Resolution and Order
Asunto: Extension of time to Submit the List of All Inactive Projects with Updated Cost Estimate in Compliance with the June 18, 2026, Resolution and Order.
|
20/julio/2026
|
2026/07/20
|
Documento
|
|
Submittal of LUMA’s Report in Partial Compliance with the June 18, 2026, Resolution and Order
Asunto: Exhibit 3 – Submittal of LUMA’s Report in Partial Compliance with the June 18, 2026, Resolution and Order
|
15/julio/2026
|
2026/07/15
|
Documento
|
|
Submittal of LUMA’s Report in Partial Compliance with the June 18, 2026, Resolution and Order
Asunto: Exhibit 2 – Submittal of LUMA’s Report in Partial Compliance with the June 18, 2026, Resolution and Order
|
15/julio/2026
|
2026/07/15
|
Documento
|
|
Submittal of LUMA’s Report in Partial Compliance with the June 18, 2026, Resolution and Order
Asunto: Submittal of LUMA’s Report in Partial Compliance with the June 18, 2026, Resolution and Order
|
15/julio/2026
|
2026/07/15
|
Documento
|
|
Motion Submitting One (1) Amended FEMA Approval of Project and Six (6) FEMA Approvals of Project, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting One (1) Amended FEMA Approval of Project and Six (6) FEMA Approvals of Project, Request for Confidential Treatment and Supporting Memorandum of Law
|
14/julio/2026
|
2026/07/14
|
Documento
|
|
Motion for Extension of Time to Submit the List of All Inactive Projects with Updated Cost Estimates in Compliance with the June 18, 2026, Resolution and Order
Asunto: Motion for Extension of Time to Submit the List of All Inactive Projects with Updated Cost Estimates in Compliance with the June 18, 2026, Resolution and […]
|
10/julio/2026
|
2026/07/10
|
Documento
|
|
Motion to Submit Monthly BESS Progress Report in Compliance with Resolutions and Orders Dated February 1, 2024, and April 23, 2024
Asunto: Genera’s Motion to Submit Monthly BESS Progress Report in Compliance with Resolutions and Orders Dated February 1, 2024, and April 23, 2024 June 2026)
|
09/julio/2026
|
2026/07/09
|
Documento
|
|
Motion Submitting Two (2) FEMA Approvals of Project, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting Two (2) FEMA Approvals of Project, Request for Confidential Treatment and Supporting Memorandum of Law
|
07/julio/2026
|
2026/07/07
|
Documento
|
|
Motion Submitting Amended Scope of Work, Request for Confidentiality, and Supporting Memorandum of Law
Asunto: Motion Submitting Amended Scope of Work, Request for Confidentiality, and Supporting Memorandum of Law
|
01/julio/2026
|
2026/07/01
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order for Motion for Approval to Submit Hurricane Fiona Area Plans To FEMA.
|
22/junio/2026
|
2026/06/22
|
Documento
|
|
Resolution and Order
Asunto: FEMA Revised Consolidated Project Plan.
|
18/junio/2026
|
2026/06/18
|
Documento
|
|
Motion Submitting six (6) FEMA approvals of Project, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting six (6) FEMA approvals of Project, Request for Confidential Treatment and Supporting Memorandum of Law
|
18/junio/2026
|
2026/06/18
|
Documento
|
|
Motion to Submit PREPA’s June 2026 Update to the PREPA-LUMA-GENERA 90-Day Plan
Asunto: Motion to Submit PREPA’s June 2026 Update to the PREPA-LUMA-GENERA 90-Day Plan
|
15/junio/2026
|
2026/06/15
|
Documento
|
|
Motion Submitting Amended Scope of Work, Request for Confidentiality, and Supporting Memorandum of Law
Asunto: Motion Submitting Scope of Work, Request for Confidentiality, and Supporting Memorandum of Law
|
11/junio/2026
|
2026/06/11
|
Documento
|
|
Motion to Submit Monthly BESS Progress Report in Compliance with Resolutions and Orders Dated February 1, 2024, and April 23, 2024
Asunto: Motion to Submit Monthly BESS Progress Report in Compliance with Resolutions and Orders Dated February 1, 2024, and April 23, 2024 (May 2026)
|
08/junio/2026
|
2026/06/08
|
Documento
|
|
Motion Submitting Two Area Plans (Caguas), Request for Confidentiality, and Supporting Memorandum of Law
Asunto: Submission Two Area Plans (Caguas), Request for Confidentiality, and Supporting Memorandum of Law
|
05/junio/2026
|
2026/06/05
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order for Initial FEMA Project Scope of Work for Line 8700 Costa Sur Power Plant to Garzas 2 HP – Garzas 1 HP
|
03/junio/2026
|
2026/06/03
|
Documento
|
|
Informative Motion on the Status of Sow : 4 X 25 MW BESS Interconnections at LUMA 38KV System (May 2026)
Asunto: Informative Motion on the Status of Sow : 4 X 25 MW BESS Interconnections at LUMA 38KV System (May 2026)
|
27/mayo/2026
|
2026/05/27
|
Documento
|
|
Motion Submitting One Initial Scope of Work, Request for Confidentiality, Supporting Memorandum of Law, and Request for Expedited Approval
Asunto: Motion Submitting One Initial Scope of Work, Request for Confidentiality, Supporting Memorandum of Law, and Request for Expedited Approval
|
26/mayo/2026
|
2026/05/26
|
Documento
|
|
Exhibit 2 Motion Submitting LUMA’s Attachment C- Global E&M Amendment
Asunto: Exhibit 2 Motion Submitting LUMA’s Attachment C- Global E&M Amendment
|
22/mayo/2026
|
2026/05/22
|
Documento
|
|
Motion Submitting LUMA’s Attachment C- Global E&M Amendment
Asunto: Motion Submitting LUMA’s Attachment C- Global E&M Amendment
|
22/mayo/2026
|
2026/05/22
|
Documento
|
|
Motion Submitting Quarterly Report on Federal Funding Activities for the Third Quarter of Fiscal Year 2026
Asunto: Submission of Quarterly Report on Federal Funding Activities for the Third Quarter of Fiscal Year 2026
|
15/mayo/2026
|
2026/05/15
|
Documento
|
|
Motion Submitting LUMA’S Adjusted Consolidated List, Proposed Attachment A, and Attachment B (Streetlights Projects)
Asunto: Exhibit 2 – Motion Submitting LUMA’S Adjusted Consolidated List, Proposed Attachment A, and Attachment B (Streetlights Projects)
|
14/mayo/2026
|
2026/05/14
|
Documento
|
|
Motion Submitting LUMA’S Adjusted Consolidated List, Proposed Attachment A, and Attachment B (Streetlights Projects)
Asunto: Motion Submitting LUMA’S Adjusted Consolidated List, Proposed Attachment A, and Attachment B (Streetlights Projects)
|
14/mayo/2026
|
2026/05/14
|
Documento
|
|
Motion to Submit Monthly Bess Progress Report in Compliance with Resolutions and Orders Dated February 1, 2024, and April 23, 2024
Asunto: Motion to Submit Monthly BESS Progress Report in Compliance with Resolutions and Orders Dated February 1, 2024, and April 23, 2024 (April 2026)
|
08/mayo/2026
|
2026/05/08
|
Documento
|
|
Motion Submitting Two (2) FEMA Approvals of Project, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting Two (2) FEMA Approvals of Project, Request for Confidential Treatment and Supporting Memorandum of Law
|
28/abril/2026
|
2026/04/28
|
Documento
|
|
Informative Motion on the Status of SOW: 4 x 25 MW BESS Interconnections at LUMA 38kV System (APRIL 2026)
Asunto: Informative Motion on the Status of SOW: 4 x 25 MW BESS Interconnections at LUMA 38kV System (APRIL 2026)
|
27/abril/2026
|
2026/04/27
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order to Amend March 26, 2021, R&O.
|
22/abril/2026
|
2026/04/22
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order to Motion for Approval to Submit Hurricane Fiona Area Plans to FEMA.
|
22/abril/2026
|
2026/04/22
|
Documento
|
|
Notice of Change of Email Address of Counsel
Asunto: Notice of Change of Email Address of Counsel
|
21/abril/2026
|
2026/04/21
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order for Motion for Approval to Submit Continuous Monitoring System Project to FEMA
|
14/abril/2026
|
2026/04/14
|
Documento
|
|
Motion to Submit Monthly Bess Progress Report in Compliance with Resolutions and Orders Dated February 1,2024, and April 23, 2024
Asunto: Genera – Motion to Submit Monthly Bess Progress Report in Compliance with Resolutions and Orders Dated February 1,2024, and April 23, 2024
|
08/abril/2026
|
2026/04/08
|
Documento
|
|
Notice of Appearance, Request for Notice and Substitution of Counsel
Asunto: Notice of Appearance, Request for Notice and Substitution of Counsel
|
08/abril/2026
|
2026/04/08
|
Documento
|
|
Informative Motion in the Status of SOW: 4×25 MW BESS Interconnections at LUMA 38kV System (March 2026)
Asunto: LUMA – Informative Motion in the Status of SOW: 4×25 MW BESS Interconnections at LUMA 38kV System (March 2026)
|
27/marzo/2026
|
2026/03/27
|
Documento
|
|
Motion Submitting Amended Area Plan, Request for Confidentiality, and Supporting Memorandum of Law
Asunto: LUMA – Motion Submitting Amended Area Plan, Request for Confidentiality, and Supporting Memorandum of Law
|
23/marzo/2026
|
2026/03/23
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order for Request for Approval to Submit to COR3 and FEMA the SOW to Convert San Juan Units 7 and 9 to Operate with […]
|
20/marzo/2026
|
2026/03/20
|
Documento
|
|
Motion to Submit PREPA’s March 2026 Update to the PREPA-LUMA-Genera 90-Day Plan
Asunto: PREPA – Motion to Submit PREPA’s March 2026 Update to the PREPA-LUMA-Genera 90-Day Plan
|
16/marzo/2026
|
2026/03/16
|
Documento
|
|
Motion Submittineg Two Area Plans (Ponce), Request for Confidentiality, and Supporting Memorandum of Law
Asunto: LUMA – Motion Submittineg Two Area Plans (Ponce), Request for Confidentiality, and Supporting Memorandum of Law
|
13/marzo/2026
|
2026/03/13
|
Documento
|
|
Resolution
Asunto: FEMA Consolidated Project Plan and FAASt Settlement.
|
12/marzo/2026
|
2026/03/12
|
Documento
|
|
Motion Submitting LUMA’s March 2026 Update to PREPA-LUMA 90 Day Plan for T&D Projects
Asunto: LUMA Exhibit 2 FEMA Project Milestone
|
11/marzo/2026
|
2026/03/11
|
Documento
|
|
Motion Submitting LUMA’s March 2026 Update to PREPA-LUMA 90 Day Plan for T&D Projects
Asunto: Motion Submitting LUMA’s March 2026 Update to PREPA-LUMA 90 Day Plan for T&D Projects
|
11/marzo/2026
|
2026/03/11
|
Documento
|
|
Motion to Sumbit Monthly Bess Progress Report in Compliance with Resolution and Orders Dated February 1, 2024, and april 23, 2024
Asunto: Genera – Motion to Sumbit Monthly Bess Progress Report in Compliance with Resolution and Orders Dated February 1, 2024, and april 23, 2024
|
10/marzo/2026
|
2026/03/10
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order for Request for Approval to Submit to COR3 and FEMA the SOW to Convert Palo Seco Units 3 & 4 to Operate with […]
|
06/marzo/2026
|
2026/03/06
|
Documento
|
|
Motion Submitting Seventeen (17) FEMA Approvals of Project, Request for Confidential Treatment, and Supporting Memorandum of Law
Asunto: LUMA – Motion Submitting Seventeen (17) FEMA Approvals of Project, Request for Confidential Treatment, and Supporting Memorandum of Law
|
05/marzo/2026
|
2026/03/05
|
Documento
|
|
Motion Submitting Two Amended FEMA Approvals of Projects, Request for Confidentiality and Supporting Memorandum of Law
Asunto: LUMA – Motion Submitting Two Amended FEMA Approvals of Projects, Request for Confidentiality and Supporting Memorandum of Law
|
05/marzo/2026
|
2026/03/05
|
Documento
|
|
Motion Requesting Informal Technical Meeting Pursuant to the Resolutions and Orders Dated February 5, 11 and 27, 2026
Asunto: PREPA – Motion Requesting Informal Technical Meeting Pursuant to the Resolutions and Orders Dated February 5, 11 and 27, 2026
|
03/marzo/2026
|
2026/03/03
|
Documento
|
|
Motion Submitting LUMA’s Implementation Plan in Compliance with Resolutions and Orders of February 5 and February 11, 2026
Asunto: LUMA – Exhibit 4_LUMA’s Incremental Projects List
|
02/marzo/2026
|
2026/03/02
|
Documento
|
|
Motion Submitting LUMA’s Implementation Plan in Compliance with Resolutions and Orders of February 5 and February 11, 2026
Asunto: LUMA – Exhibit 3_LUMA’s Urgent Incremental Priority Projects List
|
02/marzo/2026
|
2026/03/02
|
Documento
|
|
Motion Submitting LUMA’s Implementation Plan in Compliance with Resolutions and Orders of February 5 and February 11, 2026
Asunto: LUMA – Exhibit 2_LUMA’s FEMA Projects Reconciliation
|
02/marzo/2026
|
2026/03/02
|
Documento
|
|
Motion Submitting LUMA’s Implementation Plan in Compliance with Resolutions and Orders of February 5 and February 11, 2026
Asunto: LUMA – Motion Submitting LUMA’s Implementation Plan in Compliance with Resolutions and Orders of February 5 and February 11, 2026
|
02/marzo/2026
|
2026/03/02
|
Documento
|
|
Resolution and Order
Asunto: Response to Reconsideration of February 5 and February 11, 2026 Resolutions and Orders.
|
27/febrero/2026
|
2026/02/27
|
Documento
|
|
Informative Motion on the Status of SOW: 4×25 MW BESS Interconection at LUMA 38kV System (February 2026)
Asunto: LUMA – Informative Motion on the Status of SOW: 4×25 MW BESS Interconection at LUMA 38kV System (February 2026)
|
27/febrero/2026
|
2026/02/27
|
Documento
|
|
Moton in Compliance with Resolution and Order of February 5, 2026
Asunto: PREPA – Attachment A-PREPA Projects-2-25
|
27/febrero/2026
|
2026/02/27
|
Documento
|
|
Motion in Compliance with Resolution and Order of February 5, 2026
Asunto: PREPA – Moton in Compliance with Resolution and Order of February 5, 2026
|
27/febrero/2026
|
2026/02/27
|
Documento
|
|
Motion to Submit Technical Data for Request for Appoval to Submit to COR3 and FEMA the SOW to Convert San Juan Units 7 & 9 to Operate with Natural Gas as Primary Fuel
Asunto: Genera – Attachment B Ex 2 Costs Savings
|
26/febrero/2026
|
2026/02/26
|
Documento
|
|
Motion to Submit Technical Data for Request for Appoval to Submit to COR3 and FEMA the SOW to Convert San Juan Units 7 & 9 to Operate with Natural Gas as Primary Fuel
Asunto: Genera – Motion to Submit Technical Data for Request for Appoval to Submit to COR3 and FEMA the SOW to Convert San Juan Units 7 & […]
|
26/febrero/2026
|
2026/02/26
|
Documento
|
|
Motion Submitting One FEMA Approval of Porject, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: LUMA – Motion Submitting One FEMA Approval of Porject, Request for Confidential Treatment and Supporting Memorandum of Law
|
25/febrero/2026
|
2026/02/25
|
Documento
|
|
Motion to Submit Implementation Plan and Estimated Timeline in Compliance with Resolutions and Orders Issued on February 11, 2026
Asunto: Genera – Exhibit A- Implementation Plan & Estimated Timeline
|
20/febrero/2026
|
2026/02/20
|
Documento
|
|
Motion to Submit Implementation Plan and Estimated Timeline in Compliance with Resolutions and Orders Issued on February 11, 2026
Asunto: Genera – Motion to Submit Implementation Plan and Estimated Timeline in Compliance with Resolutions and Orders Issued on February 11, 2026
|
20/febrero/2026
|
2026/02/20
|
Documento
|
|
Motion for Reconsideration of the Resolution and Orders of February 5 and 11, 2026, and Request for Extension of Time
Asunto: PREPA – Motion Reconsideration – Attachment A- PREPA Comments on Project Activation List
|
20/febrero/2026
|
2026/02/20
|
Documento
|
|
Motion for Reconsideration of the Resolution and Orders of February 5 and 11, 2026, and Request for Extension of Time
Asunto: PREPA – Motion for Reconsideration of the Resolution and Orders of February 5 and 11, 2026, and Request for Extension of Time
|
20/febrero/2026
|
2026/02/20
|
Documento
|
|
Resolution and Order
Asunto: Extension of time to Comply with Resolutions and Orders of February 5 and February 11, 2026
|
19/febrero/2026
|
2026/02/19
|
Documento
|
|
Memorandum of Law in Support of Confidential Treatment of Genera’s February 9, 2026 Motion
Asunto: Genera – Memorandum of Law in Support of Confidential Treatment of Genera’s February 9, 2026 Motion
|
19/febrero/2026
|
2026/02/19
|
Documento
|
|
Motion Requesting Extension of Time to Comply with Resolutions and Orders of February 5 and February 11, 2026
Asunto: LUMA – Motion Requesting Extension of Time to Comply with Resolutions and Orders of February 5 and February 11, 2026
|
17/febrero/2026
|
2026/02/17
|
Documento
|
|
Motion Submitting Quarterly Report on Federal Funding Activities for the Second Quarter of Fiscal Year 2026
Asunto: LUMA – Motion Submitting Quarterly Report on Federal Funding Activities for the Second Quarter of Fiscal Year 2026
|
17/febrero/2026
|
2026/02/17
|
Documento
|
|
Motion Updating Request Approval to Submit to COR3 and FEMA the SOW to Convert San Juan Units 7 & 9 Operate with Natural Gas as Primary Fuel
Asunto: Genera – Motion Updating Request Approval to Submit to COR3 and FEMA the SOW to Convert San Juan Units 7 & 9 Operate with Natural Gas […]
|
12/febrero/2026
|
2026/02/12
|
Documento
|
|
Resolution and Order
Asunto: FEMA Consolidated Project Plan and FAASt Settlement.
|
11/febrero/2026
|
2026/02/11
|
Documento
|
|
Motion to Submit Monthy BESS Progress Report in Compliance with Resolution and Orders Dated February 1, 2024, and April 23, 2024 (January 2026)
Asunto: Genera – Motion to Submit Monthy BESS Progress Report in Compliance with Resolution and Orders Dated February 1, 2024, and April 23, 2024 (January 2026)
|
10/febrero/2026
|
2026/02/10
|
Documento
|
|
Resolution and Order
Asunto: Status of evaluation of Palo Seco 3-4 and San Juan 7-9 Conversions
|
06/febrero/2026
|
2026/02/06
|
Documento
|
|
Resolution and Order
Asunto: FEMA Consolidated Project Plan and FAASt Settlement.
|
05/febrero/2026
|
2026/02/05
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order for Motion for Approval to Submit Hurricane Fiona Area Plans To FEMA.
|
05/febrero/2026
|
2026/02/05
|
Documento
|
|
Moción para Presentar Informe de Progreso Mensual Correspondiente al Mes de Diciembre de 2025
Asunto: AEE – Moción para Presentar Informe de Progreso Mensual Correspondiente al Mes de Diciembre de 2025
|
28/enero/2026
|
2026/01/28
|
Documento
|
|
Informative Motion on the Status of SOW: 4 x 25 MW BESS Interconeccions at LUMA 38kV y System (January 2026)
Asunto: LUMA – Informative Motion on the Status of SOW: 4 x 25 MW BESS Interconeccions at LUMA 38kV y System (January 2026)
|
27/enero/2026
|
2026/01/27
|
Documento
|
|
Motion Submitting One FEMA Approval of Project, Request for Confidential Treatment, and Supporting Memorandum of Law
Asunto: Motion Submitting One FEMA Approval of Project, Request for Confidential Treatment, and Supporting Memorandum of Law
|
21/enero/2026
|
2026/01/21
|
Documento
|
|
Motion submitting tTwo Area Plans, Request for Confidentiality, and Supporting Memorandum of Law
Asunto: Submission of Two Area Plans, Request for Confidentiality, and Supporting Memorandum of Law
|
16/enero/2026
|
2026/01/16
|
Documento
|
|
Motion Requesting Leave to Submit for Approval to COR3 and FEMA the SOW to Convert San Juan Units 7 & 9 to Operate with Natural Gas as Primary Fuel
Asunto: Motion Requesting Leave to Submit for Approval to COR3 and FEMA the SOW to Convert San Juan Units 7 & 9 to Operate with Natural Gas […]
|
14/enero/2026
|
2026/01/14
|
Documento
|
|
Motion Submitting One FEMA Approval of Project, Request for Confidential Treatment, and Supporting Memorandum of Law
Asunto: Motion Submitting One FEMA Approval of Project, Request for Confidential Treatment, and Supporting Memorandum of Law
|
14/enero/2026
|
2026/01/14
|
Documento
|
|
Motion Request Leave to Submit for Approval to COR3 and FEMA the SOW to Convert San Juan Units 7 & 9 Operate with Natural Gas Primary Fuel
Asunto: Genera – ATTACHMENT B – Estimated Monthly Savings
|
14/enero/2026
|
2026/01/14
|
Documento
|
|
Motion Request Leave to Submit for Approval to COR3 and FEMA the SOW to Convert San Juan Units 7 & 9 Operate with Natural Gas Primary Fuel
Asunto: Genera – Motion Request Leave to Submit for Approval to COR3 and FEMA the SOW to Convert San Juan Units 7 & 9 Operate with Natural […]
|
14/enero/2026
|
2026/01/14
|
Documento
|
|
Motion to Submit Monthly BESS Progress Report in Compliance with Resolutions and Orders Date February 1, 2024, and April 23,2024
Asunto: Motion to Submit Monthly BESS Progress Report in Compliance with Resolutions and Orders Date February 1, 2024, and April 23,2024
|
12/enero/2026
|
2026/01/12
|
Documento
|
|
Motion Requesting Leave to Submit for Approval to COR3 and FEMA the SOW to Convert Palo Seco Units 3 & 4 to Operate with Natural Gas as Primary Fuel
Asunto: Motion Requesting Leave to Submit for Approval to COR3 and FEMA the SOW to Convert Palo Seco Units 3 & 4 to Operate with Natural Gas […]
|
09/enero/2026
|
2026/01/09
|
Documento
|
|
Informative Motion of the Status of SOW: 4 X 25 MW BESS Interconnections at LUMA 38kV System (December 2025)
Asunto: Informative Motion of the Status of SOW: 4 X 25 MW BESS Interconnections at LUMA 38kV System (December 2025)
|
29/diciembre/2025
|
2025/12/29
|
Documento
|
|
Motion to Supplement LUMA’S Motion in Compliance with Resolution and Order of November 7, 2025
Asunto: Motion to Supplement LUMA’S Motion in Compliance with Resolution and Order of November 7, 2025
|
23/diciembre/2025
|
2025/12/23
|
Documento
|
|
Motion to Submit PREPA’S December 2025 Update to the PREPA-LUMA 90-Day Plan
Asunto: Motion to Submit PREPA’S December 2025 Update to the PREPA-LUMA 90-Day Plan
|
11/diciembre/2025
|
2025/12/11
|
Documento
|
|
Motion to Submit Monthly BESS Progress Report in Compliance with Resolutions and Orders Date February 1, 2024, and April 23,2024
Asunto: Motion to Submit Monthly BESS Progress Report in Compliance with Resolutions and Orders Date February 1, 2024, and April 23,2024
|
10/diciembre/2025
|
2025/12/10
|
Documento
|
|
Resolution and Order
Asunto: Resolution for LUMA’s November 20, 2025, extension request
|
01/diciembre/2025
|
2025/12/01
|
Documento
|
|
Informatie Motion on the Status of SOW: 4 x 25 MW BESS Interconnections at LUMA 38KV System (November 2025)
Asunto: Informatie Motion on the Status of SOW: 4 x 25 MW BESS Interconnections at LUMA 38KV System (November 2025)
|
26/noviembre/2025
|
2025/11/26
|
Documento
|
|
Motion Requesting Extension of Time to Comply with Resolution and Order of November 7, 2025
Asunto: Motion Requesting Extension of Time to Comply with Resolution and Order of November 7, 2025
|
20/noviembre/2025
|
2025/11/20
|
Documento
|
|
Motion Submitting Nine FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting Nine FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law.
|
10/noviembre/2025
|
2025/11/10
|
Documento
|
|
Motion to Submit Monthly BESS Progress Report in Compliance with Resolutions and Orders Dated February 1, 2024, and April, 23, 2024
Asunto: Motion to Submit Monthly BESS Progress Report in Compliance with Resolutions and Orders Dated February 1, 2024, and April, 23, 2024.
|
10/noviembre/2025
|
2025/11/10
|
Documento
|
|
Motion Submitting Nine FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting Nine FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law.
|
10/noviembre/2025
|
2025/11/10
|
Documento
|
|
Resolution and Order
Asunto no disponible.
|
07/noviembre/2025
|
2025/11/07
|
Documento
|
|
Documento no encontrado.
Asunto: LUMA – Motion Submitting Four FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
|
04/noviembre/2025
|
2025/11/04
|
|
|
Motion Submitting LUMA’s Consolidated List with Costs Incurred for Obligated Projects
Asunto: Exhibit 1 Motion Subm LUMAs Consolidated List
|
27/octubre/2025
|
2025/10/27
|
Documento
|
|
Motion Submitting LUMA’s Consolidated List with Costs Incurred for Obligated Projects
Asunto: LUMA – Motion Submitting LUMA’s Consolidated List with Costs Incurred for Obligated Projects
|
27/octubre/2025
|
2025/10/27
|
Documento
|
|
Informative Motion on the Status of SOW: 4×25 MW BESS Interconnections at LUMA 38kV System (October 2025)
Asunto: LUMA – Informative Motion on the Status of SOW: 4×25 MW BESS Interconnections at LUMA 38kV System (October 2025)
|
27/octubre/2025
|
2025/10/27
|
Documento
|
|
Notice of Official Email Address and Request for Notice
Asunto: PREPA – Notice of Official Email Address and Request for Notice
|
24/octubre/2025
|
2025/10/24
|
Documento
|
|
Motion Resubmitting Corrected Exhibit 2 of the October 14, 2025, Motion in Compliance with Resolution and Order of October 3, 2025
Asunto: Corrected Exhibit 2 Motion Resubmitting
|
15/octubre/2025
|
2025/10/15
|
Documento
|
|
Motion Resubmitting Corrected Exhibit 2 of the October 14, 2025, Motion in Compliance with Resolution and Order of October 3, 2025
Asunto: LUMA – Motion Resubmitting Corrected Exhibit 2 of the October 14, 2025, Motion in Compliance with Resolution and Order of October 3, 2025
|
15/octubre/2025
|
2025/10/15
|
Documento
|
|
Motion in Compliance with Resolution and Order of October 3, 2025
Asunto: PREPA Exhibit II
|
14/octubre/2025
|
2025/10/14
|
Documento
|
|
Motion in Compliance with Resolution and Order of October 3, 2025
Asunto: PREPA Exhibit I Comprehensive Consolidated Project List.
|
14/octubre/2025
|
2025/10/14
|
Documento
|
|
Motion in Compliance with Resolution and Order of October 3, 2025
Asunto: LUMA – Motion in Compliance with Resolution and Order of October 3, 2025
|
14/octubre/2025
|
2025/10/14
|
Documento
|
|
Notice of Appearance, Request for Notice and Withdrawal as Attorney of Record
Asunto: PREPA – Notice of Appearance, Request for Notice and Withdrawal as Attorney of Record
|
14/octubre/2025
|
2025/10/14
|
Documento
|
|
Motion to Submit Comprehensive Consolidated List in Compliance with Resolution and Order Dated October 3, 2025
Asunto: Exhibit A Motion to Subm Comprehensive Cons List
|
10/octubre/2025
|
2025/10/10
|
Documento
|
|
Motion to Submit Comprehensive Consolidated List in Compliance with Resolution and Order Dated October 3, 2025
Asunto: Genera – Motion to Submit Comprehensive Consolidated List in Compliance with Resolution and Order Dated October 3, 2025
|
10/octubre/2025
|
2025/10/10
|
Documento
|
|
Resolution and Order
Asunto: GENERA Consolidated Project list
|
03/octubre/2025
|
2025/10/03
|
Documento
|
|
Resolution and Order
Asunto: LUMA Consolidated Project list
|
03/octubre/2025
|
2025/10/03
|
Documento
|
|
Resolution and Order
Asunto: PREPA Consolidated Project list
|
03/octubre/2025
|
2025/10/03
|
Documento
|
|
Resolution and Order
Asunto: Oversight Of Puerto Rico’s Electric System Modernization Efforts and the Consolidated FEMA Project List
|
03/octubre/2025
|
2025/10/03
|
Documento
|
|
Motion Submitting Seven FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting Seven FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
|
03/octubre/2025
|
2025/10/03
|
Documento
|
|
Motion Submitting Eighteen FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting Eighteen FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
|
26/septiembre/2025
|
2025/09/26
|
Documento
|
|
Informative Motion on the Status of SOW: 4×25 MW BESS Interconnections at LUMA 38KV System (September 2025) and Request for Modification of Reporting Requirement
Asunto: Informative Motion on the Status of SOW: 4×25 MW BESS Interconnections at LUMA 38KV System (September 2025) and Request for Modification of Reporting Requirement
|
26/septiembre/2025
|
2025/09/26
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order for Motion for Approval to Submit Continuous Monitoring System Project to FEMA.
|
16/septiembre/2025
|
2025/09/16
|
Documento
|
|
Motion in Compliance with Resolution and Order of August 14, 2025
Asunto: Motion in Compliance with Resolution and Order of August 14, 2025
|
12/septiembre/2025
|
2025/09/12
|
Documento
|
|
Motion in Compliance with Resolution and Order of August 14, 2025
Asunto: Motion in Compliance with Resolution and Order of August 14, 2025
|
12/septiembre/2025
|
2025/09/12
|
Documento
|
|
Motion Submitting Two FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting Two FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
|
12/septiembre/2025
|
2025/09/12
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order for Motion for Approval to Submit Continuous Monitoring System Project to FEMA.
|
11/septiembre/2025
|
2025/09/11
|
Documento
|
|
Motion Submitting LUMA’s September 2025 Update to PREPA-LUMA 90-Day Plan for T&D Projects
Asunto: Submital of LUMA’s September 2025 Update to PREPA-LUMA 90-Day Plan for T&D Projects
|
11/septiembre/2025
|
2025/09/11
|
Documento
|
|
Urgent Motion to Reiterate Submission of Fiona Permanent Work Area Plan: Mayagüez G
Asunto: Urgent Motion to Reiterate Submission of Fiona Permanent Work Area Plan: Mayagüez G
|
10/septiembre/2025
|
2025/09/10
|
Documento
|
|
Motion to Submit Monthly BESS Progress Report in Compliance with Resolution and Orders Dated February 1, 2024, and April 23, 2024
Asunto: Genera – Motion to Submit Monthly BESS Progress Report in Compliance with Resolution and Orders Dated February 1, 2024, and April 23, 2024
|
09/septiembre/2025
|
2025/09/09
|
Documento
|
|
Resolution
Asunto: Resolution pertaining to Informative Motion on the Status of SOW: 4X25 MW BESS Interconnections at LUMA 38KV System (August) and Request for Modification of Reporting Requirement, […]
|
29/agosto/2025
|
2025/08/29
|
Documento
|
|
Motion in Compliance with Resolution and Order Dated August 14, 2025
Asunto: PREPA – Exhibit B Motion in Compl with Resol Aug 14 2025
|
29/agosto/2025
|
2025/08/29
|
Documento
|
|
Motion in Compliance with Resolution and Order Dated August 14, 2025
Asunto: PREPA- Exhibit A Motion in Compl with Resol Aug 14 2025
|
29/agosto/2025
|
2025/08/29
|
Documento
|
|
Motion in Compliance with Resolution and Order Dated August 14, 2025
Asunto: PREPA – Motion in Compliance with Resolution and Order Dated August 14, 2025
|
29/agosto/2025
|
2025/08/29
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order pertaining to Urgent Motion Requesting Extension of Time to Comply with Resolution and Order of August 14, 2025, filed by LUMA Energy, LLC […]
|
28/agosto/2025
|
2025/08/28
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order pertaining to Informative Motion to Submit the Consolidated Project Plan filed by the Puerto Rico Electric Power Authority.
|
27/agosto/2025
|
2025/08/27
|
Documento
|
|
Urgent Motion Requesting Extension of Time to Comply with Resolution and Order of August 14, 2025
Asunto: LUMA – Urgent Motion Requesting Extension of Time to Comply with Resolution and Order of August 14, 2025
|
27/agosto/2025
|
2025/08/27
|
Documento
|
|
Resolution and Order
Asunto: 20250814 MI20210002 Attachment B
|
14/agosto/2025
|
2025/08/14
|
Documento
|
|
Resolution and Order
Asunto: 20250814 MI20210002 Attachment A
|
14/agosto/2025
|
2025/08/14
|
Documento
|
|
Resolution and Order
Asunto: Oversight Of Puerto Rico’s Electric System Modernization Efforts and Energy Grid Rehabilitation and Reconstruction Cost Share Program Project Status.
|
14/agosto/2025
|
2025/08/14
|
Documento
|
|
Motion Submitting Quarterly Report on Federal Funding Activities for the Fourth Quarter of Fiscal Year 2025
Asunto: IN RE: Review of the Puerto Rico Electric Power Authority’s 10-Year Infrastructure Plan-December 2020
|
14/agosto/2025
|
2025/08/14
|
Documento
|
|
Motion to Submit Monthly BESS Progress Report in Compliance with Resolution and Orders Dated February 1, 2024, and April 23, 2024
Asunto: Genera – Motion to Submit Monthly BESS Progress Report in Compliance with Resolution and Orders Dated February 1, 2024, and April 23, 2024
|
08/agosto/2025
|
2025/08/08
|
Documento
|
|
Informative Motion to Submit the Consolidated Project Plan
Asunto: PREPA – Exhibit B Inf Motion to Subm Consolidated Project Plan.pdf
|
08/agosto/2025
|
2025/08/08
|
Documento
|
|
Informative Motion to Submit the Consolidated Project Plan
Asunto: PREPA – Exhibit A Inf Motion to Subm Consolidated Project Plan
|
08/agosto/2025
|
2025/08/08
|
Documento
|
|
Informative Motion to Submit the Consolidated Project Plan
Asunto: PREPA – Informative Motion to Submit the Consolidated Project Plan
|
08/agosto/2025
|
2025/08/08
|
Documento
|
|
Informative Motion on the Status of SOW: 4×25 MW BESS Interconnections at LUMA 38kV System (July) and Request for Modification of Reporting Requirement
Asunto: LUMA – Informative Motion on the Status of SOW: 4×25 MW BESS Interconnections at LUMA 38kV System (July) and Request for Modification of Reporting Requirement
|
29/julio/2025
|
2025/07/29
|
Documento
|
|
Motion to Submit Monthly BESS Progress Report in Compliance with Resolutions and Orders Dated February 1, 2024, and April 23, 2024
Asunto: IN RE: Review of the Puerto Rico Electric Power Authority’s 10-Year Infrastructure PLan-December 2020
|
10/julio/2025
|
2025/07/10
|
Documento
|
|
Motion to Submit PREPA’s June 2025 Update to the PREPA-LUMA 90-Day Plan
Asunto: Motion to Submit PREPA’s June 2025 Update to the PREPA-LUMA 90-Day Plan
|
30/junio/2025
|
2025/06/30
|
Documento
|
|
Motion Submitting One Area Plan , Request for Confidentiality, and Supporting Memorandum of Law
Asunto: LUMA – Motion Submitting One Area Plan , Request for Confidentiality, and Supporting Memorandum of Law
|
27/junio/2025
|
2025/06/27
|
Documento
|
|
Informative Motion on the Status of SOW: 4×25 MW BESS Interconnections at LUMA 38KV System, Request for Confidentiality and Supporting Memorandum of Law
Asunto: LUMA – Informative Motion on the Status of SOW: 4×25 MW BESS Interconnections at LUMA 38KV System, Request for Confidentiality and Supporting Memorandum of Law
|
27/junio/2025
|
2025/06/27
|
Documento
|
|
Motion in Compliance with Resolution and Order of June 13, 2025, Request for Confidentiality, and Memorandum in Support of Confidentiality
Asunto: LUMA – Motion in Compliance with Resolution and Order of June 13, 2025, Request for Confidentiality, and Memorandum in Support of Confidentiality
|
23/junio/2025
|
2025/06/23
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order – Oversight Field Visits at different LUMA project execution locations.
|
13/junio/2025
|
2025/06/13
|
Documento
|
|
Motion to Submit Monthly BESS Progress Report in Compliance with Resolution and Orders Dated February 1, 2024, and April 23, 2024
Asunto: Genera – Motion to Submit Monthly BESS Progress Report in Compliance with Resolution and Orders Dated February 1, 2024, and April 23, 2024
|
10/junio/2025
|
2025/06/10
|
Documento
|
|
Motion Submitting LUMA’s June 2025 Update to PREPA-LUMA 90-Day Plan for T&D Projects
Asunto: Motion Submitting LUMA’s June 2025 Update to PREPA-LUMA 90-Day Plan for T&D Projects
|
10/junio/2025
|
2025/06/10
|
Documento
|
|
Motion to Inform the Filing of Motion to Show Cause Why Sanctions Should Not Be Imposed in Compliance with the May 30th Order and Request for Reconsideration
Asunto: Genera – Motion to Inform the Filing of Motion to Show Cause Why Sanctions Should Not Be Imposed in Compliance with the May 30th Order and […]
|
09/junio/2025
|
2025/06/09
|
Documento
|
|
Notice of Appearance and Request for Notice
Asunto: Notice of Appearance and Request for Notice
|
06/junio/2025
|
2025/06/06
|
Documento
|
|
Informative Motion on Modification of FEMA Assistance for Federally Funded Project, Request for Confidentiality, and Memorandum in Support of Confidentiality
Asunto: Informative Motion on Modification of FEMA Assistance for Federally Funded Project, Request for Confidentiality, and Memorandum in Support of Confidentiality
|
06/junio/2025
|
2025/06/06
|
Documento
|
|
Informative Motion on Modification of FEMA Assistance for Federally Funded Project, Request for Confidentiality, and Memorandum in Support of Confidentiality
Asunto: Informative Motion on Modification of FEMA Assistance for Federally Funded Project, Request for Confidentiality, and Memorandum in Support of Confidentiality
|
06/junio/2025
|
2025/06/06
|
Documento
|
|
Order to Cease and Desist and to Show Cause
Asunto: Order regarding Motion to Inform Commencement of Activities Pursuant to United States Department of Energy Order No. 202-25-1 for Fuel Swapping Conversion, filed by Genera PR, […]
|
30/mayo/2025
|
2025/05/30
|
Documento
|
|
Informative Motion on the Status of SOW: 4×25 MW BESS Interconnections at LUMA 38 kV System
Asunto: LUMA – Informative Motion on the Status of SOW: 4×25 MW BESS Interconnections at LUMA 38 kV System
|
28/mayo/2025
|
2025/05/28
|
Documento
|
|
Motion to Inform Commencement of Activities Pursuant to United States Department of Energy Order No. 202-25-1 for Fuel Swapping Conversion
Asunto: Genera – Motion to Inform Commencement of Activities Pursuant to United States Department of Energy Order No. 202-25-1 for Fuel Swapping Conversion
|
28/mayo/2025
|
2025/05/28
|
Documento
|
|
Informative Motion on Change of FEMA Assistance for Federally Funded Project
Asunto: LUMA – Informative Motion on Change of FEMA Assistance for Federally Funded Project
|
21/mayo/2025
|
2025/05/21
|
Documento
|
|
Motion to Submit the Monthly BESS Progress Report for April 2025 in Compliance with Resolutions and Orders Dated February 1, 2024, and April 23, 2024
Asunto: Genera – Motion to Submit the Monthly BESS Progress Report for April 2025 in Compliance with Resolutions and Orders Dated February 1, 2024, and April 23, […]
|
08/mayo/2025
|
2025/05/08
|
Documento
|
|
Motion Submitting Four FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting Four FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
|
01/mayo/2025
|
2025/05/01
|
Documento
|
|
Resolución y Orden
Asunto: Radicación de solicitudes de fondos federales
|
30/abril/2025
|
2025/04/30
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order for Motion Submitting Amended Scope of Work and Request for Confidentiality and Supporting Memorandum of Law
|
30/abril/2025
|
2025/04/30
|
Documento
|
|
Documento no encontrado.
Asunto: LUMA – Informative Motion on the Status of SOW: 4×25 MW BESS Interconnections at LUMA 38kv System, Request for Confidential and Supporting Memorandum of Law
|
28/abril/2025
|
2025/04/28
|
|
|
Request to Add Point of Contact to Notices
Asunto: Request to Add Point of Contact to Notices
|
25/abril/2025
|
2025/04/25
|
Documento
|
|
Notice of Withdrawal Attorney of Record
Asunto: Notice of Withdrawal Attorney of Record – Lcdo. Alejandro López Rodríguez
|
16/abril/2025
|
2025/04/16
|
Documento
|
|
Notice of Appearance and Request for Notice
Asunto: Notice of Appearance and Request for Notice
|
09/abril/2025
|
2025/04/09
|
Documento
|
|
Motion to Submit the Monthly BESS Progress Report for March 2025 in Compliance with the Resolution and Orders Dated February 1, 2024, and April 23, 2024
Asunto: Motion to Submit the Monthly BESS Progress Report for March 2025 in Compliance with the Resolutions and Orders Dated February 1, 2024, and April 23, 2024
|
09/abril/2025
|
2025/04/09
|
Documento
|
|
Motion to Submit PREPA’s March 2025 Update to the PREPA-LUMA 90-Day Plan
Asunto: Motion to Submit PREPA’s March 2025 Update to the PREPA-LUMA 90-Day Plan
|
31/marzo/2025
|
2025/03/31
|
Documento
|
|
Informative Motion on the Status of SOW: 4×25 MW BESS Interconnections at LUMA 38kV System
Asunto: LUMA – Informative Motion on the Status of SOW: 4×25 MW BESS Interconnections at LUMA 38kV System
|
28/marzo/2025
|
2025/03/28
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order for Motion Submitting One Scope of Work, Request for Confidential-ity and Supporting Memorandum of Law.
|
24/marzo/2025
|
2025/03/24
|
Documento
|
|
Motion Submitting Amended Scope of Work and Request for Confidentiality and Supporting Memorandum of Law
Asunto: LUMA – Motion Submitting Amended Scope of Work and Request for Confidentiality and Supporting Memorandum of Law
|
14/marzo/2025
|
2025/03/14
|
Documento
|
|
Notice of Appearance and Request for Notice
Asunto: Notice of Appearance and Request for Notice
|
13/marzo/2025
|
2025/03/13
|
Documento
|
|
Motion Submitting LUMA’s March 2025 Update to PREPA-LUMA 90-Day Plan for T&D Projects
Asunto: Motion Submitting LUMA’s March 2025 Update to PREPA-LUMA 90-Day Plan for T&D Projects
|
11/marzo/2025
|
2025/03/11
|
Documento
|
|
Motion to Submit the Monthly BESS Progress Report for January 2025 in Compliance with the Resolution and Orders Dated February 1, 2024, and April 23, 2024
Asunto: Motion to Submit the Monthly BESS Progress Report for January 2025 in Compliance with the Resolution and Orders Dated February 1, 2024, and April 23, 2024
|
10/marzo/2025
|
2025/03/10
|
Documento
|
|
Informative Motion on the Status of SOW: 4×25 MW BESS Interconnections at LUMA 38kv System
Asunto: Informative Motion on the Status of SOW: 4 x 25 MW BESS Interconnections at LUMA 38kv System
|
28/febrero/2025
|
2025/02/28
|
Documento
|
|
Notice Withdrawal as Attorney of Record
Asunto: Notice Withdrawal as Attorney of Record
|
25/febrero/2025
|
2025/02/25
|
Documento
|
|
Amended Motion to Request Approval for Rehabilitation Projects for the San Juan Plant Units 8 and 10 and Cambalache 1
Asunto: Genera – Amended Motion to Request Approval for Rehabilitation Projects for the San Juan Plant Units 8 and 10 and Cambalache 1
|
24/febrero/2025
|
2025/02/24
|
Documento
|
|
Motion to Request Approval for Rehabilitation Projects for the San Juan Plant Units 8 and 10 Cambalache
Asunto: Genera – Motion to Request Approval for Rehabilitation Projects for the San Juan Plant Units 8 and 10 Cambalache
|
21/febrero/2025
|
2025/02/21
|
Documento
|
|
Motion for Approval of Scope of Work
Asunto: Motion for Approval of Scope of Work
|
20/febrero/2025
|
2025/02/20
|
Documento
|
|
Motion Submitting Quarterly Report on Federal Funding Activities for the Second Quarter of Fiscal Year 2025
Asunto: LUMA – Motion Submitting Quarterly Report on Federal Funding Activities for the Second Quarter of Fiscal Year 2025
|
14/febrero/2025
|
2025/02/14
|
Documento
|
|
Motion Submitting Seven FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting Seven FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
|
11/febrero/2025
|
2025/02/11
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order on Genera’s January 31, 2025, and February 3, 2025, Motions in Connection with Genera’s FY2025 NME Budget Reallocation Request
|
10/febrero/2025
|
2025/02/10
|
Documento
|
|
Motion to Submit the Monthly BESS Progress Report for January 2025 in Compliance with the Resolutions and Orders Dated Febrruary 1, 2024, and April 23, 2024
Asunto: IN RE: Review of the Puerto Rico Electric Power Authority’s 10-Year Infrastructure Plan-December 2020
|
10/febrero/2025
|
2025/02/10
|
Documento
|
|
Resolution and Order for Motion Submitting Three Amended Scope of Works, December 12, 2024, filed by LUMA
Asunto: Resolution and Order for Motion Submitting Three Amended Scope of Works, December 12, 2024, filed by LUMA
|
07/febrero/2025
|
2025/02/07
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order for Motion Submitting One Scope of Work, Request for Confidentiality and Supporting Memorandum of Law
|
06/febrero/2025
|
2025/02/06
|
Documento
|
|
Motion to Submit Partial Response to Resolution and Order Dated January 14, 2025
Asunto: Genera – Motion to Submit Partial Response to Resolution and Order Dated January 14, 2025
|
03/febrero/2025
|
2025/02/03
|
Documento
|
|
Motion to Submit Estimated Costs for SOWs Listed in Resolution and Order Dated January 14, 2025
Asunto: Genera – Motion to Submit Estimated Costs for SOWs Listed in Resolution and Order Dated January 14, 2025
|
31/enero/2025
|
2025/01/31
|
Documento
|
|
Informative Motion on the Status of SPW: 4 x 25 MW BESS Interconnections at LUMA 38kV System, Request for Confidentiality and Supporting Memorandum of Law
Asunto: LUMA – Informative Motion on the Status of SPW: 4 x 25 MW BESS Interconnections at LUMA 38kV System, Request for Confidentiality and Supporting Memorandum of […]
|
28/enero/2025
|
2025/01/28
|
Documento
|
|
Resolution Nunc Pro Tunc
Asunto: Resolution Nunc Pro Tunc; Correction of Company Name on page 3 of Resolution and Order for the Scope of Works (SOWs) of twenty-three (23) Projects in […]
|
24/enero/2025
|
2025/01/24
|
Documento
|
|
Urgent Request for Extension to Submit Response to the Resolution and Order Dated January 14, 2025
Asunto: Urgent Request for Extension to Submit Response to the Resolution and Order Dated January 14, 2025.
|
24/enero/2025
|
2025/01/24
|
Documento
|
|
Motion Submitting One Scope of Work, Request for Confidentiality and Supporting Memorandum of Law, and Request for Expedited Approval
Asunto: LUMA – Motion Submitting One Scope of Work, Request for Confidentiality and Supporting Memorandum of Law, and Request for Expedited Approval
|
21/enero/2025
|
2025/01/21
|
Documento
|
|
Motion Submitting One FEMA Project Approval, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: LUMA- Motion Submitting One FEMA Project Approval, Request for Confidential Treatment and Supporting Memorandum of Law
|
15/enero/2025
|
2025/01/15
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order for the Scope of Works (SOWs) of twenty-three (23) Projects in Connection with Genera’s FY2025 NME Budget Reallocation Request
|
14/enero/2025
|
2025/01/14
|
Documento
|
|
Resolution and Order
Asunto: Status of SOW for: «4 x 25 MW BESS Interconnections at LUMA 38kV System»
|
14/enero/2025
|
2025/01/14
|
Documento
|
|
Resolution and order
Asunto: Resolution and Order for Motion to Submit Response in Compliance with Resolution and Order Dated December 18, 2024, regarding the Scope of Work for the Generation […]
|
10/enero/2025
|
2025/01/10
|
Documento
|
|
Informative Motion on the Status of SOW: 4 x 25 MW BESS Interconnections at LUMA 38KV System
Asunto: Luma – Informative Motion on the Status of SOW: 4 x 25 MW BESS Interconnections at LUMA 38KV System
|
09/enero/2025
|
2025/01/09
|
Documento
|
|
Motion to Submit Monthly BESS Report in Compliance with Resolution and Orders Dated February 1, 2024 and April 23, 2024
Asunto: Genera – Motion to Submit Monthly BESS Report in Compliance with Resolution and Orders Dated February 1, 2024 and April 23, 2024
|
08/enero/2025
|
2025/01/08
|
Documento
|
|
Informative Motion on Contracted Costs for Federally Funded Projects
Asunto: LUMA – Informative Motion on Contracted Costs for Federally Funded Projects
|
03/enero/2025
|
2025/01/03
|
Documento
|
|
Memorandum of Law in Support of Confidential Treatment of Attachment Submitted as Part of Response Filed on December 24, 2024
Asunto: Genera – Memorandum of Law in Support of Confidential Treatment of Attachment Submitted as Part of Response Filed on December 24, 2024
|
03/enero/2025
|
2025/01/03
|
Documento
|
|
Resolution and Order
Asunto: Status of SOW for: «4 x 25 MW BESS Inter-connections at LUMA 38kV System”
|
03/enero/2025
|
2025/01/03
|
Documento
|
|
Motion to Submit Response in Compliance with Resolution and Order Dated December 18, 2024
Asunto: IN RE: Review of the Puerto Rico Electric Power Authority’s 10-Year Infrastructure Plan-December 2020
|
24/diciembre/2024
|
2024/12/24
|
Documento
|
|
Motion to Submit PREPA’s December 2024 Update to the PREPA-GENERA-LUMA 90-day Plan
Asunto: PREPA’s December 2024 Update to the PREPA-GENERA-LUMA 90-day Plan
|
18/diciembre/2024
|
2024/12/18
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order for Motion to Submit Detailed Scope of Work for the Generation Fleet Project, No. 164988
|
18/diciembre/2024
|
2024/12/18
|
Documento
|
|
Request to Add LUMA Email Address to Notices
Asunto: Request to Add LUMA Email Address to Notices
|
12/diciembre/2024
|
2024/12/12
|
Documento
|
|
Motion Submitting Three Amended Scopes of Work, and Request for Confidentiality and Supporting Memorandum of Law
Asunto: Motion Submitting Three Amended Scopes of Work, and Request for Confidentiality and Supporting Memorandum of Law
|
12/diciembre/2024
|
2024/12/12
|
Documento
|
|
Motion Submitting LUMA’s December 2024 Update to PREPA-LUMA 90-Day Plan for T&D Projects
Asunto: Submittal of LUMA’s December 2024 Update to PREPA-LUMA 90-Day Plan for T&D Projects
|
11/diciembre/2024
|
2024/12/11
|
Documento
|
|
Motion to Submit Monthly BESS Progress Report in Compliance with Resolution and Orders Dated February 1, 2024, and April 23, 2024
Asunto: Genera – Motion to Submit Monthly BESS Progress Report in Compliance with Resolution and Orders Dated February 1, 2024, and April 23, 2024
|
09/diciembre/2024
|
2024/12/09
|
Documento
|
|
Motion Submitting Three FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: LUMA – Motion Submitting Three FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
|
03/diciembre/2024
|
2024/12/03
|
Documento
|
|
Motion Submitting Nine Scope of Works in Connection with Genera’s FY2025 NME Budget Reallocation Request
Asunto: Genera – Motion Submitting Nine Scope of Works in Connection with Genera’s FY2025 NME Budget Reallocation Request
|
27/noviembre/2024
|
2024/11/27
|
Documento
|
|
Joinder to Genera’s November 13th, 2024 Motion to Submit FEMA Approval for the Equipment and Materials Project for Project #673691
Asunto: IN RE: Review of the Puerto Rico Electric Power Authority’s 10-Year Infrastructure Plan-December 2020
|
18/noviembre/2024
|
2024/11/18
|
Documento
|
|
Motion Submitting Quarterly Report on Federal Funding Activities for the First Quarter of Fiscal Year 2025
Asunto: Submission of Quarterly Report on Federal Funding Activities.
|
14/noviembre/2024
|
2024/11/14
|
Documento
|
|
Motion to Submit FEMA Approval for the Equipment and Materials Project for Project #673691
Asunto: Motion to Submit FEMA Approval for the Equipment and Materials Project for Project #673691
|
13/noviembre/2024
|
2024/11/13
|
Documento
|
|
Motion to Submit Monthly Bess Progress Report in Compliance with Resolutions and Orders Dated February 1, 2024 and April 23, 2024
Asunto: Motion to Submit Monthly Bess Progress Report in Compliance with Resolutions and Orders Dated February 1, 2024 and April 23, 2024
|
08/noviembre/2024
|
2024/11/08
|
Documento
|
|
Motion Submitting Seven (7) Scope of Works in Connection with Genera’s FY2025 NME Budget Reallocation Request
Asunto: IN RE: Review of the Puerto Rico Electric Power Authority’s 10-Year Infrastructure Plan – December 2020
|
04/noviembre/2024
|
2024/11/04
|
Documento
|
|
Motion to Submit Genera’s Informative Memorandum Regarding Opportunity to Expand Costa Sur Peaker Project to a Combined Cycle Configuration
Asunto: Motion to Submit Genera’s Informative Memorandum Regarding Opportunity to Expand Costa Sur Peaker Project to a Combined Cycle Configuration
|
25/octubre/2024
|
2024/10/25
|
Documento
|
|
Motion Submitting Four Amended Scopes of Work, and Request for Confidentiality and Supporting Memorandum of Law
Asunto: IN RE: Review of the Puerto Rico Electric Power Authority’s 10-Year Infrastructure Plan-December 2020
|
14/octubre/2024
|
2024/10/14
|
Documento
|
|
Motion to Submit Monthly Bess Program Report in Compliance with Resolutions and Order Dated February 1, 2024, and April 23, 2024
Asunto: Motion to Submit Monthly Bess Program Report in Compliance with Resolutions and Order Dated February 1, 2024, and April 23, 2024
|
10/octubre/2024
|
2024/10/10
|
Documento
|
|
Motion Submitting List of Potential Transmission and Distribution Asset Sites for Battery Energy Storage Systems in Compliance with Order Issued on September 4, 2024, and Request for Confidentiality and Supporting Memorandum of Law
Asunto: IN RE: Review of the Puerto Rico Electric Power Authority’s 10-Year Infrastructure Plan-December 2020.
|
08/octubre/2024
|
2024/10/08
|
Documento
|
|
Redacted Exhibit 1Motion Submitting List of Potential Transmission and Distribution Asset Sites for Battery Energy Storage Systems in Compliance with Order Issued on September 4, 2024, and Request for Confidentiality and Supporting Memorandum of Law
Asunto: IN RE: Review of the Puerto Rico Electric Power Authority’s 10- Year Infrastructure Plan-December 2020
|
08/octubre/2024
|
2024/10/08
|
Documento
|
|
Motion to Submit Detailed Scope of Work for the Generation Fleet Project, No. 164988
Asunto: Genera – Motion to Submit Detailed Scope of Work for the Generation Fleet Project, No. 164988
|
02/octubre/2024
|
2024/10/02
|
Documento
|
|
Motion to Submit PREPA’s September 2024 Update to the PREPA-LUMA 90-Day Plan
Asunto: IN RE: Review of the Puerto Rico Electric Power Authority’s 10-Year Infrastructure Plan-December 2020.
|
27/septiembre/2024
|
2024/09/27
|
Documento
|
|
Motion Submitting One FEMA Project Approval, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: IN RE: Review of the Puerto Rico Electric Power Authority’s 10-Year Infrastructure Plan-December 2020.
|
20/septiembre/2024
|
2024/09/20
|
Documento
|
|
Motion to Inform Obligation of Bess Installation Sow at Generation Sites and to Further Supplement the September 11, 2024 Submittal
Asunto: Motion to Inform Obligation of Bess Installation Sow at Generation Sites and to Further Supplement the September 11, 2024 Submittal
|
19/septiembre/2024
|
2024/09/19
|
Documento
|
|
Request for Extension of Time to Comply with Resolution and Order Issued on September 4, 2024
Asunto: IN RE: Review of the Puerto Rico Electric Power Authority’s 10-Year Infrastructure Plan-December 2020.
|
18/septiembre/2024
|
2024/09/18
|
Documento
|
|
Motion Submitting LUMA’s September 2024 Update to PREPA-LUMA 90-Day Plan for T&D Projects
Asunto: Submittal of LUMA’s September 2024 Update to PREPA-LUMA 90-Day Plan for T&D Projects
|
11/septiembre/2024
|
2024/09/11
|
Documento
|
|
Motion to Submit a Supplement to the Monthly Bess Progress Report Submitted on September 10, 2024
Asunto: Motion to Submit a Supplement to the Monthly Bess Progress Report Submitted on September 10, 2024
|
11/septiembre/2024
|
2024/09/11
|
Documento
|
|
Motion to Submit Monthly Bess Progress Report and Response to Resolution and Order Dated September 4, 2024
Asunto: Motion to Submit Monthly Bess Progress Report and Response to Resolution and Order Dated September 4, 2024
|
10/septiembre/2024
|
2024/09/10
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order for LUMA and Genera’s BESS Project.
|
04/septiembre/2024
|
2024/09/04
|
Documento
|
|
Motion to Submit Response to Request for Information in Compliance with the Resolution and Order Dated August 26, 2024
Asunto: IN RE: Review of the Puerto Rico Electric Power Authority’s 10-Year Infrastructure Plan-December 2020.
|
03/septiembre/2024
|
2024/09/03
|
Documento
|
|
Motion Submitting LUMA’s Amendment to the June 2024 Update to PREPA-LUMA 90-Day Plan for T&D Projects
Asunto: IN RE: Review of the Puerto Rico Electric Power Authority’s 10-Year Infrastructure Plan-December 2020
|
30/agosto/2024
|
2024/08/30
|
Documento
|
|
Resolution and Order
Asunto: Determination on LUMA’s Motion Submitting Two Initial Scopes of Work and a Request for Confidentiality and Supporting Memorandum of Law, dated August 23, 2024.
|
28/agosto/2024
|
2024/08/28
|
Documento
|
|
Resolution and Order
Asunto: Determination on GENERA’s August 19 Motion to Clarify and Request Amendment of Resolution and Order dated August 8, 2024.
|
26/agosto/2024
|
2024/08/26
|
Documento
|
|
Motion Submitting two Initial Scopes of Work and Request for Confidentiality and Supporting Memorandum of Law
Asunto: Motion Submitting two Initial Scopes of Work and Request for Confidentiality and Supporting Memorandum of Law
|
23/agosto/2024
|
2024/08/23
|
Documento
|
|
Resolution and Order
Asunto: Determination on LUMA’s July 31 2024, Motion Submitting Three (3) Amended SOW, One (1) SOW, an Updated Project List, and Request for Confidentiality and Supporting Memorandum […]
|
22/agosto/2024
|
2024/08/22
|
Documento
|
|
Urgent Request for Extension to Submit Response to Resolution and Order Dated August 8, 2024
Asunto: IN RE: Review of the Puerto Rico Electric Power Authority’s 10-Year Infrastructure Plan – December 2020.
|
13/agosto/2024
|
2024/08/13
|
Documento
|
|
Motion Submitting Quarterly Report on Federal Funding Activities for the Fourth Quarter of Fiscal Year 2024
Asunto: Submission of Quarterly Report on Federal Funding Activities.
|
12/agosto/2024
|
2024/08/12
|
Documento
|
|
Motion to Submit Monthly Bess Progress Report in Compliance with Resolutionand Orders Dated February 1, 2024, and April 23, 2024
Asunto: Motion to Submit Monthly Bess Progress Report in Compliance with Resolutionand Orders Dated February 1, 2024, and April 23, 2024
|
09/agosto/2024
|
2024/08/09
|
Documento
|
|
Resolution and Order
Asunto: IN RE: Review of the Puerto Rico Electric Power Authority’s 10-Year Infrastructure Plan – December 2020.
|
08/agosto/2024
|
2024/08/08
|
Documento
|
|
Resolution and Order
Asunto: IN RE: Review of the Puerto Rico Electric Power Authority’s 10-Year Infrastructure Plan – December 2020.
|
08/agosto/2024
|
2024/08/08
|
Documento
|
|
Motion to Inform Status of Federally Funded Projects
Asunto: Motion to Inform Status of Federally Funded Projects
|
01/agosto/2024
|
2024/08/01
|
Documento
|
|
Motion Submitting Three Amended Scopes of Work, One Scope of Work, an Updated Project List, and Request for Confidentiality and Supporting Memorandum of Law
Asunto: IN RE: Review of the Puerto Rico Electric Power Authority’s 10-Year Infraestructure Plan-December 2020.
|
31/julio/2024
|
2024/07/31
|
Documento
|
|
Resolution and Order
Asunto: Determination on LUMA’s Motion Submitting Four Scopes of Work and a Request for Confidentiality and Supporting Memorandum of Law dated June 28, 2024.
|
24/julio/2024
|
2024/07/24
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order to Request for Approval of Operation, Fleet and Equipment Purchase Project SOW, filed by Genera on May 28, 2024.
|
24/julio/2024
|
2024/07/24
|
Documento
|
|
Motion to Submit two Scope of Work for Critical Infrastructure Projects at the Aguirre Power Plant and the San Juan Steam Plant
Asunto: Motion to Submit two Scope of Work for Critical Infrastructure Projects at the Aguirre Power Plant and the San Juan Steam Plant
|
24/julio/2024
|
2024/07/24
|
Documento
|
|
Motion Informing the Withdrawal of Federally Funded Projects and Submitting One Scope of Work and Request for Confidentiality and Supporting Memorandum of Law
Asunto: IN RE: Review of The Puerto Rico Electric Power Authority’s 10-year Infraestructure Plan-December 2020.
|
19/julio/2024
|
2024/07/19
|
Documento
|
|
Resolution and Order
Asunto: Genera Motion Requesting Acceptance of Amended Scope of Work for Battery Energy Storage System Project.
|
17/julio/2024
|
2024/07/17
|
Documento
|
|
Motion Submitting Four FEMA Approvals of Projects, Request for Confidential Treatment and Supporting memorandum of Law
Asunto: IN RE: Review fo the Puerto Rico Electric Power Authority’s 10-year Infraestructure Plan-December 2020.
|
12/julio/2024
|
2024/07/12
|
Documento
|
|
Motion to Submit Monthly BESS Progress Report in Compliance with Resolutions and Orders Dated February 1, 2024, and April 23, 2024
Asunto: IN RE: Review of the Puerto Rico Electric Power Authority’s 10-Year Infraestructure Plan-December 2020.
|
10/julio/2024
|
2024/07/10
|
Documento
|
|
Motion Submitting One Updated FEMA Approval of Project, Request for Confidential Treatment, and Supporting Memorandum of Law
Asunto: Motion Submitting One Updated FEMA Approval of Project, Request for Confidential Treatment, and Supporting Memorandum of Law
|
03/julio/2024
|
2024/07/03
|
Documento
|
|
Resolution and Order
Asunto: Determination on LUMA’s Motion Submitting One Scope of Work and a Request for Confidentiality and Supporting Memorandum of Law, dated June 21, 2024.
|
28/junio/2024
|
2024/06/28
|
Documento
|
|
Resolution and Order
Asunto: Determination on LUMA’s June 13, 2024, Motion Submitting Amended Scope of Work, and Request for Confidentiality and Supporting Memorandum of Law.
|
28/junio/2024
|
2024/06/28
|
Documento
|
|
Motion to Submit Response in Compliance with Resolution and Order Dated June 17, 2024
Asunto: IN RE: Review of The Puerto Rico Electric Power Authority’s 10 – Year Infraestructure Plan – December 2020.
|
28/junio/2024
|
2024/06/28
|
Documento
|
|
Motion Submitting Four Scopes of Work and Request for Confidentiality and Supporting Memorandum of Law
Asunto: IN RE: Review of The Puerto Rico Electric Power Authority’s 10-Year Infraestructure Plan-December 2020.
|
28/junio/2024
|
2024/06/28
|
Documento
|
|
Motion Submitting Five FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: In Re: Review of the Puerto Rico Electric Power Authority’s 10-Year Infrastructure Plan-December 2020.
|
25/junio/2024
|
2024/06/25
|
Documento
|
|
Motion to Submit PREPA’s June 2024 Update to the PREPA-LUMA 90-Day Plan
Asunto: Motion to Submit PREPA’s June 2024 Update to the PREPA-LUMA 90-Day Plan
|
21/junio/2024
|
2024/06/21
|
Documento
|
|
Motion Submitting One Scope of Work and a Request for Confidentiality and Supporting Memorandum of Law
Asunto: IN RE: Review of the Puerto Rico Electric Power Authority’s 10-Year Infrastructure Plan-December 2020.
|
21/junio/2024
|
2024/06/21
|
Documento
|
|
Motion to Submit Amended Scope of Work for Project No.164988
Asunto: Motion to Submit Amended Scope of Work for Project No.164988
|
20/junio/2024
|
2024/06/20
|
Documento
|
|
Resolution Nunc Pro Tunc
Asunto: Resolution Nunc Pro Tunc; Correction of Filing Date
|
18/junio/2024
|
2024/06/18
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order to Request for Approval of Operation, Fleet and Equipment Purchase Project SOW, filed by Genera on May 28, 2024.
|
17/junio/2024
|
2024/06/17
|
Documento
|
|
Motion Submitting ONE FEMA Approval of Project Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting ONE FEMA Approval of Project Request for Confidential Treatment and Supporting Memorandum of Law
|
14/junio/2024
|
2024/06/14
|
Documento
|
|
Motion to Submit Response in Compliance with Resolution and Order Dated May 29, 2024
Asunto: Motion to Submit Response in Compliance with Resolution and Order Dated May 29, 2024
|
11/junio/2024
|
2024/06/11
|
Documento
|
|
Motion Submitting LUMA’s June 2024 Update to PREPA-LUMA 90-day Plan for Project T&D Projects
Asunto: Submittal of LUMA’s June 2024 Update to PREPA-LUMA 90-day Plan for Project T&D Projects
|
11/junio/2024
|
2024/06/11
|
Documento
|
|
Motion to Submit Monthly Bess Progress Report in Compliance with Resolution and Order Dated February 1, 2024, and April 23, 2024
Asunto: Motion to Submit Monthly Bess Progress Report in Compliance with Resolution and Order Dated February 1, 2024, and April 23, 2024
|
10/junio/2024
|
2024/06/10
|
Documento
|
|
Motion Submitting Three FEMA Approvals of Projects, Request for Confidential Treatment, and Supporting Memorandum of Law
Asunto: Motion Submitting Three FEMA Approvals of Projects, Request for Confidential Treatment, and Supporting Memorandum of Law
|
04/junio/2024
|
2024/06/04
|
Documento
|
|
Resolution and Order
Asunto: Dates and Frequency for the Visits for revision of FEMA and COR3 approved projects.
|
29/mayo/2024
|
2024/05/29
|
Documento
|
|
Request for Approval of Operation, Fleet and Equipment Purchase Project SOW
Asunto: IN RE: Review of the Puerto Rico Electric Power Authority’s 10-Year Infraestructure Plan – December 2020
|
28/mayo/2024
|
2024/05/28
|
Documento
|
|
Resolution and Order
Asunto: Motion Submitting One Scope of Work and a Request for Confidentiality and Supporting Memorandum of Law filed by LUMA on April 4, 2024, and Motion in […]
|
22/mayo/2024
|
2024/05/22
|
Documento
|
|
Motion Submitting Five FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: IN RE: Review of the Puerto Rico Electric Power Authority’s 10-Year Infraestructure Plan – December 2020
|
17/mayo/2024
|
2024/05/17
|
Documento
|
|
Motion Submitting Quarterly Report on Federal Funding Activities for the Third Quarter of Fiscal Year 2024
Asunto: Submission of Quarterly Report on Federal Funding Activities
|
15/mayo/2024
|
2024/05/15
|
Documento
|
|
Motion to Inform Status of Federally Funded Projects
Asunto: IN RE; Review of the Puerto Rico Electric Power Authority’s 10-Year Infraestructure Plan – December 2020
|
15/mayo/2024
|
2024/05/15
|
Documento
|
|
Motion to Submit Monthly BESS Progress Report in Compliance with Resolution and Order Dated February 1, 2024, and April 23, 2024
Asunto: Review of the Puerto Rico Electric Power Authority’s 10 – Year Infraestructure Plan-December 2020
|
10/mayo/2024
|
2024/05/10
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order in response to Motion in Compliance with the Resolution and Order of April 23, 2024, filed by GENERA on May 1, 2024.
|
09/mayo/2024
|
2024/05/09
|
Documento
|
|
Notice of Appearance
Asunto: Notice of Appearance
|
08/mayo/2024
|
2024/05/08
|
Documento
|
|
Resolution and Order
Asunto: Motion Submitting One Amended Scope of Work and a Request for Confidentiality and Supporting Memorandum of Law and Motion Submitting Eleven Initial Scopes of Work and […]
|
07/mayo/2024
|
2024/05/07
|
Documento
|
|
Motion in Compliance with Resolution and Order of April 23, 2024
Asunto: Motion in Compliance with Resolution and Order of April 23, 2024
|
30/abril/2024
|
2024/04/30
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order to Motion to Submit FEMA Approval in Compliance with Resolution and Order Dated February 1, 2024, filed by Genera on February 12, 2024.
|
23/abril/2024
|
2024/04/23
|
Documento
|
|
Resolution and Order
Asunto: Motion Submitting One Scope of Work and a Request for Confidentiality and Supporting Memorandum of Law and Motion Submitting Forty-One Amended Initial Scopes of Work and […]
|
23/abril/2024
|
2024/04/23
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order on Motion to Submit Scope of Work in Compliance with Resolution and Order dated November 8, 2023, filed by Genera on March 28, […]
|
23/abril/2024
|
2024/04/23
|
Documento
|
|
Motion Submitting Four FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum o Law – Annexes
Asunto: Motion Submitting Four FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum o Law – Annexes
|
18/abril/2024
|
2024/04/18
|
Documento
|
|
Motion Submitting Eleven Initial Scopes of Work and Request for Confidentiality and Supporting Memorandum of Law
Asunto: Review of Puerto Rico Electric Power Authority’s 10-Year Infrastructure Plan – December 2020
|
18/abril/2024
|
2024/04/18
|
Documento
|
|
Motion Submitting One Amended Scope of Work and a Request for Confidentially and Supporting Memorandum of Law
Asunto: Motion Submitting One Amended Scope of Work and a Request for Confidentially and Supporting Memorandum of Law
|
16/abril/2024
|
2024/04/16
|
Documento
|
|
Motion Submitting Supplement to LUMA’s March 2024 Update to PREPA-LUMA 90 day Plan for T&D Projects
Asunto: Supplement to LUMA’s March 2024 Update to PREPA-LUMA 90-day Plan for T&D Projects
|
15/abril/2024
|
2024/04/15
|
Documento
|
|
Motion to Submit Proposed Version 3 of Equipment and Materials Project for Project #3673691 in Compliance with Resolution and Order Dated April 4, 2024
Asunto: Motion to Submit Proposed Version 3 of Equipment and Materials Project for Project #3673691 in Compliance with Resolution and Order Dated April 4, 2024
|
15/abril/2024
|
2024/04/15
|
Documento
|
|
Motion to Submit Monthly Bess Progress Report in Compliance with Resolution and Order Dated February 1, 2024
Asunto: Motion to Submit Monthly Bess Progress Report in Compliance with Resolution and Order Dated February 1, 2024
|
10/abril/2024
|
2024/04/10
|
Documento
|
|
Motion to Inform and Clarify Resolution and Order Dated April 4 2024 and to Show Cause
Asunto: Motion to Inform and Clarify Resolution and Order Dated April 4 2024 and to Show Cause
|
09/abril/2024
|
2024/04/09
|
Documento
|
|
Memorandum of Law in Support of Confidential Treatment of Scope of Work Submitted on March 28, 2024, in Compliance with Resolution and Order Dated November 8, 2023
Asunto: Memorandum of Law in Support of Confidential Treatment of Scope of Work Submitted on March 28, 2024, in Compliance with Resolution and Order Dated November 8, […]
|
08/abril/2024
|
2024/04/08
|
Documento
|
|
Motion Submitting Forty- One Amended and Initial Scopes of Work and Request for Confidentially and Supporting Memorandum of Law
Asunto: Motion Submitting Forty- One Amended and Initial Scopes of Work and Request for Confidentially and Supporting Memorandum of Law
|
05/abril/2024
|
2024/04/05
|
Documento
|
|
Resolution and Order
Asunto: Determination on Motion for Approval of the Scope of Work for the Bonus Facility, presented by PREPA on March 19, 2024
|
04/abril/2024
|
2024/04/04
|
Documento
|
|
Resolution and Order
Asunto: Determination on GENERA’s February 12,2024, Motion to Submit FEMA Approval in Compliance with Resolution and Order Dated February 1, 2024.
|
04/abril/2024
|
2024/04/04
|
Documento
|
|
Motion Submitting one Scope of Work and a Request for Confidentially and Supporting Memorandum of Law
Asunto: Submission of One Scope of Work and a Request for Confidentially and Supporting Memorandum of Law
|
04/abril/2024
|
2024/04/04
|
Documento
|
|
Motion to Submit Scope of Work in Compliance with Resolution and Order Dated November 8, 2023
Asunto: 20240328 MI20210002 Exhibit A – BESS Project Project Aguirre Vega Baja Cambalache Detailed SOW
|
28/marzo/2024
|
2024/03/28
|
Documento
|
|
Motion to Submit Scope of Work in Compliance with Resolution and Order Dated November 8, 2023
Asunto: Motion to Submit Scope of Work in Compliance with Resolution and Order Dated November 8, 2023
|
28/marzo/2024
|
2024/03/28
|
Documento
|
|
Resolution and Order
Asunto: Determination on LUMA’s March 6 Motion, for Submission of Four Initial Scope of Work, Request for Confidentiality and Supporting Memorandum of Law.
|
27/marzo/2024
|
2024/03/27
|
Documento
|
|
Motion Submitting Four FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting Four FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
|
27/marzo/2024
|
2024/03/27
|
Documento
|
|
Motion For Approval of The Scope of Work for The Bonus Facility
Asunto: Motion For Approval of The Scope of Work for The Bonus Facility
|
19/marzo/2024
|
2024/03/19
|
Documento
|
|
Motion to Inform Status of Federally Funded Project
Asunto: Motion to Inform Status of Federally Funded Project
|
14/marzo/2024
|
2024/03/14
|
Documento
|
|
Motion Submitting LUMA’S March 2024 Update to PREPA-LUMA 90-day Plan for T&D Projects
Asunto: Motion Submitting LUMA’S March 2024 Update to PREPA-LUMA 90-day Plan for T&D Projects
|
14/marzo/2024
|
2024/03/14
|
Documento
|
|
Resolution and Order
Asunto: Determination on LUMA’s February 28 Motion, for Submission of Thirteen Initial Scope of Work, Request for Confidentiality and Supporting Memorandum of Law, and Intended Course of […]
|
13/marzo/2024
|
2024/03/13
|
Documento
|
|
Motion to Submit PREPA’s December 2023 and March 2024 Update to the PREPA-LUMA 90-Day Plan
Asunto: Motion to Submit PREPA’s December 2023 and March 2024 Update to the PREPA-LUMA 90-Day Plan
|
11/marzo/2024
|
2024/03/11
|
Documento
|
|
Motion Submitting four Initial Scopes of Work and Request Confidentially and Supporting Memorandum of Law
Asunto: Submission of four Initial Scopes of Work and Request Confidentially and Supporting Memorandum of Law
|
06/marzo/2024
|
2024/03/06
|
Documento
|
|
Motion Submitting Thirteen Initial Scopes of Work for Confidentiality, Supporting Memorandum of Law, and Intended Course of Action for Subsequent Federally Funded T&D Projects
Asunto: Submission of Thirteen Initial Scopes of Work for Confidentiality, Supporting Memorandum of Law, and Intended Course of Action for Subsequent Federally Funded T&D Projects
|
29/febrero/2024
|
2024/02/29
|
Documento
|
|
Motion to Clarify the February 17th Informative Motion
Asunto: Motion to Clarify the February 17th Informative Motion
|
22/febrero/2024
|
2024/02/22
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order regarding Informative Motion and in Compliance with the February 14th Resolution and Order and Urgent Motion Submitting for Review and Approval of the […]
|
21/febrero/2024
|
2024/02/21
|
Documento
|
|
Motion Submitting Two FEMA Approvals of Projects, Request for Confidential Treatment, and Supporting Memorandum of Law
Asunto: Motion Submitting Two FEMA Approvals of Projects, Request for Confidential Treatment, and Supporting Memorandum of Law
|
21/febrero/2024
|
2024/02/21
|
Documento
|
|
Informative Motion and in Compliance with The February 14th Resolution and Order
Asunto: Informative Motion and in Compliance with The February 14th Resolution and Order
|
17/febrero/2024
|
2024/02/17
|
Documento
|
|
Motion to Inform Withdrawal of Federally Funded Projects
Asunto: Motion to Inform Withdrawal of Federally Funded Projects
|
15/febrero/2024
|
2024/02/15
|
Documento
|
|
Resolution and Order
Asunto: Determination on LUMA’s February 2, 2024, Urgent Motion on One Scope of Work, and Request for Confidentiality and Supporting Memorandum of Law.
|
15/febrero/2024
|
2024/02/15
|
Documento
|
|
Motion Submitting Quarterly Report on Federal Funding Activities for the Second Quarter of Fiscal Year 2024
Asunto: Submission of Quarterly Report on Federal Funding Activities
|
14/febrero/2024
|
2024/02/14
|
Documento
|
|
Motion to Inform Status of Federally Funded Project
Asunto: Motion to Inform Status of Federally Funded Project
|
14/febrero/2024
|
2024/02/14
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order regarding Memorandum of Law in Support of Request for Confidentiality of Documents Submitted Under Seal with the January 14th and January 22nd Motions, […]
|
14/febrero/2024
|
2024/02/14
|
Documento
|
|
Resolution and Order
Asunto: Determination on LUMA’s January 23, 2024 Motion in Compliance with Resolution and Order of January 18, 2024 to Show Cause for Incompliance
|
12/febrero/2024
|
2024/02/12
|
Documento
|
|
Motion to Submit FEMA Approval in Compliance with Resolution and Order Dated February 1, 2024
Asunto: Motion to Submit FEMA Approval in Compliance with Resolution and Order Dated February 1, 2024
|
12/febrero/2024
|
2024/02/12
|
Documento
|
|
Memorandum of Law in Support of Request for Confidentiality of Documents Submitted Under Seal with the January 14th and January 22nd Motions
Asunto: Motion Submitting for Review and Approval the Scope of Work for the Transfer Ownership to PREPA of Temporary Generation Units
|
09/febrero/2024
|
2024/02/09
|
Documento
|
|
Motion to Inform Status of Federally Funded Projects
Asunto: Motion to Inform Status of Federally Funded Projects
|
07/febrero/2024
|
2024/02/07
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order regarding Motion for Extension of Time to Comply with January 26th Resolution, filed by the Puerto Rico Electric Power Authority.
|
07/febrero/2024
|
2024/02/07
|
Documento
|
|
Urgent Motion Submitting One Scope of Work and a Request for Confidentiality and Supporting Memorandum of Law
Asunto: Urgent Motion Submitting One Scope of Work and a Request for Confidentiality and Supporting Memorandum of Law
|
05/febrero/2024
|
2024/02/05
|
Documento
|
|
Motion for Extension of Time to Comply with January 26 Resolution
Asunto: Motion for Extension of Time to Comply with January 26 Resolution
|
02/febrero/2024
|
2024/02/02
|
Documento
|
|
Second Motion in Compliance with the January 19, 2024 Resolution and Order
Asunto: Motion submitting for review and approval the Scope of Work for the Transfer Ownership to PREPA of Temporary Generation Units
|
02/febrero/2024
|
2024/02/02
|
Documento
|
|
Informative Motion on LUMA’s Compliance with Resolution and Order dated January 19, 2024
Asunto: Informative Motion on LUMA’s Compliance with Resolution and Order dated January 19, 2024
|
02/febrero/2024
|
2024/02/02
|
Documento
|
|
Resolution and Order
Asunto: Determination on GENERA’S November 21 Motion Submitting Response in Compliance with Resolution and Order Dated November 8, 2023 and Request a Time Extension to Provide the […]
|
01/febrero/2024
|
2024/02/01
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order regarding Urgent Motion Submitting for Review and Approval of the Scope of Work for the Transfer/Ownership to PREPA of the Temporary Generation Units […]
|
26/enero/2024
|
2024/01/26
|
Documento
|
|
Informative Motion on Updated Version of the Second Report on Demobilization of FEMA Generation in Compliance with Resolution and Order Dated January 19, 2024.
Asunto: Informative Motion on Updated Version of the Second Report on Demobilization of FEMA Generation
|
26/enero/2024
|
2024/01/26
|
Documento
|
|
Motion to Inform Status of Federally Funded Projects
Asunto: Motion to Inform Status of Federally Funded Projects
|
25/enero/2024
|
2024/01/25
|
Documento
|
|
Motion to Inform Status of Federally Funded Projects
Asunto: Motion to Inform Status of Federally Funded Projects
|
25/enero/2024
|
2024/01/25
|
Documento
|
|
Motion In Compliance with Resolution and Order of January 18, 2023, to Show Case for Incompliance
Asunto: Motion In Compliance with Resolution and Order of January 18, 2023, to Show Case for Incompliance
|
23/enero/2024
|
2024/01/23
|
Documento
|
|
Motion in Compliance with the January 19th, 2024 Resolution and Order
Asunto: Motion Submitting for Review and Approval the Scope of Work for the Transfer Onwership to PREPA of Temporary Generation Units.
|
22/enero/2024
|
2024/01/22
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order regarding Urgent Motion Submitting for Review and Approval of the Scope of Work for the Transfer/Ownership to PREPA of the Temporary Generation Units, […]
|
19/enero/2024
|
2024/01/19
|
Documento
|
|
Resolution and Order and Show Cause for Incompliance
Asunto: Determination on LUMA’s December 21 and December 27, 2023, Motions for Scope of Works, and Request for Confidentiality and Supporting Memorandum of Law.
|
18/enero/2024
|
2024/01/18
|
Documento
|
|
Motion to Submit Equipment and Material Projects Information in Response to Resolution and Order Dated January 10, 2024
Asunto: Motion to Submit Equipment and Material Projects Information in Response to Resolution and Order Dated January 10, 2024
|
18/enero/2024
|
2024/01/18
|
Documento
|
|
Urgent Motion Submitting for Review and Approval the Scope of Work for the Transfer/Ownership to PREPA of the Temporary Generation Units
Asunto: Motion Submitting for Review and Approval the Scope of Work for the Transfer/Ownership to PREPA of the Temporary Generation Units
|
14/enero/2024
|
2024/01/14
|
Documento
|
|
Urgent Motion Submitting for Review and Approval the Scope of Work for the Transfer/Ownership to PREPA of the Temporary Generation Units
Asunto: Exhibit 9 – CC Ltr to COR3
|
14/enero/2024
|
2024/01/14
|
Documento
|
|
Urgent Motion Submitting for Review and Approval the Scope of Work for the Transfer/Ownership to PREPA of the Temporary Generation Units
Asunto: Exhibit 4 – COR3 Letter to FEMA- Acquisition of Temporary Generators for the Stabilization of Power Grid
|
14/enero/2024
|
2024/01/14
|
Documento
|
|
Urgent Motion Submitting for Review and Approval the Scope of Work for the Transfer/Ownership to PREPA of the Temporary Generation Units
Asunto: Exhibit 3 – COR3 Letter to FEMA Re DFA Power Stabilization
|
14/enero/2024
|
2024/01/14
|
Documento
|
|
Urgent Motion Submitting for Review and Approval the Scope of Work for the Transfer/Ownership to PREPA of the Temporary Generation Units
Asunto: Exhibit 2 – October 16, 2023 – Letter from FEMA to COR3 – DFA Power Stabilization
|
14/enero/2024
|
2024/01/14
|
Documento
|
|
Resolution and Order
Asunto: Determination on GENERA’s November 13 and November 17, 2023, Motions for a Request of Approval of Projects to Replace Critical Components and Improve Fuel Efficiency and […]
|
10/enero/2024
|
2024/01/10
|
Documento
|
|
Motion Submitting four FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting four FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
|
04/enero/2024
|
2024/01/04
|
Documento
|
|
Informative Motion on Consolidated Scopes of Work and Request for Confidentiality and Supporting Memorandum of Law
Asunto: Informative Motion on Consolidated Scopes of Work and Request for Confidentiality and Supporting Memorandum of Law
|
28/diciembre/2023
|
2023/12/28
|
Documento
|
|
Motion Submitting Three FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting Three FEMA Approvals of Projects, Request for Confidential Treatment, and Supporting Memorandum of Law
|
27/diciembre/2023
|
2023/12/27
|
Documento
|
|
Motion Submitting Amended Scope of Work and a Request for Confidentiality and Supporting Memorandum of Law
Asunto: Motion Submitting Amended Scope of Work and a Request for Confidentiality and Supporting Memorandum of Law
|
21/diciembre/2023
|
2023/12/21
|
Documento
|
|
LUMA’s Motion to Submit Information on Accelerated Storage Addition Program in compliance with Resolution and Order of November 30, 2023 and of December 11, 2023 and Request for Energy Bureau to Open a Separate Docket for The Evaluation of This Program
Asunto: LUMA’s Motion to Submit Information on Accelerated Storage Addition Program in compliance with Resolution and Order of November 30, 2023 and of December 11, 2023 and […]
|
21/diciembre/2023
|
2023/12/21
|
Documento
|
|
Motion Submitting LUMA’s December 2023 Update to PREPA-LUMA 90-Day Plan for T&D Projects
Asunto: Submittal of LUMA’s December 2023 Update to PREPA-LUMA 90-Day Plan for T&D Projects
|
14/diciembre/2023
|
2023/12/14
|
Documento
|
|
Motion Submitting One FEMA Approval of Project, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting One FEMA Approval of Project, Request for Confidential Treatment and Supporting Memorandum of Law
|
14/diciembre/2023
|
2023/12/14
|
Documento
|
|
Motion Submitting Response to November 29, 2023 Resolution and Order
Asunto: Motion Submitting Response to November 29, 2023 Resolution and Order
|
11/diciembre/2023
|
2023/12/11
|
Documento
|
|
Resolution and Order
Asunto: LUMA’s Accelerated Storage Addition Program
|
11/diciembre/2023
|
2023/12/11
|
Documento
|
|
LUMA’s Motion to Submit Information on Status of Due Diligence to Allow Genera Bess Projects to Interconnect, In Compliance with Resolution and Order of November 30, 2023
Asunto: LUMA’s Motion to Submit Information on Status of Due Diligence to Allow Genera Bess Projects to Interconnect, In Compliance with Resolution and Order of November 30, […]
|
07/diciembre/2023
|
2023/12/07
|
Documento
|
|
Motion to Submit Response to Resolution and Order Dated November 8, 2023
Asunto: Motion to Submit Response to Resolution and Order Dated November 8, 2023
|
06/diciembre/2023
|
2023/12/06
|
Documento
|
|
Request for Amendment of Notice of Appearance and Request for Notice
Asunto: Request for Amendment of Notice of Appearance and Request for Notice
|
06/diciembre/2023
|
2023/12/06
|
Documento
|
|
LUMA’s Motion Requesting Extension to Submit Information on Accelerated Storage Additions Program Requested in Resolution and Order of November 30, 2023
Asunto: LUMA’s Motion Requesting Extension to Submit Information on Accelerated Storage Additions Program Requested in Resolution and Order of November 30, 2023
|
04/diciembre/2023
|
2023/12/04
|
Documento
|
|
Motion Submitting Response in Compliance with Resolution and Order Dated November 29, 2023
Asunto: Motion Submitting Response in Compliance with Resolution and Order Dated November 29, 2023
|
04/diciembre/2023
|
2023/12/04
|
Documento
|
|
Resolution and Order
Asunto: LUMA’s Accelerated Storage Addition Program
|
30/noviembre/2023
|
2023/11/30
|
Documento
|
|
Resolution and Order
Asunto: Visits for revision of FEMA and 2020 COR3 approved projects
|
29/noviembre/2023
|
2023/11/29
|
Documento
|
|
Resolution and Order
Asunto: Determination on LUMA’s November 7, 2023, Motion Submitting One Scope of Work, and Request for Confidentiality and Supporting Memorandum of Law
|
27/noviembre/2023
|
2023/11/27
|
Documento
|
|
Motion Submitting Responses to November 8, 2023, Resolution and Order
Asunto: 20231122 ROI-LUMA-MI-2021-0002-20231108-PREB-001_Attachment 2
|
22/noviembre/2023
|
2023/11/22
|
Documento
|
|
Motion Submitting Responses to November 8, 2023, Resolution and Order
Asunto: 20231122 ROI-LUMA-MI-2021-0002-20231108-PREB-001_Attachment 1
|
22/noviembre/2023
|
2023/11/22
|
Documento
|
|
Motion Submitting Responses to November 8, 2023, Resolution and Order
Asunto: Motion Submitting Responses to November 8, 2023, Resolution and Order
|
22/noviembre/2023
|
2023/11/22
|
Documento
|
|
Motion Submitting Response in Compliance with Resolution and Order Dated November 8, 2023 and Request of Time Extension to Provide the Detailed Scope of Works Per Site
Asunto: Motion Submitting Response in Compliance with Resolution and Order Dated November 8, 2023 and Request of Time Extension to Provide the Detailed Scope of Works Per […]
|
21/noviembre/2023
|
2023/11/21
|
Documento
|
|
Motion Submitting Time Extension to Provide Scope of Works in Response to Resolution and Order Dated November 8, 2023
Asunto: Motion Submitting Time Extension to Provide Scope of Works in Response to Resolution and Order Dated November 8, 2023
|
17/noviembre/2023
|
2023/11/17
|
Documento
|
|
Motion Submitting Quarterly Report on Federal Funding Activities for the First Quarter of Fiscal Year 2024
Asunto: Submission of Quarterly Report on Federal Funding Activities
|
14/noviembre/2023
|
2023/11/14
|
Documento
|
|
Motion Submitting Response to Resolution and Order Dated November 8, 2023, Determination on Genera’s October 15, 2023, Motion for the Request for Approval of Projects to Replace Critical Components and Improve Duel Efficiency
Asunto: Motion Submitting Response to Resolution and Order Dated November 8, 2023, Determination on Genera’s October 15, 2023, Motion for the Request for Approval of Projects to […]
|
13/noviembre/2023
|
2023/11/13
|
Documento
|
|
Motion Submitting Seven FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting Seven FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
|
09/noviembre/2023
|
2023/11/09
|
Documento
|
|
Resolution and Order
Asunto: LUMA’s approved SOWs Request of Information («ROl»)
|
08/noviembre/2023
|
2023/11/08
|
Documento
|
|
Resolution and Order
Asunto: Determination on GENERA’s October 27, 2023, Amended Motion for Leave to Submit Amendment to Project and 406 BESS Initial Scope of Work
|
08/noviembre/2023
|
2023/11/08
|
Documento
|
|
Resolution and Order
Asunto: Determination on GENERA’s October 15, 2023, Motion for the Request for Approval of Projects to Replace Critical Components and Improve Fuel Efficiency
|
08/noviembre/2023
|
2023/11/08
|
Documento
|
|
Motion Submitting One Scope of Work, Request for Confidentiality and Supporting Memorandum of Law
Asunto: Motion Submitting One Scope of Work, Request for Confidentiality and Supporting Memorandum of Law
|
07/noviembre/2023
|
2023/11/07
|
Documento
|
|
Motion Submitting Three FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting Three FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
|
27/octubre/2023
|
2023/10/27
|
Documento
|
|
Amended 1 Motion for Leave to Submit Amendment to Project and 406 BESSs Initial Scope of Work
Asunto: GENERA Amended 1 – Motion for Leave to Submit Amendment to Project and 406 BESSs Initial Scope of Work
|
27/octubre/2023
|
2023/10/27
|
Documento
|
|
Notice of Appearance and Request for Notice
Asunto: Notice of Appearance and Request for Notice
|
26/octubre/2023
|
2023/10/26
|
Documento
|
|
Motion for Leva to Submit Amendment to Project and 406 BESSs Initial Scope of Work
Asunto: Motion for Leva to Submit Amendment to Project and 406 BESSs Initial Scope of Work
|
26/octubre/2023
|
2023/10/26
|
Documento
|
|
Genera PR-Request for Approval of Projects to Replace Critical Components and Improve Fuel Efficiency
Asunto: Genera PR-Request for Approval of Projects to Replace Critical Components and Improve Fuel Efficiency
|
15/octubre/2023
|
2023/10/15
|
Documento
|
|
Resolutiona and Order
Asunto: Determination on PREPA’s September 28, 2023, Motion for the Resubmission of PREPA’s Hydroelectric Fleet Application, and Request for Confidential Designation and Treatment.
|
11/octubre/2023
|
2023/10/11
|
Documento
|
|
Notice of Withdraw as Attorney of Record
Asunto: Notice of Withdraw as Attorney of Record
|
11/octubre/2023
|
2023/10/11
|
Documento
|
|
Motion to Submit PREPA’s September 2023 Update to the PREPA-LUMA 90-Day Plan
Asunto: Motion to Submit PREPA’s September 2023 Update to the PREPA-LUMA 90-Day Plan
|
28/septiembre/2023
|
2023/09/28
|
Documento
|
|
Motion to Resubmit PREPA’s Hydroelectric Fleet Application Package and Request for Confidential Designation
Asunto: Motion to Resubmit PREPA’s Hydroelectric Fleet Application Package and Request for Confidential Designation
|
28/septiembre/2023
|
2023/09/28
|
Documento
|
|
Motion Submitting LUMA’s September 2023 Update to PREPA-LUMA 90-Day Plan for T&D Projects
Asunto: Motion Submitting LUMA’s September 2023 Update to PREPA-LUMA 90-Day Plan for T&D Projects
|
14/septiembre/2023
|
2023/09/14
|
Documento
|
|
Motion Submitting LUMA’s September 2023 Update to PREPA-LUMA 90-Day Plan for T&D Project
Asunto: Submittal of LUMA’s September 2023 Update to PREPA-LUMA 90-Day Plan for T&D Projects
|
14/septiembre/2023
|
2023/09/14
|
Documento
|
|
Resolution and Order
Asunto: Determination on LUMA’s August 25, 2023, Motion
|
30/agosto/2023
|
2023/08/30
|
Documento
|
|
Motion Submitting Two FEMA Approval of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting Two FEMA Approval of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
|
28/agosto/2023
|
2023/08/28
|
Documento
|
|
Motion Submitting One Scope of Work, Request for Confidentiality, and Supporting Memorandum of Law
Asunto: Submission of One Scope of Work, Request for Confidentiality, and Supporting Memorandum of Law
|
25/agosto/2023
|
2023/08/25
|
Documento
|
|
Motion Submitting Quarterly Report on Federal Funding activities for the Fourth Quarter of Fiscal Year 2023
Asunto: Submission of Quarterly Report on Federal Funding activities
|
14/agosto/2023
|
2023/08/14
|
Documento
|
|
Motion Submitting One FEMA Approval of Project, Request for Confidential Treatment, and Supporting Memorandum of Law
Asunto: Motion Submitting One FEMA Approval of Project, Request for Confidential Treatment, and Supporting Memorandum of Law
|
08/agosto/2023
|
2023/08/08
|
Documento
|
|
Motion Submitting One FEMA Approval of Project, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting One FEMA Approval of Project, Request for Confidential Treatment and Supporting Memorandum of Law
|
04/agosto/2023
|
2023/08/04
|
Documento
|
|
Notice to Appearance and Request for Notice
Asunto: Notice to Appearance and Request for Notice
|
02/agosto/2023
|
2023/08/02
|
Documento
|
|
Resolution and Order
Asunto: Determination on LUMA’s July 17, 2023, Motion
|
01/agosto/2023
|
2023/08/01
|
Documento
|
|
Resolution and Order
Asunto: Determination on PREPA’s July 10, 2023, Motion
|
01/agosto/2023
|
2023/08/01
|
Documento
|
|
Motion in Compliance with Resolution and Order July 10, 2023
Asunto: Motion in Compliance with Resolution and Order July 10, 2023
|
17/julio/2023
|
2023/07/17
|
Documento
|
|
Motion Submitting One FEMA Approval of Project, Request for Confidential Treatment, and Supporting Memorandum of Law
Asunto: Motion Submitting One FEMA Approval of Project, Request for Confidential Treatment, and Supporting Memorandum of Law
|
14/julio/2023
|
2023/07/14
|
Documento
|
|
Motion Submitting One FEMA Approval of Project, Request for Confidential Treatment, and Supporting Memorandum of Law
Asunto: Motion Submitting One FEMA Approval of Project, Request for Confidential Treatment, and Supporting Memorandum of Law
|
11/julio/2023
|
2023/07/11
|
Documento
|
|
Motion Submitting One FEMA Approval of Project, Request for Confidential Treatment, and Supporting Memorandum of Law
Asunto: Motion Submitting One FEMA Approval of Project, Request for Confidential Treatment, and Supporting Memorandum of Law
|
11/julio/2023
|
2023/07/11
|
Documento
|
|
Motion to submit PREPA Hydroelectric Fleet Application Package and Request for Confidential Designation
Asunto: Motion to submit PREPA Hydroelectric Fleet Application Package and Request for Confidential Designation
|
10/julio/2023
|
2023/07/10
|
Documento
|
|
Resolution and Order
Asunto: Determination on LUMA’S June 28, 2023, Informative Motion.
|
10/julio/2023
|
2023/07/10
|
Documento
|
|
Resolution and Order
Asunto: Determination on PREPA’s June 22, 2023, Motion.
|
06/julio/2023
|
2023/07/06
|
Documento
|
|
Resolution and Order
Asunto: Determination on PREPA’s June 22, 2023 Motion
|
06/julio/2023
|
2023/07/06
|
Documento
|
|
Motion to Submit PREPA’s June 2023 Update to the PREPA-LUMA 90 Day Plan for Generation Projects and Request for the Energy Bureau to Accept PREPA’s 90 Day Plan for the Previous Four Quarters
Asunto: Motion to Submit PREPA’s June 2023 Update to the PREPA-LUMA 90 Day Plan for Generation Projects and Request for the Energy Bureau to Accept PREPA’s 90 […]
|
05/julio/2023
|
2023/07/05
|
Documento
|
|
Informative Motion on Proposal Under the Program 40101(C): Grid Resilience Grants of the US Department of Energy
Asunto: Informative Motion on Proposal Under the Program 40101(C): Grid Resilience Grants of the US Department of Energy
|
28/junio/2023
|
2023/06/28
|
Documento
|
|
Motion to Submit Scope of Work for IT-OT Systems Upgrades
Asunto: Motion to Submit Scope of Work for IT-OT Systems Upgrades
|
22/junio/2023
|
2023/06/22
|
Documento
|
|
Motion Submitting Four FEMA Approval of Projects, Request for Confidential Treatment, and Supporting Memorandum of Law
Asunto: Motion Submitting Four FEMA Approval of Projects, Request for Confidential Treatment, and Supporting Memorandum of Law
|
22/junio/2023
|
2023/06/22
|
Documento
|
|
Motion to Submit Scope of Work for Mayaguez Unit 3B Gas Generations Inspections and Repairs
Asunto: Motion to Submit Scope of Work for Mayaguez Unit 3B Gas Generations Inspections and Repairs
|
22/junio/2023
|
2023/06/22
|
Documento
|
|
Motion Submitting of LUMA’s June 2023 Update to PREPA-LUMA 90-Day Plan for T&D Projects
Asunto: Motion Submitting of LUMA’s June 2023 Update to PREPA-LUMA 90-Day Plan for T&D Projects
|
20/junio/2023
|
2023/06/20
|
Documento
|
|
Resolution and Order
Asunto: Determination on PREPA’s May 18, 2023 Motion
|
26/mayo/2023
|
2023/05/26
|
Documento
|
|
Motion Submitting Five FEMA Approval of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting Five FEMA Approval of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
|
24/mayo/2023
|
2023/05/24
|
Documento
|
|
Informative Motion on Contracted Costs for Federal Funded Projects
Asunto: Informative Motion on Contracted Costs for Federal Funded Projects
|
19/mayo/2023
|
2023/05/19
|
Documento
|
|
Motion Submitting LUMA’S Revised Second Quarterly Federal Funding Report for the Fiscal Year 2023
Asunto: Motion Submitting LUMA’S Revised Second Quarterly Federal Funding Report for the Fiscal Year 2023
|
18/mayo/2023
|
2023/05/18
|
Documento
|
|
Motion to Submit Scope of Work for Guayabal Dam Seismic Retrofit and Hurricane Maria Repairs
Asunto: Motion to Submit Scope of Work for Guayabal Dam Seismic Retrofit and Hurricane Maria Repairs
|
18/mayo/2023
|
2023/05/18
|
Documento
|
|
Motion Submission of Quarterly Report on Federal Funding Activities for the Third Quarter of Fiscal Year 2023
Asunto: Submission of Quarterly Report on Federal Funding Activities
|
15/mayo/2023
|
2023/05/15
|
Documento
|
|
Resolution and Order
Asunto: Determination on LUMA’s April 24, 2023, Motion
|
15/mayo/2023
|
2023/05/15
|
Documento
|
|
Motion to Inform Status of Federally Funded Project
Asunto: Motion to Inform Status of Federally Funded Project
|
12/mayo/2023
|
2023/05/12
|
Documento
|
|
Motion Submitting Two FEMA Approvals of Projects, Request for Confidential Treatment, and Supporting Memorandum of Law
Asunto: Motion Submitting Two FEMA Approvals of Projects, Request for Confidential Treatment, and Supporting Memorandum of Law
|
09/mayo/2023
|
2023/05/09
|
Documento
|
|
Resolution and Order
Asunto: Determination on LUMA’s April 24, 2023, Motion for the Submission of Scope of Work and Request for Confidentiality and Supporting Memorandum of Law
|
05/mayo/2023
|
2023/05/05
|
Documento
|
|
Resolution and Order
Asunto: Determination on LUMA’s April 27, 2023, Motion
|
05/mayo/2023
|
2023/05/05
|
Documento
|
|
Motion Submitting Three Scopes of Work and Updated List of Projects and Request for Confidentiality and Supporting Memorandum of Law
Asunto: Exhibit 2 – List of Updated Projects_ – NEPR-MI-2021-0002
|
27/abril/2023
|
2023/04/27
|
Documento
|
|
Motion Submitting Three Scopes of Work and Updated List of Projects and Request for Confidentiality and Supporting Memorandum of Law
Asunto: Motion Submitting Three Scopes of Work and Updated List of Projects and Request for Confidentiality and Supporting Memorandum of Law
|
27/abril/2023
|
2023/04/27
|
Documento
|
|
Informative Motion on Two Proposals Under the Smart Grid Investment Matching Grant Program of the U.S. Department of Energy
Asunto: Informative Motion on Two Proposals Under the Smart Grid Investment Matching Grant Program of the U.S. Department of Energy
|
24/abril/2023
|
2023/04/24
|
Documento
|
|
Motion Submitting Scope of Work and Request for Confidentiality and Supporting Memorandum of Law
Asunto: Motion Submitting Scope of Work and Request for Confidentiality and Supporting Memorandum of Law
|
24/abril/2023
|
2023/04/24
|
Documento
|
|
Motion to Substitute Exhibit Submitted to the Energy Bureau on March 29, 2023
Asunto: 20230418 Exhibit2_2023-03-29_Project Listing_CORRECTIONS
|
18/abril/2023
|
2023/04/18
|
Documento
|
|
Motion to Substitute Exhibit Submitted to the Energy Bureau on March 29, 2023
Asunto: Motion to Substitute Exhibit Submitted to the Energy Bureau on March 29, 2023
|
18/abril/2023
|
2023/04/18
|
Documento
|
|
Motion Submitting Three FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting Three FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
|
11/abril/2023
|
2023/04/11
|
Documento
|
|
Resolution and Order
Asunto: Determination on LUMA’s March 29, 2023, Motion for the Submission of Two Scope of Works, List of Updated Projects, and Request for Confidential Designation and Treatment.
|
05/abril/2023
|
2023/04/05
|
Documento
|
|
Motion Submitting Two Scopes of Work and Update List of Projects and Request for Confidentiality and Supporting Memorandum of Law
Asunto: Exhibit2_2023-03-29_Project Listing
|
29/marzo/2023
|
2023/03/29
|
Documento
|
|
Motion Submitting Two Scopes of Work and Updated List of Projects and Request for Confidentiality and Supporting Memorandum of Law
Asunto: Submission of Two Scopes of Work and List of Updated Projects and Request for Confidentiality and Supporting Memorandum of Law
|
29/marzo/2023
|
2023/03/29
|
Documento
|
|
Motion Submitting Two FEMA approval of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting Two FEMA approval of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
|
28/marzo/2023
|
2023/03/28
|
Documento
|
|
Motion Submitting LUMA’s March 2023 Update to PREPA-LUMA 90 Day Plan for T&D Projects
Asunto: Motion Submitting LUMA’s March 2023 Update to PREPA-LUMA 90 Day Plan for T&D Projects
|
23/marzo/2023
|
2023/03/23
|
Documento
|
|
Resolution and Order
Asunto: February 9, 2023, LUMA’s Motion Submitting Nine FEMA Approvals of Projects, Request for Confidential Designation and Treatment and Supporting Memorandum of Law
|
20/marzo/2023
|
2023/03/20
|
Documento
|
|
Resolution and Order
Asunto: Determination on PREPA’s March 10 Motion and Request for Confidential Designation and Treatment of the Scope of Work for San Juan Central Unit 6 Generation Project
|
20/marzo/2023
|
2023/03/20
|
Documento
|
|
Motion Submitting Seven FEMA Approvals of Projects, Request for Confidential Treatment, and Supporting Memorandum of Law
Asunto: Motion Submitting Seven FEMA Approvals of Projects, Request for Confidential Treatment, and Supporting Memorandum of Law
|
15/marzo/2023
|
2023/03/15
|
Documento
|
|
Urgent Motion to Submit Scope of Work for San Juan Central Unit 6 Generation Project
Asunto: Urgent Motion to Submit Scope of Work for San Juan Central Unit 6 Generation Project
|
10/marzo/2023
|
2023/03/10
|
Documento
|
|
Motion to Inform Status of Federally Funded Project
Asunto: Motion to Inform Status of Federally Funded Project
|
23/febrero/2023
|
2023/02/23
|
Documento
|
|
Motion Submitting Three FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting Three FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
|
23/febrero/2023
|
2023/02/23
|
Documento
|
|
Resolution and Order
Asunto: Determination on LUMA’s January 30, 2023, Motion and Request for Confidential Designation and Treatment of the Initial Scope of Work («SOW») for T & D Project.
|
22/febrero/2023
|
2023/02/22
|
Documento
|
|
Motion Submitting LUMA’s Second Quarter Federal Funding Report for Fiscal Year 2023
Asunto: Submission of Second Quarter Federal Funding Report for Fiscal Year 2023
|
14/febrero/2023
|
2023/02/14
|
Documento
|
|
Motion Submitting Nine FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting Nine FEMA Approvals of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
|
09/febrero/2023
|
2023/02/09
|
Documento
|
|
Motion Submitting Seven FEMA Approval of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: LUMA- Motion Submitting Seven FEMA Approval of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
|
01/febrero/2023
|
2023/02/01
|
Documento
|
|
Motion Submitting Initial Scope of Work and Request for Confidentiality and Supporting Memorandum of Law
Asunto: 20230130 Redacted Exhibit 1 to Motion -90016-EN-SOW-0001-Renewable Network Upgrades-Final
|
30/enero/2023
|
2023/01/30
|
Documento
|
|
Motion Submitting Initial Scope of Work and Request for Confidentiality and Supporting Memorandum of Law
Asunto: Submission of Initial Scope of Work and Request for Confidentiality and Supporting Memorandum of Law
|
30/enero/2023
|
2023/01/30
|
Documento
|
|
Motion to Substitute Exhibit Submitted to the Energy Bureau on May 20, 2022, Request Confidentiality of Portions of Such Exhibit, and to Submit Supporting Memorandum of Law
Asunto: Exhibit 1 Test and Technology Laboratory iSOW_Redacted_Redacted – NEPR-MI-2021-0002
|
19/enero/2023
|
2023/01/19
|
Documento
|
|
Motion to Substitute Exhibit Submitted to the Energy Bureau on May 20, 2022, Request Confidentiality of Portions of Such Exhibit, and to Submit Supporting Memorandum of Law
Asunto: Motion to Substitute Exhibit Submitted to the Energy Bureau on May 20, 2022, Request Confidentiality of Portions of Such Exhibit, and to Submit Supporting Memorandum of […]
|
19/enero/2023
|
2023/01/19
|
Documento
|
|
Motion Submitting Ten FEMA Approvals of Projects, Request for Confidential Treatment, and Supporting Memorandum of Law
Asunto: Motion Submitting Ten FEMA Approvals of Projects, Request for Confidential Treatment, and Supporting Memorandum of Law
|
17/enero/2023
|
2023/01/17
|
Documento
|
|
Motion Submitting Twenty FEMA Approval of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting Twenty FEMA Approval of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
|
03/enero/2023
|
2023/01/03
|
Documento
|
|
Motion Submitting Three FEMA Approval of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting Three FEMA Approval of Projects, Request for Confidential Treatment and Supporting Memorandum of Law
|
29/diciembre/2022
|
2022/12/29
|
Documento
|
|
Motion Submitting «Load Forecasting Data Needs» Report
Asunto: Submission of «Load Forecasting Data Needs» Report
|
21/diciembre/2022
|
2022/12/21
|
Documento
|
|
Motion Submitting LUMA’s December 2022 Update to PREPA-LUMA 90-Day Plan for T&D Projects
Asunto: Submittal of LUMA’s December 2022 Update to PREPA-LUMA 90-Day Plan for T&D Projects
|
21/diciembre/2022
|
2022/12/21
|
Documento
|
|
Resolution and Order
Asunto: Determination on LUMA’s November 11 and November 16, 2022 Motions and Request for Confidential Designation and Treatment of sixty-one (61) Statement of Works («SOWs»)
|
10/diciembre/2022
|
2022/12/10
|
Documento
|
|
Motion to Substitute Exhibit Submitted to the Energy Bureau on May 9, 2022, Request Confidentiality of Portions of Such Exhibit and Submit Supporting Memorandum of Law
Asunto: Motion to Substitute Exhibit Submitted to the Energy Bureau on May 9, 2022, Request Confidentiality of Portions of Such Exhibit and Submit Supporting Memorandum of Law
|
23/noviembre/2022
|
2022/11/23
|
Documento
|
|
Informative Motion On Contracted Costs for Federally Funded Projects
Asunto: Informative Motion On Contracted Costs for Federally Funded Projects
|
23/noviembre/2022
|
2022/11/23
|
Documento
|
|
Motion to Substitute Exhibit Submitted to the Energy Bureau on May 24, 2022, Request Confidentiality of Portions of Such Exhibit, and Submit Supporting Memorandum of Law
Asunto: Motion to Substitute Exhibit Submitted to the Energy Bureau on May 24, 2022, Request Confidentiality of Portions of Such Exhibit, and Submit Supporting Memorandum of Law
|
18/noviembre/2022
|
2022/11/18
|
Documento
|
|
Motion Submitting Scope of Work and Update List of Projects and Request for Confidentiality and Supporting Memorandum of Law
Asunto: Exhibit 2_2022-11-16_Project Listing – Motion Submitting Scope of Work
|
16/noviembre/2022
|
2022/11/16
|
Documento
|
|
Motion Submitting Scope of Work and Update List of Projects and Request for Confidentiality and Supporting Memorandum of Law
Asunto: Motion Submitting Scope of Work and Update List of Projects and Request for Confidentiality and Supporting Memorandum of Law
|
16/noviembre/2022
|
2022/11/16
|
Documento
|
|
Submission of First Quarter Federal Funding Report for Fiscal Year 2023
Asunto: Motion Submitting Luma’s First Quarter Federal Funding Report for Fiscal Year 2023
|
14/noviembre/2022
|
2022/11/14
|
Documento
|
|
Motion Submitting Sixty Scopes of Work and Updated List of Projects and Request for Confidentiality and Supporting Memorandum of Law
Asunto: Exhibit 2_2022-11-08_Project Listing (1)
|
11/noviembre/2022
|
2022/11/11
|
Documento
|
|
Motion Submitting Sixty Scopes of Work and Updated List of Projects and Request for Confidentiality and Supporting Memorandum of Law
Asunto: Submission of Sixty Scopes of Work and List of Update Projects and Request for Confidentiality and Supporting Memorandum of Law
|
11/noviembre/2022
|
2022/11/11
|
Documento
|
|
Motion to Inform Status of Federally Funded Projects
Asunto: Motion to Inform Status of Federally Funded Projects
|
11/noviembre/2022
|
2022/11/11
|
Documento
|
|
Second Motion to Inform in Compliance with the Order Entered on September 15, 2022 20221110
Asunto: Second Motion to Inform in Compliance with the Order Entered on September 15, 2022
|
10/noviembre/2022
|
2022/11/10
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order on PREPA’s October 26 Motion and October 27 Motion.
|
04/noviembre/2022
|
2022/11/04
|
Documento
|
|
Motion Submitting Hazard Mitigation Grant Program Projects and Request for Confidentiality and Supporting Memorandum of Law
Asunto: Motion Submitting Hazard Mitigation Grant Program Projects and Request for Confidentiality and Supporting Memorandum of Law
|
01/noviembre/2022
|
2022/11/01
|
Documento
|
|
Motion Submitting FEMA Approval of Project, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting FEMA Approval of Project, Request for Confidential Treatment and Supporting Memorandum of Law
|
31/octubre/2022
|
2022/10/31
|
Documento
|
|
Motion to Clarify Regarding Amendment to 404 HMGP Application Package
Asunto: Motion to Clarify Regarding Amendment to 404 HMGP Application Package
|
28/octubre/2022
|
2022/10/28
|
Documento
|
|
Motion to Submit 404 HMGP Application Package and Request for Leave to Present to COR3 and FEMA
Asunto: Motion to Submit 404 HMGP Application Package and Request for Leave to Present to COR3 and FEMA
|
26/octubre/2022
|
2022/10/26
|
Documento
|
|
Motion to Substitute Exhibit Submitted on May 27, 2022, Request Confidentiality of Portions of Such Exhibit, and Submit Supporting Memorandum of Law
Asunto: Motion to Substitute Exhibit Submitted on May 27, 2022, Request Confidentiality of Portions of Such Exhibit, and Submit Supporting Memorandum of Law
|
24/octubre/2022
|
2022/10/24
|
Documento
|
|
Motion Submitting Five FEMA Approvals of Project, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting Five FEMA Approvals of Project, Request for Confidential Treatment and Supporting Memorandum of Law
|
24/octubre/2022
|
2022/10/24
|
Documento
|
|
Request for Order Regarding Repairs, Request for Reconsideration, and to Inform Regarding Storage Systems
Asunto: Request for Order Regarding Repairs, Request for Reconsideration, and to Inform Regarding Batteries
|
22/octubre/2022
|
2022/10/22
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order on PREPA’s June 24 Motion.
|
21/octubre/2022
|
2022/10/21
|
Documento
|
|
Notice of Appearance and Request for Notice
Asunto: Notice of Appearance and Request for Notice
|
18/octubre/2022
|
2022/10/18
|
Documento
|
|
Motion to Inform Regarding the Order Entered on September 15, 2022
Asunto: Motion to Inform Regarding the Order Entered on September 15, 2022
|
17/octubre/2022
|
2022/10/17
|
Documento
|
|
Motion to Substitute Exhibit Submitted to the Energy Bureau on June 1, 2022, Request Confidentiality of Portions of Such Exhibit, and Submit Supporting Memorandum of Law
Asunto: Motion to Substitute Exhibit Submitted to the Energy Bureau on June 1, 2022, Request Confidentiality of Portions of Such Exhibit, and Submit Supporting Memorandum of Law
|
14/octubre/2022
|
2022/10/14
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order on Request to Amend PREPA’s Integrated Resource Plan
|
12/octubre/2022
|
2022/10/12
|
Documento
|
|
Supplement to Request to Amend PREPA’S Integrated Resource Plan
Asunto: Supplement to Request to Amend PREPA’S Integrated Resource Plan – NEPR-MI-2021-0002
|
12/octubre/2022
|
2022/10/12
|
Documento
|
|
Request to Amend PREPA’S Integrated Resource Plan
Asunto: Request to Amend PREPA’S Integrated Resource Plan
|
11/octubre/2022
|
2022/10/11
|
Documento
|
|
Motion to Inform Approval of Palo Seco, San Juan, Costa Sur and Aguirre Power Plant Permanent Repairs and Request for Confidential Treatment
Asunto: Motion to Inform Approval of Palo Seco, San Juan, Costa Sur and Aguirre Power Plant Permanent Repairs and Request for Confidential Treatment
|
05/octubre/2022
|
2022/10/05
|
Documento
|
|
Motion Submitting Three FEMA Approvals of Project, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Exhibit 1 – FEMA Approvals 9-15-22
|
22/septiembre/2022
|
2022/09/22
|
Documento
|
|
Motion Submitting Three FEMA Approvals of Project, Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting Three FEMA Approvals of Project, Request for Confidential Treatment and Supporting Memorandum of Law
|
22/septiembre/2022
|
2022/09/22
|
Documento
|
|
Motion Submitting LUMA’s September 2022 Update to PREPA-LUMA 90-Day Plan for T&D Projects
Asunto: Motion Submitting LUMA’s September 2022 Update to PREPA-LUMA 90-Day Plan for T&D Projects
|
16/septiembre/2022
|
2022/09/16
|
Documento
|
|
Resolution
Asunto: Resolution on PREPA’s September 3 and 7, 2022 Motions
|
15/septiembre/2022
|
2022/09/15
|
Documento
|
|
Motion to Submit Responses to Requests for Information Ordered in the August 18 Order
Asunto: Motion to Submit Responses to Requests for Information Ordered in the August 18 Order
|
07/septiembre/2022
|
2022/09/07
|
Documento
|
|
Motion Submitting LUMA’s Fourth Quarter Federal Funding Report for Fiscal Year 2022
Asunto: Motion Submitting LUMA’s Fourth Quarter Federal Funding Report for Fiscal Year 2022
|
07/septiembre/2022
|
2022/09/07
|
Documento
|
|
Partial Request for Reconsideration of the August 3 and 18 Orders
Asunto: Partial Request for Reconsideration of the August 3 and 18 Orders
|
03/septiembre/2022
|
2022/09/03
|
Documento
|
|
Motion Submitting Two FEMA Approvals of Project Request for Confidential Treatment and Supporting Memorandum of Law
Asunto: Motion Submitting Two FEMA Approvals of Project Request for Confidential Treatment and Supporting Memorandum of Law
|
02/septiembre/2022
|
2022/09/02
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order regarding Request to Align the Filing of the Quarterly Report for the Fourth Quarter of Each Fiscal Year (“Q4 Report”) with Year-End Reporting […]
|
31/agosto/2022
|
2022/08/31
|
Documento
|
|
Resolution and Order
Asunto: July 29 and August 10, 2022, LUMA’s Motions and Request for Confidential Designation and Treatment of Six Projects Statement of Work (“SOWS”).
|
25/agosto/2022
|
2022/08/25
|
Documento
|
|
Resolución y Orden
Asunto: Resolution and Order regarding Motion to Inform Reallocation of FEMA 404 HMGP Funds and Request for Approval of Generation Projects, filed by the Puerto Rico Electric […]
|
18/agosto/2022
|
2022/08/18
|
Documento
|
|
Request to Align the Filing of Quarterly Report for Fourth Quarter of Each Fiscal Year («Q4 Report») with Year-End Reporting Under the T&D OMA and to File Q4 Report on October 28, 2022
Asunto: Request to Align the Filing of Quarterly Report for Fourth Quarter of Each Fiscal Year («Q4 Report») with Year-End Reporting Under the T&D OMA and to […]
|
15/agosto/2022
|
2022/08/15
|
Documento
|
|
Motion Submitting Two Scopes of Work and Updated List of Projects and Request for Confidentiality and Supporting Memorandum of Law
Asunto: Exhibit2_2022-08-10_Project Listing
|
10/agosto/2022
|
2022/08/10
|
Documento
|
|
Motion Submitting Two Scopes of Work and Updated List of Projects and Request for Confidentiality and Supporting Memorandum of Law
Asunto: Submission of Two Scopes of Work and List of Projects and Request for Confidentiality and Supporting Memorandum of Law
|
10/agosto/2022
|
2022/08/10
|
Documento
|
|
Resolution
Asunto: Resolution on the Petition for Leave to Conduct Works in PREPA’s Steam Units to Achieve Environmental Regulatory Compliance
|
03/agosto/2022
|
2022/08/03
|
Documento
|
|
Motion to Inform Reallocation of FEMA 404 HMPG Funds and Request for Approval of Generation Projects
Asunto: Motion to Inform Reallocation of FEMA 404 HMPG Funds and Request for Approval of Generation Projects
|
02/agosto/2022
|
2022/08/02
|
Documento
|
|
Motion Submitting Four Scopes of Work and Updated List of Projects and Request for Confidentiality and Supporting Memorandum of Law
Asunto: Submission of Four Scopes of Work and List of Updated Projects and Request for Confidentiality and Supporting Memorandum of Law
|
29/julio/2022
|
2022/07/29
|
Documento
|
|
Motion Submitting Four Scopes of Work and Updated List of Projects and request for Confidentiality and Supporting Memorandum of Law and Confidential Exhibit 1
Asunto: Submission of Four Scopes of Work and Updated List of Projects and request for Confidentiality and Supporting Memorandum of Law
|
29/julio/2022
|
2022/07/29
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order on PREPA’s June 24 Motion.
|
21/julio/2022
|
2022/07/21
|
Documento
|
|
Motion Submitting FEMA Approval of Four Projects, Request for Confidential Treatment and Memorandum of Law in Support of this Request
Asunto: Motion Submitting FEMA Approval of Four Projects, Request for Confidential Treatment and Memorandum of Law in Support of this Request
|
19/julio/2022
|
2022/07/19
|
Documento
|
|
Resolution and Order
Asunto: Evaluation of PREPA’s June 14, 2022, Request for approval for SOW 8095 and Request for Confidential Designation and Treatment
|
11/julio/2022
|
2022/07/11
|
Documento
|
|
Resolution and Order
Asunto: Evaluation of LUMA’s May 20, 2022, Request for approval for SOW-Test and Technology Laboratory
|
11/julio/2022
|
2022/07/11
|
Documento
|
|
Motion to Inform Approval of Costa Sur, Palo Seco and San Juan Power Permanent Repairs
Asunto: Motion to Inform Approval of Costa Sur, Palo Seco and San Juan Power Permanent Repairs
|
08/julio/2022
|
2022/07/08
|
Documento
|
|
Motion Reiterating Request in «Motion Submitting Scope of Work and Updated List of Projects» Submitted on May 20, 2022
Asunto: Reiteration of Request in «Motion Submitting Scope of Work and Updated List of Projects» Submitted on May 20, 2022
|
06/julio/2022
|
2022/07/06
|
Documento
|
|
Memorandum of Law in Support of Confidential Treatment of FEMA Approvals Submitted by LUMA on It’s June 18, 2022 Motion
Asunto: Memorandum of Law in Support of Confidential Treatment of FEMA Approvals Submitted by LUMA on It’s June 18, 2022 Motion
|
28/junio/2022
|
2022/06/28
|
Documento
|
|
Urgent Motion for Reconsideration of the June 4 Order
Asunto: Urgent Motion for Reconsideration of the June 4 Order
|
24/junio/2022
|
2022/06/24
|
Documento
|
|
Second Motion to Reiterate Petition for Leave to Conduct Work to Achieve Environmental Regulatory Compliance and Request for Technical Conference
Asunto: Second Motion to Reiterate Petition for Leave to Conduct Work to Achieve Environmental Regulatory Compliance and Request for Technical Conference
|
24/junio/2022
|
2022/06/24
|
Documento
|
|
Memorandum of Law in Support of Confidential Treatment of FEME Approval of the FAAST (Distribution Feeders – Arecibo Short Term Group 2) (Distribution ) T&D Project
Asunto: Memorandum of Law in Support of Request for Confidential Treatment
|
21/junio/2022
|
2022/06/21
|
Documento
|
|
Motion Submitting Four FEMA Approvals of Project and Request for Confidential Treatment
Asunto: Motion Submitting Four FEMA Approvals of Project and Request for Confidential Treatment
|
18/junio/2022
|
2022/06/18
|
Documento
|
|
Motion Submitting June 2022 Update to PREPA-LUMA 90 Day Plan for T&D Projects
Asunto: Submittal of June 2022 Update to PREPA-LUMA 90 Day Plan for T&D Projects
|
17/junio/2022
|
2022/06/17
|
Documento
|
|
Motion to Submit SOW 8095 in Compliance with the June 4 Order
Asunto: Motion to Submit SOW 8095 in Compliance with the June 4 Order
|
14/junio/2022
|
2022/06/14
|
Documento
|
|
Motion Submitting FEMA Approval of Project and Request for Confidential Treatment
Asunto: Motion Submitting FEMA Approval of Project and Request for Confidential Treatment
|
09/junio/2022
|
2022/06/09
|
Documento
|
|
Supplemental Motion to Submit Contracts of Aguirre Power Plant Infrastructure Repairs and Cambalache Power Plant Permanent Repairs
Asunto: Supplemental Motion to Submit Contracts of Aguirre Power Plant Infrastructure Repairs and Cambalache Power Plant Permanent Repairs
|
08/junio/2022
|
2022/06/08
|
Documento
|
|
Motion to Inform Approval of Aguirre Power Plant Infrastructure Repairs and Cambalache Power Plant Permanent Repairs
Asunto: Motion to Inform Approval of Aguirre Power Plant Infrastructure Repairs and Cambalache Power Plant Permanent Repairs
|
05/junio/2022
|
2022/06/05
|
Documento
|
|
Resolution and Order
Asunto: Evaluation of PREPA’s Deferred Generation Projects
|
04/junio/2022
|
2022/06/04
|
Documento
|
|
Motion Submitting FEMA Approval of Four Projects
Asunto: Motion Submitting FEMA Approval of Four Projects
|
01/junio/2022
|
2022/06/01
|
Documento
|
|
Motion Submitting FEMA Approval of Three Projects
Asunto: Motion Submitting FEMA Approval of Three Projects
|
27/mayo/2022
|
2022/05/27
|
Documento
|
|
Motion Inform Approval of Mayaguez Project
Asunto: Motion to Inform Approval of Mayaguez Hydro-Gas Power Plant Permanent Repairs
|
27/mayo/2022
|
2022/05/27
|
Documento
|
|
Motion Submitting FEMA Approval of Project
Asunto: Motion Submitting FEMA Approval of Project
|
24/mayo/2022
|
2022/05/24
|
Documento
|
|
Motion to Inform Approval of Costa Sur Powe Plant Repairs Projects
Asunto: Motion to Inform Approval of Costa Sur Powe Plant Repairs Projects
|
20/mayo/2022
|
2022/05/20
|
Documento
|
|
Motion Submitting Scope of Work and Updated List of Projects
Asunto: Exhibit2_2022-05-20_Project Listing
|
20/mayo/2022
|
2022/05/20
|
Documento
|
|
Motion Submitting Scope of Work and Updated List of Projects
Asunto: Motion Submitting Scope of Work and Updated List of Projects
|
20/mayo/2022
|
2022/05/20
|
Documento
|
|
Motion Submitting Quarterly Report on Federal Funding Activities
Asunto: Copy of Exhibit 2_LUMA Q322 Schedules – NEPR-MI-2021-0002
|
16/mayo/2022
|
2022/05/16
|
Documento
|
|
Motion Submitting Quarterly Report on Federal Funding Activities
Asunto: Submission of Quarterly Report on Federal Funding Activities
|
16/mayo/2022
|
2022/05/16
|
Documento
|
|
Motion Submitting FEMA Approval of Project and Requesting Subject Matter of this Proceeding be Expanded
Asunto: Motion Submitting FEMA Approval of Project and Requesting Subject Matter of this Proceeding be Expanded
|
09/mayo/2022
|
2022/05/09
|
Documento
|
|
Resolution and Order
Asunto: Evaluation of PREPA’s February 8, 2022, Request for approval of ten (10) SOWs; Evaluation of PREPA’s February 14. 2022, Request for approval of twenty-three (23) SOWs; […]
|
13/abril/2022
|
2022/04/13
|
Documento
|
|
Joint Motion Submitting March 2022 PREPA-LUMA 90-Day Plan
Asunto: Joint Motion Submitting March 2022 PREPA-LUMA 90-Day Plan
|
18/marzo/2022
|
2022/03/18
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order for the Motion to Submit Update List of Projects and LUMA January 24 Three Scopes of Work
|
15/marzo/2022
|
2022/03/15
|
Documento
|
|
Response to PREPA’s Petition for Leave to Conduct Works in PREPA’s Steam Units to Achieve Environmental Regulatory Compliance
Asunto: Opposition to PREPA’s Proposal to Convert San Juan Units 7-10 to Burn Gas
|
09/marzo/2022
|
2022/03/09
|
Documento
|
|
Resolution and Order
Asunto: Evaluation of PREPA’s January 28, 2022, Request for approval of twenty (20) SOWs and Request For Confidential Designation and Treatment
|
09/marzo/2022
|
2022/03/09
|
Documento
|
|
Resolution and Order
Asunto: Evaluation of PREPA’s February 2, 2022, Request for approval of fourteen (14) SOWs and Request for Confidential Designation and Treatment
|
28/febrero/2022
|
2022/02/28
|
Documento
|
|
Motion to Complete Response to RFI
Asunto: Motion to Complete Response to RFI
|
23/febrero/2022
|
2022/02/23
|
Documento
|
|
Resolution and Order
Asunto: Evaluation of PREPA’s January 25, 2022 Request for approval of ten (10) SOWs and Request for Confidential Designation and Treatment
|
18/febrero/2022
|
2022/02/18
|
Documento
|
|
Notice of Appearance and Request for Notice
Asunto: Notice of Appearance and Request for Notice
|
17/febrero/2022
|
2022/02/17
|
Documento
|
|
Motion Seeking an Order Ending the Preliminary Studies for New Combined Cycle Power Plant in Palo Seco
Asunto: Preliminary Studies for New Combined Cycle Power Plant in Palo Seco
|
17/febrero/2022
|
2022/02/17
|
Documento
|
|
Motion Submitting Quarterly Report on Federal Funding Activities
Asunto: Exhibit 2- MI-2021-0002
|
15/febrero/2022
|
2022/02/15
|
Documento
|
|
Motion Submitting Quarterly Report on Federal Funding Activities
Asunto: Motion Submitting Quarterly Report on Federal Funding Activities
|
15/febrero/2022
|
2022/02/15
|
Documento
|
|
Motion to Complete Generation Projects SOWs Submittal and Partial Responses to RFI and Request for Extension of Time to Submit Additional Responses to RFI
Asunto: Attachment C
|
14/febrero/2022
|
2022/02/14
|
Documento
|
|
Motion to Complete Generation Projects SOWs Submittal and Partial Responses to RFI and Request for Extension of Time to Submit Additional Responses to RFI
Asunto: Motion to Complete Generation Projects SOWs Submittal and Partial Responses to RFI and Request for Extension of Time to Submit Additional Responses to RFI
|
14/febrero/2022
|
2022/02/14
|
Documento
|
|
Petition for Leave to Conduct Works in PREPA’s Steam Units to Achieve Environmental Regulation Compliance
Asunto: Petition for Leave to Conduct Works in PREPA’s Steam Units to Achieve Environmental Regulation Compliance
|
11/febrero/2022
|
2022/02/11
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order for the Motion to Request Approval for the Partial Compliance with the January 4 Order
|
10/febrero/2022
|
2022/02/10
|
Documento
|
|
Fourth Motion to Submit Additional Generation Projects SOWs
Asunto: Fourth Motion to Submit Additional Generation Projects SOWs
|
08/febrero/2022
|
2022/02/08
|
Documento
|
|
Third Motion to Submit Additional Generation Project SOWs
Asunto: Third Motion to Submit Additional Generation Project SOWs
|
02/febrero/2022
|
2022/02/02
|
Documento
|
|
Motion to Substitute Exhibit 2 Submitted to the Energy Bureau on January 24, 2022, Request Confidentiality of Portions of Such Exhibit 2, and Submit Supporting Memorandum of Law
Asunto: EXHIBIT 2 2022-02-02_Updated Jan 24 Exhibit2_3-SOWs-Combined REDACTED – NEPR-MI-2021-0002
|
02/febrero/2022
|
2022/02/02
|
Documento
|
|
Motion to Substitute Exhibit 2 Submitted to the Energy Bureau on January 24, 2022, Request Confidentiality of Portions of Such Exhibit 2, and Submit Supporting Memorandum of Law
Asunto: Motion to Substitute Exhibit 2 Submitted to the Energy Bureau on January 24, 2022, Request Confidentiality of Portions of Such Exhibit 2, and Submit Supporting Memorandum […]
|
02/febrero/2022
|
2022/02/02
|
Documento
|
|
Second Motion to Submit Additional Generation Project SOWs
Asunto: Second Motion to Submit Additional Generation Project SOWs
|
28/enero/2022
|
2022/01/28
|
Documento
|
|
Motion to Submit Additional Generation Projects SOWs
Asunto: Motion to Submit Additional Generation Projects SOWs
|
25/enero/2022
|
2022/01/25
|
Documento
|
|
Motion Submitting Updates List of Transmission and Distribution Projects and Three Scopes of Work
Asunto: 2022-01-24_Exhibit1_UpdatedProjectList
|
24/enero/2022
|
2022/01/24
|
Documento
|
|
Motion Submitting Updates List of Transmission and Distribution Projects and Three Scopes of Work
Asunto: Motion Submitting Updates List of Transmission and Distribution Projects and Three Scopes of Work
|
24/enero/2022
|
2022/01/24
|
Documento
|
|
Resolution and Order
Asunto: Partial Compliance with the January 4 Order and PREPA Request for Extension of Time. Request for Confidential Designation and Treatment
|
21/enero/2022
|
2022/01/21
|
Documento
|
|
Request for Extension of Time to Submit Responses to RFI Included in the January 4 Order
Asunto: Request for Extension of Time to Submit Responses to RFI Included in the January 4 Order
|
18/enero/2022
|
2022/01/18
|
Documento
|
|
Partial Compliance with the January 4 Order and Request for Extension of Time
Asunto: Partial Compliance with the January 4 Order and Request for Extension of Time
|
13/enero/2022
|
2022/01/13
|
Documento
|
|
Motion to Reiterate Request for Approval of Generation Projects and/or Technical Conference
Asunto: Motion to Reiterate Request for Approval of Generation Projects and/or Technical Conference
|
04/enero/2022
|
2022/01/04
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order on Motion to Submit Fourth Group of Generation Projects.
|
04/enero/2022
|
2022/01/04
|
Documento
|
|
Joint Motion Submitting December 2021 PREPA-LUMA 90 Day Plan
Asunto: Joint Motion Submitting December 2021 PREPA-LUMA 90 Day Plan
|
21/diciembre/2021
|
2021/12/21
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order for PREPA’s Fifth Group of Generation Projects Scope of Work
|
20/diciembre/2021
|
2021/12/20
|
Documento
|
|
Resolution and Order
Asunto: Resolution and Order to Motion to Submit Third Group of Generation Projects Initial SOW’s and request of confidential designation
|
01/diciembre/2021
|
2021/12/01
|
Documento
|
|
Motion to Submit Fifth Group of Generation Project Scope of Work
Asunto: Motion to Submit Fifth Group of Generation Projects Scope of Work
|
01/diciembre/2021
|
2021/12/01
|
Documento
|
|
Motion to Clarify and Request for Technical Conference
Asunto: Motion to Clarify and Request for Technical Conference
|
29/noviembre/2021
|
2021/11/29
|
Documento
|
|
Resolution and Order Nunc Pro Tunc
Asunto: Motion to Submit Fourth Group of Generation Projects
|
22/noviembre/2021
|
2021/11/22
|
Documento
|
|
Resolution and Order
Asunto: Motion to Submit Fourth Group of Generation Projects
|
18/noviembre/2021
|
2021/11/18
|
Documento
|
|
Motion Submitting Quarterly Report on Federal Funding Activities
Asunto: Exhibit 2 – LUMA Q122 Schedules
|
15/noviembre/2021
|
2021/11/15
|
Documento
|
|
Motion Submitting Quarterly Report on Federal Funding Activities
Asunto: Submission of Quarterly Report on Federal Funding Activities
|
15/noviembre/2021
|
2021/11/15
|
Documento
|
|
Motion Submitting Quarterly Report on Federal Funding Activities
Asunto: Exhibit 2 – LUMA Q122 Schedules
|
15/noviembre/2021
|
2021/11/15
|
Documento
|
|
Motion Submitting Quarterly Report on Federal Funding Activities
Asunto: Submission of Quarterly Report on Federal Funding Activities
|
15/noviembre/2021
|
2021/11/15
|
Documento
|
|
Motion to Submit Fourth Group of Generation Projects
Asunto: Motion to Submit Fourth Group of Generation Projects
|
15/noviembre/2021
|
2021/11/15
|
Documento
|
|
Motion to Submit Third Group of Generation Projects Initial SOWs
Asunto: Motion to Submit Third Group of Generation Projects Initial SOWs
|
08/noviembre/2021
|
2021/11/08
|
Documento
|
|
Resolution and Order
Asunto: Motion to Submit Updated List of Project and Thirty-Eight Scopes of Work
|
18/octubre/2021
|
2021/10/18
|
Documento
|
|
Resolution and Order
Asunto: Evaluation of Projects in Buildings of August 30 Motion
|
14/octubre/2021
|
2021/10/14
|
Documento
|
|
Motion Submitting Update List of Transmission and Distribution Projects and Thirty-Eight Scopes of Work
Asunto: Copy of 2021-10-04_Exhibit1_UpdatedProjectList
|
05/octubre/2021
|
2021/10/05
|
Documento
|
|
Motion Submitting Update List of Transmission and Distribution Projects and Thirty-Eight Scopes of Work
Asunto: Motion to Submit Update List of Project and Thirty-Eight Scopes of Work
|
04/octubre/2021
|
2021/10/04
|
Documento
|
|
Resolution and Order
Asunto: LUMA Request for Continuance of Technical Conference
|
29/septiembre/2021
|
2021/09/29
|
Documento
|
|
Resolution and Order
Asunto: Motion to Submit Second Group of Generation Projects Initial SOWs
|
28/septiembre/2021
|
2021/09/28
|
Documento
|
|
Motion for Continuance of Technical Conference
Asunto: Request for Continuance of Technical Conference
|
28/septiembre/2021
|
2021/09/28
|
Documento
|
|
Resolution and Order
Asunto: Motion Requesting Clarification, Submitting Update List of Transmission and Distribution Projects and Twenty-Nine Scopes of Work
|
22/septiembre/2021
|
2021/09/22
|
Documento
|
|
Motion Submitting September 2021 Update to PREPA-LUMA 90 Day Plan
Asunto: Motion Submitting September 2021 Update to PREPA-LUMA 90 Day Plan
|
21/septiembre/2021
|
2021/09/21
|
Documento
|
|
Resolution and Order
Asunto: Motion to Submit Generation Projects Initial SOWs
|
08/septiembre/2021
|
2021/09/08
|
Documento
|
|
Motion to Submit Second Group of Generation Projects Initial SOWs
Asunto: Motion to Submit Second Group of Generation Projects Initial SOWs
|
07/septiembre/2021
|
2021/09/07
|
Documento
|
|
Resolution
Asunto: Motion Requesting Clarification of a Portion of the Energy Bureau’s August 20, 2021 Resolution
|
31/agosto/2021
|
2021/08/31
|
Documento
|
|
Motion Requesting Clarification of a Portion of the Energy Bureau’s Resolution and Order Entered on August 20, 2021 and Submitting Updated List of Transmission and Distribution Projects and Twenty-Nine Scope of Work
Asunto: Exhibit 2_29-SOWs-Combined
|
30/agosto/2021
|
2021/08/30
|
Documento
|
|
Motion Requesting Clarification of a Portion of the Energy Bureau’s Resolution and Order Entered on August 20, 2021 and Submitting Updated List of Transmission and Distribution Projects and Twenty-Nine Scope of Work
Asunto: Exhibit1_UpdatedProjectList
|
30/agosto/2021
|
2021/08/30
|
Documento
|
|
Motion Requesting Clarification of a Portion of the Energy Bureau’s Resolution and Order Entered on August 20, 2021 and Submitting Updated List of Transmission and Distribution Projects and Twenty-Nine Scope of Work
Asunto: Request for Clarification of a Portion of the Energy Bureau’s Resolution and Order Entered on August 20, 2021 and Submission of Updated List of Projects and […]
|
30/agosto/2021
|
2021/08/30
|
Documento
|
|
Motion to Submit Generation Projects Inicial SOWS
Asunto: Motion to Submit Generation Projects Initial SOWs
|
20/agosto/2021
|
2021/08/20
|
Documento
|
|
Motion to Submit Generation Projects Initial Sows
Asunto: Motion to Submit Generation Projects Initial Sows
|
20/agosto/2021
|
2021/08/20
|
Documento
|
|
Resolution and Order
Asunto: Motion submitting List of Projects and Twenty-Eight Scopes of Work; Motion Submitting Amended List of Projects
|
20/agosto/2021
|
2021/08/20
|
Documento
|
|
Motion in Compliance with Order Entered on August 9, 2021
Asunto: Motion in Compliance with Order Entered on August 9, 2021
|
11/agosto/2021
|
2021/08/11
|
Documento
|
|
Resolution and Order
Asunto: PREPA’s Request for Technical Conference
|
09/agosto/2021
|
2021/08/09
|
Documento
|
|
Request to Set Aside Order and for Cancellation of Technical Conference
Asunto: Request to Set Aside Order and for Cancellation of Technical Conference
|
08/agosto/2021
|
2021/08/08
|
Documento
|
|
Resolution and Order
Asunto: PREPA’s Request for Technical Conference
|
06/agosto/2021
|
2021/08/06
|
Documento
|
|
Request for Technical Conference to Update the Energy Bureau on the Status of Generation Projects and FEMA Section 404 Hazard Mitigation Grant Program
Asunto: Request for Technical Conference to Update the Energy Bureau on the Status of Generation Projects and FEMA Section 404 Hazard Mitigation Grant Program
|
03/agosto/2021
|
2021/08/03
|
Documento
|
|
Motion Submitting Corrected LUMA Presentation at Technical Conference of July 11, 2021 and Requesting Appovals of Matters Presented and Proposed During the Technical Conference
Asunto: Submission of Corrected LUMA Presentation at Technical Conference of July 11, 2021 and Request for Approvals of Matters Presented during the Technical Conference
|
16/julio/2021
|
2021/07/16
|
Documento
|
|
Motion Submitting LUMA’s Presentation for Technical Conference of July 12, 2021
Asunto: LUMA’s Presentation for Technical Conference of July 12, 2021
|
09/julio/2021
|
2021/07/09
|
Documento
|
|
Joint Motion Submitting Redline Version of Update 10-Year Infrastructure Work Plan
Asunto: Joint Motion Submitting Redline Version of Update 10-Year Infrastructure Work Plan
|
09/julio/2021
|
2021/07/09
|
Documento
|
|
Motion Submitting Amended List of Projects
Asunto: Corrected Exhibit 1 – Updated Project
|
09/julio/2021
|
2021/07/09
|
Documento
|
|
Motion Submitting Amended List of Projects
Asunto: Submission of Amended List of Projects
|
09/julio/2021
|
2021/07/09
|
Documento
|
|
Motion Submitting List of Projects and Twenty-Eight Scopes of Work
Asunto: Exhibit 2 SOWs-Combined
|
08/julio/2021
|
2021/07/08
|
Documento
|
|
Motion Submitting List of Projects and Twenty-Eight Scopes of Work
Asunto: Exhibit 1 Motion Submitting List of Projects
|
08/julio/2021
|
2021/07/08
|
Documento
|
|
Motion Submitting List of Projects and Twenty-Eight Scopes of Work
Asunto: Submission if List of Projects and Scopes of Work
|
08/julio/2021
|
2021/07/08
|
Documento
|
|
Joint Motion Submitting Updated 10-Year Infrastructure Work Plan
Asunto: Joint Motion Submitting Updated 10-Year Infrastructure Work Plan
|
06/julio/2021
|
2021/07/06
|
Documento
|
|
LUMA’s Request for Relief from July 6th Deadline for Filing Detailed Scopes of Work
Asunto: Request for Relief from July 6th Deadline for Filing Detailed Scopes of Work
|
06/julio/2021
|
2021/07/06
|
Documento
|
|
Resolution and Order
Asunto: Technical Conference
|
02/julio/2021
|
2021/07/02
|
Documento
|
|
Motion in Compliance with June 8th Resolution Order and Request for Technical Workshop
Asunto: Motion in Compliance with June 8th Resolution Order and Request for Technical Workshop
|
15/junio/2021
|
2021/06/15
|
Documento
|
|
Resolución Nunc Pro Tunc
Asunto: Motion in Compliance with Resolution and Order Entered on April 22, 2021.
|
11/junio/2021
|
2021/06/11
|
Documento
|
|
Notice of Appearance and Request for Notice
Asunto: Notice of Appearance and Request for Notice
|
08/junio/2021
|
2021/06/08
|
Documento
|
|
Resolution and Order
Asunto: Motion in Compliance with Resolution and Order Entered on April 22, 2021
|
08/junio/2021
|
2021/06/08
|
Documento
|
|
Resolution and Order
Asunto: PREPA Requests for Extension to Comply with the April 22, 2021 Order
|
08/junio/2021
|
2021/06/08
|
Documento
|
|
Request for Extension of Time to Submit Information in Compliance with the April 22, 2021 Order
Asunto: Request for Extension to Comply with the April 22 Order
|
20/mayo/2021
|
2021/05/20
|
Documento
|
|
Motion in Compliance with the Resolution and Order Entered on April 22, 2021
Asunto: Motion in Compliance with March 26 Order
|
04/mayo/2021
|
2021/05/04
|
Documento
|
|
Motion in Compliance with the Resolution and Order Entered on April 22, 2021
Asunto: Motion in Compliance with March 26 Order
|
28/abril/2021
|
2021/04/28
|
Documento
|
|
Resolution and Order
Asunto: Evaluation of PREPA’s Motion Compliance with the Resolution and Order Entered on March 26, 2021
|
22/abril/2021
|
2021/04/22
|
Documento
|
|
Motion in Compliance with Resolution and Order Entered on March 26, 2021
Asunto: Motion in Compliance with March 26 Order
|
14/abril/2021
|
2021/04/14
|
Documento
|
|
Resolution and Order
Asunto: PREPA’s Revised 10-Year Plan Evaluation
|
26/marzo/2021
|
2021/03/26
|
Documento
|
|
Motion Submitting March 2021 Revised 10 Year Infrastructure Plan
Asunto: Motion Submitting March 2021- Revised 10-Year Infrastructure Plan
|
19/marzo/2021
|
2021/03/19
|
Documento
|
|
REply to PREPA’s Response to LEO’s Opposition Re: Approval of 10-Year Infrastructure Plan
Asunto: PREPA’s 10-Year Infrastructure Plan
|
18/marzo/2021
|
2021/03/18
|
Documento
|
|
Response to the Local Environmental Organizations Opposition to PREPA’s Motion Seeking PREB Approval of 10 Year Infrastructure Plan
Asunto: PREPA’s Response to Order entered on March 3, 2021
|
09/marzo/2021
|
2021/03/09
|
Documento
|
|
Resolution
Asunto: Resolution conceding a term for the Puerto Rio Electric Power Authority to submit its response to the Local Environmental Organizations’ Opposition to Revised 10-Year Infrastructure Plan
|
03/marzo/2021
|
2021/03/03
|
Documento
|
|
Opposition to PREPA’s Motion Seeking PREB Approval of 10 Year Infrastructure Plan
Asunto: PREPA’s 10 Year Infrastructure Plan with Attachments
|
02/marzo/2021
|
2021/03/02
|
Documento
|
|
Opposition to PREPA’s Motion Seeking PREB Approval of 10 Year Infrastructure Plan
Asunto: PREPA’s 10 Year Infrastructure Plan
|
02/marzo/2021
|
2021/03/02
|
Documento
|
|
Response to Resolution and Order Entered on January 25, 2021 and Request for Approval of Revised 10 Year Infrastructure Plan
Asunto: Response to Resolution and Order entered on January 25, 2021
|
16/febrero/2021
|
2021/02/16
|
Documento
|
|
Resolution and Order
Asunto: Notice of Appearance and Request for Notice
|
29/enero/2021
|
2021/01/29
|
Documento
|
|
Notice of Appearance and Request for Notice
Asunto: Notice of Appearance on behalf of the Puerto Rico Electric Power Authority
|
26/enero/2021
|
2021/01/26
|
Documento
|
|
Resolution and Order
Asunto: Determination on alignment with the Approved Integrated Resources Plan and Modified Action Plan
|
25/enero/2021
|
2021/01/25
|
Documento
|