descargar
Exhibit 2 Vegetation Maintenance and Clearing (June 2026) Asunto: Exhibit 2 Vegetation Maintenance and Clearing (June 2026) 29/junio/2026 2026/06/29 Documento
Exhibit 3 (51) Line Segments (June 2026) Asunto: Exhibit 3 (51) Line Segments (June 2026) 29/junio/2026 2026/06/29 Documento
Motion to Submit June 2026 Monthly Collaborative Report in Compliance with Resolutions and Orders of March 28, 2025, and February 18, 2026, and Request for Clarification Asunto: Motion to Submit June 2026 Monthly Collaborative Report in Compliance with Resolutions and Orders of March 28, 2025, and February 18, 2026, and Request for Clarification 29/junio/2026 2026/06/29 Documento
Informative Motion Regarding Exhibit 1 of the «Motion to Submit LUMA’s Comprehensive Transmission Plan Report» Filed on June 1, 2026, and Request for Confidential Treatment Asunto: Informative Motion Regarding Exhibit 1 of the «Motion to Submit LUMA’s Comprehensive Transmission Plan Report» Filed on June 1, 2026, and Request for Confidential Treatment 02/junio/2026 2026/06/02 Documento
Vegetation Maintenance and Vegetation Clearing spreadsheet Asunto: Exhibit 2 Vegetation Maintenance and Clearing (May 2026) 27/mayo/2026 2026/05/27 Documento
Complete Transmission Line Hardening & Maintenance spreadsheet Asunto: Exhibit 3_ (51) Line Segments (May 2026) 27/mayo/2026 2026/05/27 Documento
Motion to Submit May 2026 Monthly Collaborative Report in Compliance with Resolutions and Orders of March 28, 2025, and February 18, 2026, and Request for Clarification Asunto: Motion to Submit May 2026 Monthly Collaborative Report in Compliance with Resolutions and Orders of March 28, 2025, and February 18, 2026, and Request for Clarification 27/mayo/2026 2026/05/27 Documento
Motion to Submit April 2026 Monthly Collaborative Report in Compliance with Resolutions and Orders of March 28, 2025, and February 18, 2026 and Request for Clarification Asunto: Motion to Submit April 2026 Monthly Collaborative Report in Compliance with Resolutions and Orders of March 28, 2025, and February 18, 2026 and Request for Clarification 27/abril/2026 2026/04/27 Documento
Urgent Request for Extension of Time to Submit the Comprehensive Transmission Plan Asunto: Urgent Request for Extension of Time to Submit the Comprehensive Transmission Plan 24/abril/2026 2026/04/24 Documento
Motion to Submit March 2026 Monthly Collaborative Report in Compliance with Resolutions and Order of March 28, 2025, and February 18, 2026 and Request for Clarification Asunto: LUMA –  Exhibit 3_(51) Line Segments 27/marzo/2026 2026/03/27 Documento
Motion to Submit March 2026 Monthly Collaborative Report in Compliance with Resolutions and Order of March 28, 2025, and February 18, 2026 and Request for Clarification Asunto: LUMA – Exhibit 2_Vegetation Maintenance and Clearing 27/marzo/2026 2026/03/27 Documento
Motion to Submit March 2026 Monthly Collaborative Report in Compliance with Resolutions and Order of March 28, 2025, and February 18, 2026 and Request for Clarification Asunto: LUMA – Motion to Submit March 2026 Monthly Collaborative Report in Compliance with Resolutions and Order of March 28, 2025, and February 18, 2026 and Request […] 27/marzo/2026 2026/03/27 Documento
Motion to Submit February 2026 Monthly Collaborative Report in Compliance with Resolution and Orders of March 28, 2025, and February 18, 2026 Asunto: LUMA –  Exhibit 3_51-Line Segements Motion Submit Feb 2026 Monthly Collaborate Report 27/febrero/2026 2026/02/27 Documento
Motion to Submit February 2026 Monthly Collaborative Report in Compliance with Resolution and Orders of March 28, 2025, and February 18, 2026 Asunto: LUMA – Exhibit 2_Vegetation Maintenance and Clearing Motion Submit Feb 2026 Monthly Collaborate Report 27/febrero/2026 2026/02/27 Documento
Motion to Submit February 2026 Monthly Collaborative Report in Compliance with Resolution and Orders of March 28, 2025, and February 18, 2026 Asunto: LUMA – Motion to Submit February 2026 Monthly Collaborative Report in Compliance with Resolution and Orders of March 28, 2025, and February 18, 2026 27/febrero/2026 2026/02/27 Documento
Resolution and Order Asunto: Resolution and Order – Monthly Report 18/febrero/2026 2026/02/18 Documento
Resolution Asunto: PREPA’s Second Proposed Contract Resulting from Temporary Emergency Power Generation 02/febrero/2026 2026/02/02 Documento
Motion to Submit January 2026 Monthly Collaborative Report in Compliance with Resolution and Order of March 28, 2025 Asunto: Motion to Submit January 2026 Monthly Collaborative Report in Compliance with Resolution and Order of March 28, 2025 27/enero/2026 2026/01/27 Documento
Motion Submitting the Second Proposed Contract Resulting from Temporary Emergency Power Generatiion RFP for the Energy Bureau’s Review and Approval and Memorandum of Law in Support of Request for Confidential Treatment Asunto: PREPA – Motion Submitting the Second Proposed Contract Resulting from Temporary Emergency Power Generatiion RFP for the Energy Bureau’s Review and Approval and Memorandum of Law […] 23/enero/2026 2026/01/23 Documento
Motion to Vacate Resolution and Order of December 11, 2025 Asunto: Reporting Directives and Information Requirement regarding PREPA’s Proposed Contract Resulting from Temporary Emergency Power Generation 29/diciembre/2025 2025/12/29 Documento
Memorandum of Law in Suport of Confidential Treatment of Redacted Language and Exhibits 7 to 9 of Javelin’s Motion to Vacate Resolution and Order of December 11, 2025 Asunto: Directives regarding PREPA’s Proposed Contract Resulting from Temporary Emergency Power Generation 29/diciembre/2025 2025/12/29 Documento
Motion to Submit December 2025 Monthly Collaborative Report in Compliance with Resolution and Order of March 28, 2025 Asunto: Motion to Submit December 2025 Monthly Collaborative Report in Compliance with Resolution and Order of March 28, 2025 29/diciembre/2025 2025/12/29 Documento
Resolution and Orden Asunto: PREPA’s First Proposed Contract Resulting from Temporary Emergency Power Generation. 11/diciembre/2025 2025/12/11 Documento
Resolution Asunto: Reporting Directives and Information Requirement regarding PREPA’s Proposed Contract Resulting from Temporary Emergency Power Generation. 13/noviembre/2025 2025/11/13 Documento
Motion to Submit October 2025 Monthly Collaborative Report in Compliance with Resolution and Order of March 28, 2025 Asunto: LUMA – Motion to Submit October 2025 Monthly Collaborative Report in Compliance with Resolution and Order of March 28, 2025 27/octubre/2025 2025/10/27 Documento
Notice of Official Email Address and Request for Notice Asunto: PREPA – Notice of Official Email Address and Request for Notice 23/octubre/2025 2025/10/23 Documento
 Motion in Compliance with October 10, 2025, Resolution and Order and Memorandum of Law in Support of Request for Confidential Treatment Asunto: Reporting Directives and Information Requirement regarding PREPA’s Proposed Contract Resulting from Temporary Emergency Power Generation 15/octubre/2025 2025/10/15 Documento
Notice of Appearance, Request for Notice and Withdrawal as Attorney of Record Asunto: PREPA -Notice of Appearance, Request for Notice and Withdrawal as Attorney of Record 14/octubre/2025 2025/10/14 Documento
Resolution and Order Asunto: Reporting Directives and Information Requirement regarding PREPA’s Proposed Contract Resulting from Temporary Emergency Power Generation 10/octubre/2025 2025/10/10 Documento
Motion in Compliance with Resolution and Order Dated August 28, 2025 Asunto: PREPA – Motion in Compliance with Resolution and Order Dated August 28, 2025 29/septiembre/2025 2025/09/29 Documento
Motion to Submit September 2025 Monthly Collaborative Report in Compliance with Resolution and Order of March 28, 2025 Asunto: LUMA – Motion to Submit September 2025 Monthly Collaborative Report in Compliance with Resolution and Order of March 28, 2025 26/septiembre/2025 2025/09/26 Documento
Motion Requesting Extension of Time to Comply with Resolution and Order of August 28, 2025 Asunto: PREPA – Motion Requesting Extension of Time to Comply with Resolution and Order of August 28, 2025 08/septiembre/2025 2025/09/08 Documento
Motion in Compliance with the August 1, 2025 Resolution and Order Regarding the Fuel-Security Contingency Plan Asunto: PREPA – Motion in Compliance with the August 1, 2025 Resolution and Order Regarding the Fuel-Security Contingency Plan 08/septiembre/2025 2025/09/08 Documento
Motion in Compliance with Resolution and Order of August 28, 2025, Request for Confidential Treatment and Supporting Memorandum of Law Asunto: LUMA – Exhibit 3 Motion Req Ext of Time to Comply with Resol Aug 28 2025 08/septiembre/2025 2025/09/08 Documento
Motion in Compliance with Resolution and Order of August 28, 2025, Request for Confidential Treatment and Supporting Memorandum of Law Asunto: LUMA – Motion in Compliance with Resolution and Order of August 28, 2025, Request for Confidential Treatment and Supporting Memorandum of Law 08/septiembre/2025 2025/09/08 Documento
Resolution and Order Asunto: Compliance with Priority Stabilization Plan; FEMA Formulation Practices. 28/agosto/2025 2025/08/28 Documento
Motion to Submit August 2025 Monthly Collaborative Report in Compliance with Resolution and Order of March 28, 2025 Asunto: LUMA – Motion to Submit August 2025 Monthly Collaborative Report in Compliance with Resolution and Order of March 28, 2025 27/agosto/2025 2025/08/27 Documento
Confidential Informative Motion and Request for Clarifying Resolution Asunto: IN RE: Electric System Priority Stabilization Plan 18/agosto/2025 2025/08/18 Documento
Motion in Compliance with the August 1, 2025 Resolution and Order Regarding the Fuel – Security Contingency Plan Asunto: PREPA – Motion in Compliance with the August 1, 2025 Resolution and Order Regarding the Fuel – Security Contingency Plan 08/agosto/2025 2025/08/08 Documento
Motion in Compliance with Order of August 1, 2025 Asunto: Genera – Motion in Compliance with Order of August 1, 2025 07/agosto/2025 2025/08/07 Documento
Informative Motion Regarding Partial Compliance with Resolution and Order of August 1, 2025 and Request for Brief Extension of Time Asunto: Informative Motion Regarding Partial Compliance with Resolution and Order of August 1, 2025 and Request for Brief Extension of Time 06/agosto/2025 2025/08/06 Documento
Resolution and Order Asunto: Fuel-Security Contingency Plan. 01/agosto/2025 2025/08/01 Documento
Motion to Submit June 2025 Monthly Collaborative Report in Compliance with Resolution and Order of March 28, 2025 Asunto: LUMA – Motion to Submit June 2025 Monthly Collaborative Report in Compliance with Resolution and Order of March 28, 2025 29/julio/2025 2025/07/29 Documento
Resolution and Order Asunto: Resolution and Order pertaining to Puerto Rico Court of Appeals July 17, 2025 Ruling, in case TA2025RA00057. 21/julio/2025 2025/07/21 Documento
Informative Motion Related to the Court of Appeals Case TA2025RA00057 Asunto: Exhibit A 18/julio/2025 2025/07/18 Documento
Informative Motion Related to the Court of Appeals Case TA2025RA00057 Asunto: IN RE: Plan Prioritario para la Estabilización de la RED Eléctrica 18/julio/2025 2025/07/18 Documento
Informative Motion Related to the Court of Appeals Case TA2025RA00057 Asunto: IN RE: Plan Prioritario para la Estabilización de la RED ELéctrica 18/julio/2025 2025/07/18 Documento
Resolución Asunto: Resolución respecto a la Moción en Cumplimiento de Resolución y Orden de 26 de junio de 2025, presentada por la Autoridad de Energía Eléctrica de Puerto […] 16/julio/2025 2025/07/16 Documento
Resolution and Order Asunto: Reporting Directives and Fuel-Security Contingency Plan. 16/julio/2025 2025/07/16 Documento
Resolution and Order Asunto: Resolution and Order pertaining to Puerto Rico Court of Appeals July 9, 2025 Resolution, in case TA2025RA00057. 15/julio/2025 2025/07/15 Documento
Moción en Cumplimiento de Resolución y Orden de 26 de junio de 2025 Asunto: IN RE: Plan Prioritario para la Estabilización de la RED Eléctrica 15/julio/2025 2025/07/15 Documento
Second Supplemental and Informative Motion Asunto: Reporting Directives and Information Requirement regarding PREPA’s Proposed Contract Resulting from Temporary Emergency Power Generation 15/julio/2025 2025/07/15 Documento
Informative Motion in Compliance with Resolution and Order Dated July 4, 2025 Asunto: Informative Motion in Compliance with Resolution and Order Dated July 4, 2025 12/julio/2025 2025/07/12 Documento
Supplemental and Informative Motion Asunto: Reporting Directives and Information Requirement regarding PREPA’s Proposed Contract Resulting from Temporary Emergency Power Generation 11/julio/2025 2025/07/11 Documento
Motion to Vacate Resolution of July 4, 2025 Asunto: Reporting Directives and Information Requirement regarding PREPA’s Proposed contract Resulting from Temporary Emergency Power Generation 09/julio/2025 2025/07/09 Documento
Motion to Vacate Resolution of July 4, 2025 Asunto: IN RE: Electric System Priority Stabilization Plan 09/julio/2025 2025/07/09 Documento
Motion to Comply with the June 27, 2025 Resolution and Order Asunto: IN RE: Plan Prioritario para la Estabilización de la Red Eléctrica 07/julio/2025 2025/07/07 Documento
Resolution and Order Asunto: Reporting Directives and Information Requirement regarding PREPA’s Proposed Contract Resulting from Temporary Emergency Power Generation. 04/julio/2025 2025/07/04 Documento
Petition to Intervene and Request of Access to Documents Asunto: IN RE: Electric System Priority Stabilization Plan 03/julio/2025 2025/07/03 Documento
Resolution and Order Asunto: Reporting Directives and Information Requirement regarding PREPA’s Proposed Contract Resulting from Temporary Emergency Power Generation. 27/junio/2025 2025/06/27 Documento
Motion to Submit June 2025 Monthly Collaborative Report in Compliance with Resolution and Order of March 28, 2025 Asunto: LUMA – Motion to Submit June 2025 Monthly Collaborative Report in Compliance with Resolution and Order of March 28, 2025 27/junio/2025 2025/06/27 Documento
Resolución y Orden Asunto: Resolución y Orden respecto a la Moción en Cumplimiento con Resolución y Orden de 29 de mayo de 2025 26/junio/2025 2025/06/26 Documento
Motion Submitting Proposed Contract Resulting from Temporary Emergency Power Generation RFP for the Energy Bureau’s Review and Approval Asunto: Motion Submitting Proposed Contract Resulting from Temporary Emergency Power Generation RFP for the Energy Bureau’s Review and Approval 20/junio/2025 2025/06/20 Documento
Moción en Cumplimiento con Resolución y Orden del 29 de mayo de 2025 Asunto: Moción en Cumplimiento con Resolución y Orden del 29 de mayo de 2025 05/junio/2025 2025/06/05 Documento
Moción sobre Término para Cumplir con Resolución y Orden del 29 de mayo de 2025 Asunto: Moción sobre Término para Cumplir con Resolución y Orden del 29 de mayo de 2025 03/junio/2025 2025/06/03 Documento
Resolución y Orden Asunto: Resolución y Orden respecto a la Resolución de 11 de octubre de 2024 29/mayo/2025 2025/05/29 Documento
Motion to Submit May 2025 Monthly Collaborative Report in Compliance with Resolution and Order of March 28, 2025 Asunto: Exhibit 1 Motion to Subm May Monthly Collaborative Report 27/mayo/2025 2025/05/27 Documento
Motion to Submit May 2025 Monthly Collaborative Report in Compliance with Resolution and Order of March 28, 2025 Asunto: LUMA – Motion to Submit May 2025 Monthly Collaborative Report in Compliance with Resolution and Order of March 28, 2025 27/mayo/2025 2025/05/27 Documento
Request to Add Luma Email Address to Notices Asunto: Request to Add Luma Email Address to Notices 09/mayo/2025 2025/05/09 Documento
Moción Informativa Asunto no disponible. 30/abril/2025 2025/04/30 Documento
Motion to Submit Corrected Exhibit 1 to Motion to Submit April 2025 Monthly Collaborative Report in Compliance with Resolution and Order of March 28, 2025 Asunto: Motion to Submit Corrected Exhibit 1 to Motion to Submit April 2025 Monthly Collaborative Report in Compliance with Resolution and Order of March 28, 2025 29/abril/2025 2025/04/29 Documento
Motion to Submit April 2025 Monthly Collaborative Report in Compliance with Resolution and Order of March 28, 2025 Asunto: Motion to Submit April 2025 Monthly Collaborative Report in Compliance with Resolution and Order of March 28, 2025 28/abril/2025 2025/04/28 Documento
Resolution and Order Nunc Pro Tunc Asunto: Establishment of the Electric System Priority Stabilization Two-Year Plan. 28/marzo/2025 2025/03/28 Documento
Resolution and Order Asunto: Establishment of the Electric System Priority Stabilization Two-Year Plan. 28/marzo/2025 2025/03/28 Documento
Motion in Compliance with Resolution and Order of March 12, 2025 and Request for Confidential Treatment Asunto: Motion in Compliance with Resolution and Order of March 12, 2025 and Request for Confidential Treatment 24/marzo/2025 2025/03/24 Documento
Moción en Cumplimiento con la Resolución y Orden del 12 de marzo de 2025 Asunto: AEE – Moción en Cumplimiento con la Resolución y Orden del 12 de marzo de 2025 24/marzo/2025 2025/03/24 Documento
Notice of Appearance and Request for Notice Asunto: Notice of Appearance and Request for Notice 21/marzo/2025 2025/03/21 Documento
Moción en Cumplimiento con la Resolución y Orden del 19 de marzo de 2025 Asunto: Moción en Cumplimiento con la Resolución y Orden del 19 de marzo de 2025 21/marzo/2025 2025/03/21 Documento
Resolución y Orden Asunto: Resolución y Orden respecto a la adquisición de nueva generación temporera. 19/marzo/2025 2025/03/19 Documento
Resolución y Orden Asunto: Resolución y Orden respecto a Moción Sometiendo Posición de LUMA respecto a Solicitud de Genera para la Aprobación Acelerada de Soluciones de Capacidad de Generación de […] 12/marzo/2025 2025/03/12 Documento
Motion Submitting LUMA’s Position Regarding Genera’s Request for Expedited Approval of Emergency Generation Capacity Solutions Asunto: IN RE: Plan Prioritario para la Estabilización de la Red Eléctrica 06/marzo/2025 2025/03/06 Documento
Resolución y Orden Asunto: Solicitud de Generación Temporera Adicio-nal. 27/febrero/2025 2025/02/27 Documento
Request for Expedited Approval of Emergency Generation Capacity Solutions Asunto: Request for Expedited Approval of Emergency Generation Capacity Solutions 26/febrero/2025 2025/02/26 Documento
Motion Supplementing Responses to Items 11 and 16 of Order of December 5, 2024 Asunto: Genera – Motion Supplementing Responses to Items 11 and 16 of Order of December 5, 2024 16/enero/2025 2025/01/16 Documento
Motion Submitting Responses to Items 8, 12 and 14 (a) of Resolution and Order of December 5, 2024 Asunto: Genera – Motion Submitting Responses to Items 8, 12 and 14 (a) of Resolution and Order of December 5, 2024 08/enero/2025 2025/01/08 Documento
Motion in Partial Compliance with Resolution and Order of December 5, 2024 and for Extension of Time to Comply with Items 8 and 12 of the Request of Information Asunto: Anejo 4 23/diciembre/2024 2024/12/23 Documento
Motion in Partial Compliance with Resolution and Order of December 5, 2024 and for Extension of Time to Comply with Items 8 and 12 of the Request of Information Asunto: Anejo 3 23/diciembre/2024 2024/12/23 Documento
Motion in Partial Compliance with Resolution and Order of December 5, 2024 and for Extension of Time to Comply with Items 8 and 12 of the Request of Information Asunto: Anejo 2 23/diciembre/2024 2024/12/23 Documento
Motion in Partial Compliance with Resolution and Order of December 5, 2024 and for Extension of Time to Comply with Items 8 and 12 of the Request of Information Asunto: Anejo 1 23/diciembre/2024 2024/12/23 Documento
Motion in Partial Compliance with Resolution and Order of December 5, 2024 and for Extension of Time to Comply with Items 8 and 12 of the Request of Information Asunto: IN RE: Plan Prioritario para la Estabilización de la Red Eléctrica 23/diciembre/2024 2024/12/23 Documento
LUMA’s Motion Submitting Responses to Energy Bureau’s Requirement of Information in Compliance with Resolution and Order of December 5, 2024 Asunto: IN RE: Priority Plan for the Stabilization of the Electric Grid 23/diciembre/2024 2024/12/23 Documento
Motion in Compliance with the December 5th Order Asunto: IN RE: Plan Prioritario para la Estabilización de la RED Eléctrica 21/diciembre/2024 2024/12/21 Documento
Compilación de comentarios y recomendaciones a los Planes Prioritarios de LUMA Energy y Genera PR, dentro del expediente NEPR-MI-2024-0005 Asunto: Compilación de comentarios y recomendaciones a los Planes Prioritarios de LUMA Energy y Genera PR, dentro del expediente NEPR-MI-2024-0005 19/diciembre/2024 2024/12/19 Documento
Resolution and Order Asunto: Requirement of Information (“ROI”). 05/diciembre/2024 2024/12/05 Documento
Notice of Withdrawal as Attorney of Record Asunto: Notice of Withdrawal as Attorney of Record 25/octubre/2024 2024/10/25 Documento
Resolution and Order Asunto: Resolution and Order imposing administrative fine for noncompliance of June 13 Resolution and July 5 Order. 11/octubre/2024 2024/10/11 Documento
PEHSU Commentary on Plan Prioritario para la Estabilización de la Red Eléctrica Stabilization al Negociado de Energía Asunto: Comments 08/octubre/2024 2024/10/08 Documento
El Puente PR Comentarios al NEPR Asunto: Comentarios 08/octubre/2024 2024/10/08 Documento
Ponencia en Reacción a Planes de Estabilización de Genera PR y LUMA Energy Asunto: Comentarios 08/octubre/2024 2024/10/08 Documento
CAMBIO Comentarios Asunto: Comentarios 08/octubre/2024 2024/10/08 Documento
Carta Grupal Comentarios Plan Prioritario para la Estabilización de la Red Eléctrica Stabilization al Negociado de Energia Asunto: Comentarios 08/octubre/2024 2024/10/08 Documento
Comentarios A Irizarry Asunto: Comentarios 07/octubre/2024 2024/10/07 Documento
CCPR Comments to Priority Stabilization Plan Asunto: Comments 04/octubre/2024 2024/10/04 Documento
AHPR Comments to Priority Stabilization Plan Asunto: Comments 03/octubre/2024 2024/10/03 Documento
PRMA Letter – Industriales Carta NEPR Asunto: Comments 03/octubre/2024 2024/10/03 Documento
ACDET, ASORE y Otros Comments to Priority Stabilization Plan Asunto: Comments 03/octubre/2024 2024/10/03 Documento
PRHTA Public Comments on Priority Plan for the Stabilization of the Electric Grid Asunto: Comments 03/octubre/2024 2024/10/03 Documento
Motion Submitting Additional Information Requested During Virtual Technical Workshop of September 11, 2024 Asunto: Motion Submitting Additional Information Requested During Virtual Technical Workshop of September 11, 2024 25/septiembre/2024 2024/09/25 Documento
Motion in Compliance with Order of September 11, 2024 Asunto: IN RE: Plan Prioritario para la Estabilización de la RED ELéctrica 13/septiembre/2024 2024/09/13 Documento
Motion in Compliance with Resolution and Order Issued on August 23, 2024 Asunto: Motion in Compliance with Resolution and Order Issued on August 23, 2024 12/septiembre/2024 2024/09/12 Documento
Moción para Someter Presentación Enmendada de Vista Técnica Asunto: IN RE: Plan Prioritario para la Estabilización de la RED Eléctrica 11/septiembre/2024 2024/09/11 Documento
Motion in Compliance with Resolution and Order of August 23, 2024 Asunto: IN RE: Plan Prioritario para la Estabilización de la RED Eléctrica 11/septiembre/2024 2024/09/11 Documento
Motion Submitting LUMA’s Presentation for Virtual Technical Workshop Scheduled for Septembre 11, 2024 Asunto: IN RE: Plan Prioritario para la Estabilización de la RED Eléctrica 09/septiembre/2024 2024/09/09 Documento
Motion in Compliance with Resolution and Order of August 9, 2024 Asunto: Motion in Compliance with Resolution and Order of August 9, 2024 09/septiembre/2024 2024/09/09 Documento
Moción en Cumplimiento con Resolución y Orden del 9 de agosto de 2024 Asunto: IN RE: Plan Prioritario para la Estabilización de la RED ELéctrica 06/septiembre/2024 2024/09/06 Documento
Motion Requesting Participation by Windmar Renewable Energy, Inc. in the «Plan Prioritario para la Estabilización de la RED Eléctrica Docket» Asunto: IN RE: Plan Prioritario para la Estabilización de la RED ELéctrica 28/agosto/2024 2024/08/28 Documento
Moción de Reconsideración de Resolución y Orden Emitida el 23 de agosto de 2024 Asunto: Moción de Reconsideración de Resolución y Orden Emitida el 23 de agosto de 2024 27/agosto/2024 2024/08/27 Documento
Resolution and Order Asunto: Resolution and Order addressing Motion Requesting Partial Modification of Scheduling Order, presented by Genera. 23/agosto/2024 2024/08/23 Documento
Resolution and Order Asunto: Resolution and Order imposing administrative fine for noncompliance of June 13 Resolution and July 5 Order. 23/agosto/2024 2024/08/23 Documento
Motion Requesting Partial Modification to Scheduling Order Asunto: Motion Requesting Partial Modification to Scheduling Order 13/agosto/2024 2024/08/13 Documento
Motion Requesting Order to Initiate Procurement Process for Leasing of Supplemental Power Generation Asunto: IN RE: Plan Prioritario para la Estabilización de la RED Eléctrica 09/agosto/2024 2024/08/09 Documento
Resolution and Order Asunto: Establishment of Procedural Calendar. 09/agosto/2024 2024/08/09 Documento
Motion Submitting Updated Preliminary Plan Asunto: Motion Submitting Updated Preliminary Plan 19/julio/2024 2024/07/19 Documento
Moción en Cumplimiento de Orden Asunto: IN RE: Plan Prioritario para la Estabilización de la RED Eléctrica 19/julio/2024 2024/07/19 Documento
Resolución y Orden Asunto: Resolución y Orden respecto a Moción en Cumplimiento con la Resolución y Orden de 13 de junio de 2024, presentada por la Autoridad de Energía Eléctrica […] 11/julio/2024 2024/07/11 Documento
Motion in Compliance with Order to Show Cause of Juy 5, 2024 and Submitting Preliminary Plan Draft Required by the Resolution and order of June 13, 2024. Asunto: Motion in Compliance with Order to Show Cause of Juy 5, 2024 and Submitting Preliminary Plan Draft Required by the Resolution and order of June 13, […] 10/julio/2024 2024/07/10 Documento
Motion in Compliance with the June 13, 2024, Resolution and Order Asunto: Motion in Compliance with the June 13, 2024, Resolution and Order 10/julio/2024 2024/07/10 Documento
Moción en Cumplimiento de Orden y Sometiendo Plan Preliminar de Estabilización del Sistema Eléctrico Asunto: Presentación de Plan Preliminar de Estabilización del Sistema Eléctrico 08/julio/2024 2024/07/08 Documento
Resolución y Orden Asunto: Solicitudes de Prórroga presentadas por LUMA, Genera y la Autoridad. 05/julio/2024 2024/07/05 Documento
Moción para Solicitar Término Adicional para Cumplir con Resolución y Orden el 13 de junio de 2024 Asunto: Moción para Solicitar Término Adicional para Cumplir con Resolución y Orden el 13 de junio de 2024 02/julio/2024 2024/07/02 Documento
Solicitud de Extensión de Término para Presentar Informe Preliminar Requerido Mediante Resolución y Orden de 13 de junio de 2024 Asunto: IN RE: Plan Prioritario para la Estabilización de la RED Eléctrica 01/julio/2024 2024/07/01 Documento
Request for Extension of Time to Submit the Preliminary Plan Required by the Resolution and Order of June 13, 2024 Asunto: IN RE: Plan Prioritario para la Estabilización de la RED Eléctrica 28/junio/2024 2024/06/28 Documento
Notice of Appearance and Request for Notice Asunto: IN RE: Plan Prioritario para la Estabilización de la RED Eléctrica 28/junio/2024 2024/06/28 Documento
Notice of Appearance Asunto: Notice of Appearance 17/junio/2024 2024/06/17 Documento
Resolución y Orden Asunto: Apertura de Docket. 13/junio/2024 2024/06/13 Documento

Antonio Torres-Miranda is presently an Associate Commissioner for the Energy Bureau of the Puerto Rico Public Service Regulatory Board (Energy Bureau). Previously, Mr. Torres had been the Director of the Legal Advisory Division of the Energy Bureau.

Mr. Torres has a bachelor’s degree in mechanical engineering from the University of Puerto Rico. He also has a master’s degree in engineering management from the Polytechnical University of Puerto Rico. In the 1990’s he passed the exam to be a Certified Energy Manager. He is presently a member of the Puerto Rico Professional College of Engineer and Land Surveyors.

Mr. Torres graduated with honors from the Interamerican University of Puerto Rico where he obtained his Juris Doctor degree. He is presently member of the bar of the Commonwealth of Puerto Rico and is a member of the U.S. District of Puerto Rico Federal bar.

He commenced his engineering work experience with the Department of Defense in a Naval base in Virginia were he designed industrial ventilation systems. He then went to New York to work with Kennetech Energy Management were he first commenced being immersed in the energy sector. He then transferred to Puerto Rico with Kennetech in which he conducted wind studies throughout the island together with U.S. Wind Power. He continued implementation of energy management systems in several industrial companies throughout Puerto Rico until Kennetech joined forces with Enron to develop the first privately owned power plant in Puerto Rico known as EcoElectrica. This 450 MW natural gas power plant included the development of the first LNG terminal in Puerto Rico.

He also worked as a contractor with the Puerto Rico Electric Power Authority in the development of a 42 miles natural gas pipeline.

Before joining the Energy Bureau Mr. Torres developed several natural gas projects in Puerto Rico.

Ferdinand Ramos-Soegaard attained a bachelor’s degree in electrical engineering (BSEE) graduating from the Georgia Institute of Technology in Atlanta, GA in 2000. His degree specialized in power distribution and telecommunications systems.

Mr. Ramos-Soegaard is a licensed professional engineer in the Commonwealth of Puerto Rico and the state of Florida. Throughout his professional carrier Mr. Ramos has been involved in all aspects of the design, construction and maintenance of electrical distribution systems, including high voltage transmission lines and renewable energy interconnections to the Puerto Rico Electric Power Authority subtransmission grid.

Sylvia B. Ugarte Araujo holds a bachelor’s degree in industrial and Systems Engineering from the University of Florida (1998). She studied at the Inter-American University of Puerto Rico School of Law (2004) and then obtained a Master of Laws from the Inter-American University of Puerto Rico (2019). Ms. Ugarte is admitted to the practice of law and notary by the Supreme Court of Puerto Rico (2004), the Federal Court for the District of Puerto Rico, for the First Circuit of Boston (2005), the Court of Appeals of the First Circuit (2005) and the Supreme Court of Texas (2018). She was Director of the Office of Legal Counsel of the Energy Bureau of the Public Service Regulatory Board and the Designated Director of the Office of Legal Counsel of the Public Service Regulatory Board. She has served as Legal Director of the Puerto Rico Infrastructure Financing Authority and has worked with renowned law firms. She has over fifteen (15) years of vast professional experience as a trial attorney with an emphasis on commercial and construction litigation and extensive experience in administrative law. Also, as an industrial engineer she has been a consultant for government agencies in charge of large projects and in private entities.

Lillian Mateo-Santos obtained her Bachelor’s Degree in Business Administration from the University of Puerto Rico, Río Piedras Campus, in 1993 and a Juris Doctor degree from the University of Puerto Rico School of Law in 1996. In 1999, she obtained a degree of Masters of Laws (LLM) in Environmental and Energy of the Tulane University Law School. Before joining the Puerto Rico Energy Bureau, Ms. Mateo-Santos was a member of various law firms. Her private practice was focused on energy, environmental, land use and permitting matters, including administrative law litigation.

On June 5, 2019, Ms. Mateo-Santos was elected 2nd Vice President of the Southeastern Association of Regulatory Utility Commissioners (SEARUC). She is a member of the American Bar Association and is admitted to practice law and notary law in Puerto Rico, and the United States Court of Appeals for the First Circuit.

Edison Avilés-Deliz obtained his Bachelor of Science in Electrical Engineering with specialties in Power and Control Systems (BSEE) Cum Laude from the University of Puerto Rico, Mayagüez Campus in 1991 and a Juris Doctor (JD) also Cum Laude from the University of Puerto Rico School of Law in 1997. In addition, he holds Master degrees with Distinctions in Diplomacy/International Relations/Business (MA) from Norwich University in Vermont and in Energy Law from Vermont Law School (LLM).

Avilés-Deliz is a licensed engineer and member of the College of Engineers and Surveyors of Puerto Rico (CIAPR). He was president of the Disciplinary and Professional Ethics Tribunal of the CIAPR, of the Institute of Electrical Engineers of CIAPR and of the Society of Electrical Engineers of Puerto Rico. He is admitted to practice as a public notary in Puerto Rico and as a lawyer, both in the District Court of Puerto Rico and the Court of Appeals for the First Federal Circuit.

He is a member of Phi Eta Mu Fraternity, the Engineering Honor Society Tau Beta Pi, and the International Studies Honor Society Sigma Iota Rho. He is also a Senior member of the IEEE.

Antonio Torres-Miranda es actualmente Comisionado Asociado del Negociado de Energía de la Junta Reglamentadora de Servicios Públicos de Puerto Rico (Negociado de Energía). Anteriormente, el Sr. Torres había sido Director de la División de Asesoría Legal del Negociado de Energía.

El Sr. Torres tiene un bachillerato en ingeniería mecánica de la Universidad de Puerto Rico. También tiene una maestría en administración de ingeniería de la Universidad Politécnica de Puerto Rico. En la década de 1990 aprobó el examen para ser Gerente de Energía Certificado. Actualmente es miembro del Colegio de Ingenieros y Agrimensores de Puerto Rico.

El Sr. Torres se graduó con honores de la Universidad Interamericana de Puerto Rico donde obtuvo su título de Juris Doctor (JD). Actualmente es miembro del Colegio de Abogados del Estado de Puerto Rico y es miembro del Colegio de Abogados Federal del Distrito de Puerto Rico de los Estados Unidos.

Comenzó su experiencia laboral en ingeniería con el Departamento de Defensa en una base naval en Virginia donde diseñó sistemas de ventilación industrial. Luego se fue a Nueva York para trabajar con Kennetech Energy Management, donde comenzó a sumergirse en el sector energético. Luego se transfirió a Puerto Rico con Kennetech, donde realizó estudios eólicos en toda la isla U.S. Wind Power. Continuó con la implementación de sistemas de administración de energía en varias empresas industriales en todo Puerto Rico hasta que Kennetech unió fuerzas con Enron para desarrollar la primera planta de energía de propiedad privada en Puerto Rico conocida como EcoEléctrica. Esta planta de energía de gas natural de 450 MW incluyó el desarrollo de la primera terminal de GNL en Puerto Rico.

También trabajó como contratista con la Autoridad de Energía Eléctrica de Puerto Rico en el desarrollo de una tubería de gas natural de 42 millas.

Antes de unirse al Negociado de Energía, el Sr. Torres desarrolló varios proyectos de gas natural en Puerto Rico.

La Lcda. Sylvia B. Ugarte Araujo posee un Bachillerato en Ingeniería Industrial y de Sistemas de la Universidad de la Florida (1998). Estudió en la Escuela de Derecho de la Universidad Interamericana de Puerto Rico (2004) y luego obtuvo una Maestría en Derecho de la Universidad Interamericana de Puerto Rico (2019). La Lcda. Ugarte está admitida a la práctica de la abogacía y la notaría por el Tribunal Supremo de Puerto Rico (2004), al Tribunal Federal, Distrito de Puerto Rico, al Primer Circuito Federal de Boston (2005), al Tribunal de Apelaciones del Primer Circuito (2005) y al Tribunal Supremo de la jurisdicción del estado de Texas (2018). Fue Directora de la Oficina de Asesoramiento Legal del Negociado de Energía de la Junta Reglamentadora de Servicio Público y la Directora Designada de la Oficina de Asesoramiento Legal de la Junta Reglamentadora de Servicio Público. Ha ejercido como Directora Legal de la Autoridad para el Financiamiento de la Infraestructura de Puerto Rico y ha trabajado con bufetes de abogado de renombre. Tiene sobre quince (15) años de vasta experiencia profesional como abogada litigante con énfasis en litigio comercial y construcción y una amplia experiencia en derecho administrativo. Así también, como ingeniera industrial ha sido consultora para agencias gubernamentales encargadas de proyectos de envergadura y en entidades privadas.

Ferdinand A. Ramos-Soegaard obtuvo su Bachillerato en Ciencias en Ingeniería Eléctrica (BSEE, por sus siglas en inglés) del Georgia Institute of Technology en Atlanta, GA en el 2000, con especialidad en sistemas de distribución de potencia y telecomunicaciones.

Ramos-Soegaard es ingeniero licenciado en el Estado Libre Asociado de Puerto Rico y en el Estado de Florida. A través de su carrera profesional, Ramos-Soegaard ha estado envuelto en todos los aspectos del diseño, construcción y mantenimiento de sistemas de distribución eléctrica, incluyendo líneas de transmisión de alto voltaje e interconexiones de sistemas de energía renovable a la red de subtransmisión de la Autoridad de Energía Eléctrica de Puerto Rico.

Lillian Mateo-Santos obtuvo su Bachillerato en Administración de Empresas de la Universidad de Puerto Rico, Recinto de Río Piedras en 1993 y el grado de Juris Doctor de la Facultad de Derecho de la Universidad de Puerto Rico en 1996. En 1999 obtuvo una Maestría en Derecho (LLM) en Ambiental y Energía de la Facultad de Derecho de la Universidad de Tulane. Antes de formar parte del Negociado de Energía de Puerto Rico, la Lic. Mateo-Santos fue miembro de varios bufetes de abogados. Su práctica privada se enfocó en asuntos de energía, ambiental, uso de terrenos y permisos, incluyendo litigación de derecho administrativo.

El 5 de junio de 2019, la Lic. Mateo-Santos fue elegida 2nda Vice Presidenta del Southern Association of Regulatory Utility Commissioners (SEARUC). Es miembro de la American Bar Association y está admitida para ejercer como abogado y notario público en Puerto Rico, y en el Tribunal de Apelaciones para el Primer Circuito Federal.

Edison Avilés-Deliz obtuvo su bachillerato Cum Laude en Ingeniería Eléctrica con especialidades en Sistemas de Controles y Potencia (BSEE) de la Universidad de Puerto Rico, Recinto de Mayagüez en 1991 y un Juris Doctor (JD) también Cum Laude de la Facultad de Derecho de la Universidad de Puerto Rico en 1997. Además, ostenta maestrías con Distinciones en Diplomacia/Relaciones Internacionales/Negocios (MA) de la Universidad de Norwich en Vermont y en Derecho en Energía de la Universidad de Derecho de Vermont (LLM).

Avilés-Deliz es ingeniero licenciado y miembro del Colegio de Ingenieros y Agrimensores de Puerto Rico (CIAPR). Fue presidente del Tribunal Disciplinario y de Ética Profesional del CIAPR, del Instituto de Ingenieros Electricistas del CIAPR y de la Sociedad de Ingenieros Electricistas de Puerto Rico. Está admitido para ejercer como notario público en Puerto Rico y como abogado, tanto en el Tribunal de Distrito de Puerto Rico como el Tribunal de Apelaciones para el Primer Circuito Federal.

Pertenece a la fraternidad Phi Eta Mu, a la Sociedad de Honor de Ingeniería Tau Beta Pi, a la Sociedad de Honor de Estudios Internacionales Sigma Iota Rho. También es miembro senior de la IEEE.

Subscríbete